Tuesday, 19, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Rsa No.263/2024 vs Kuldeep Chauhan
2025 Latest Caselaw 706 HP

Citation : 2025 Latest Caselaw 706 HP
Judgement Date : 9 May, 2025

Himachal Pradesh High Court

Rsa No.263/2024 vs Kuldeep Chauhan on 9 May, 2025

2025:HHC:13579

IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA RSA No.263/2024.

Date of Decision: 09th May, 2025.

The Managing Director & Anr. .....Appellants.

                              Versus

      Kuldeep Chauhan                                                .....Respondent.
      Coram

The Hon'ble Mr. Justice Bipin Chander Negi, Judge.

Whether approved for reporting?1

For the Appellants: Mr. Durga Singh Kainthla, Advocate.

For the Respondents: Mr. P.S. Goverdhan, Sr. Advocate with Mr. Rakesh Thakur, Advocate, for the respondent.

Bipin Chander Negi, Judge (oral).

The Appellant, by filing this appeal under section 100 of

the Code of Civil Procedure (for short, CPC), has assailed the

judgement and decree dated 28.02.2023 passed by District

Judge, Solan, in Civil Appeal No. 43-S/13 of 2022 whereby

Appeal filed by the Appellants against the Judgement and

Decree dated 20.12.2019 passed by the learned Civil Judge

Court No. 1, Solan in Civil Suit No. 53/1 of 2016 was partly

allowed.

2. The parties shall hereinafter be referred to as "plaintiff"

and "defendants" in accordance with their status before the trial

Court. The facts leading up to the present appeal are that the

plaintiff's case, as set out in the plaint, is that a contract for

felling and conversion of 532 trees comprised in Lot No.5/2012-

13 (Rajgarh HL), engraving and haulage of forest produce,

Whether reporters of Local Papers may be allowed to see the judgment? YES

2025:HHC:13579

carriage, and dispatch up to the roadside depot in Forest

Division Rajgarh was awarded to him by the Himachal Pradesh

Forest Development Corporation, Shimla, through the Divisional

Manager, vide agreement dated 10.2.2012. The plaintiff

executed the contract as per its terms and conditions to the

satisfaction of defendants No.3 and 4. Upon completion of the

work, he submitted his bills to defendant No.4 for payment, but

an amount of ₹39,094/- was deducted as "extension fee,"

despite the plaintiff never having applied for an extension of

time to complete the work.

3. The plaintiff contends that when he visited the site after

being assigned the work, he found that the trees to be felled

and converted were not marked with any hammer or khudan

marks, making them unidentifiable and rendering the execution

of the work practically impossible. He made representations to

the Divisional Manager, Forest Division, Solan (D-4), following

which a joint inspection was conducted by a team from the

Forest Department and the Forest Development Corporation,

and the trees were re-enumerated. Only after this was the

plaintiff able to fell and convert the trees and transport the

forest produce to the roadside depot. The plaintiff argues that

the defendants were not entitled to deduct any amount for

delayed execution, as the delay was caused by their failure to

properly mark the trees. He seeks recovery of ₹39,094/- along

with interest at 16% per annum from the defendants.

2025:HHC:13579

4. Defendants No.3 and 4, in their joint written statement,

admit the execution of the agreement but contest the suit on

preliminary objections regarding maintainability, cause of

action, valuation, and jurisdiction. On merits, they deny the

plaintiff's allegations and assert that the plaintiff informed them

about the unmarked trees only after six months of the work

being awarded. They argue that the delay in completion was

attributable to the plaintiff, and under Clause 12(b) of the

agreement, they were entitled to deduct an extension fee at 1%

per month of the contract value for the leftover work. They

maintain that the deduction was lawful and pray for the

dismissal of the suit.

5. Defendants No.1 and 2 (State of H.P. and Secretary,

Forest) did not file a separate written statement but adopted

the defence of defendants No.3 and 4. In his replication, the

plaintiff denies that he informed the authorities about the

unmarked trees only after six months. He reiterates that the

work could not commence on time due to the absence of

markings, making the trees unidentifiable.

6. The trial court framed the following issues on 3.5.2017:

1. Whether the plaintiff is entitled to recovery of ₹49,976/- along with future interest @ 16% per annum, as prayed for? OPP.

2. Whether the suit is not maintainable in the present form, as alleged? OPD

3. Whether the plaintiff has no cause of action to file the present suit, as alleged? OPD

4. Whether the plaintiff has not come to court with clean hands and has suppressed material facts from this court, as alleged? OPD

2025:HHC:13579

5. Whether the suit has not been properly valued for the purpose of court fee and jurisdiction, as alleged? OPD

6. Whether this court has no jurisdiction to try and decide the present suit, as alleged? OPD

7. Whether the plaintiff is estopped by his own act, conduct, deeds, admissions, omissions, and acquiescence from filing the present suit, as alleged? OPD

8. Whether the suit is bad for misjoinder and non- joinder of parties, as alleged? OPD.

9. Whether the suit is not within limitation, as alleged? OPD

10. Whether the suit is bad for want of better particulars, as alleged? OPD

11. Relief

7. After recording evidence and hearing the parties, the

trial court held that the plaintiff could not adhere to the

stipulated time period due to the defendants' failure to mark

and identify the trees. The fault lay with defendants No.3 and 4,

and they were not entitled to deduct any amount for delayed

execution. Accordingly, the trial court decided Issue No.1 in

favor of the plaintiff and the remaining issues against the

defendants, decreeing the suit for ₹49,976/- with interest at 6%

per annum from the date of the suit till realization.

8. Aggrieved by this judgment and decree dated

20.12.2019, defendants No.3 and 4 filed a first appeal. The

grounds of appeal stated that the trial court failed to appreciate

the evidence correctly and overlooked the fact that the plaintiff

did not comply with the agreement's terms within the stipulated

time. The plaintiff did not initiate work for six months and only

later raised the issue of unmarked trees. Despite this, the

defendants accommodated his request by re-enumerating the

trees. The appellants argued that under Clause 12(b) of the

2025:HHC:13579

agreement, they were entitled to deduct the extension fee for

the delay and that the trial court's decision is erroneous.

9. The first appellate court partly allowed the appeal of

defendants No.3 and 4. The decree passed by the trial court

was partly modified and the suit was decreed to the following

effects:-

(a) Plaintiff was held entitled to recover amount of ₹ 39,094/- with pre-suit interest at the rate of 6% per annum from July 2014 till filing of suit i. e.21.4.2016.

(b) The plaintiff was further held entitled to recover the principal so adjudged [i.e. ₹ 39,094/- plus pre-suit interest component as awarded vide (a) above], with interest at the rate of 6 % from the date of suit till realization.

(c) The rest of the suit was decreed against

10. Against the aforesaid modification in the judgement &

decree of the trial court no further appeal had been preferred by

the plaintiff. Aggrieved by the impugned judgment and decree,

the defendant has filed this second appeal.

11. Perused the impugned judgment and heard counsels for

the parties.

12. Upon careful consideration of the material on record and

the submissions advanced, this Court finds that the two courts

below have concurrently and correctly held that while there was

no dispute regarding the allotment of work in 2011, the

defendant's own witness admitted that hammering and marking

of trees was done only on 20.10.2012, after which the plaintiff

commenced work in November 2012. The defendant's primary

contention that the work was not completed within the

2025:HHC:13579

stipulated time stands rebutted by the evidence on record,

which clearly establishes that the delay was attributable to the

defendant's failure to provide proper tree markings.

13. The contention raised by the learned counsel for

defendants No.3 and 4 regarding excessive pre-suit interest was

found to be reasonable and well-founded by the courts below. A

cumulative sum of Rs.39,094/- was retained by defendants

No.3 and 4 as extension fee and security. The plaintiff,

however, claimed a principal amount of Rs.49,976/- as on the

date of the suit by including interest calculated at 16% per

annum, as evident from para-No.7 of the plaint. Since the

agreement Ex.PW1/A did not stipulate any interest rate payable

on dues, the plaintiff was held to be entitled to interest only at a

reasonable rate on the amount found due by both the Courts. I

see no infirmity in the same.

14. In the aforesaid facts and attending circumstances,

there arises no question of law, much-less a substantial

question of law for consideration of the Court, therefore, the

appeal is dismissed being devoid of any merit. Pending

miscellaneous applications, if any, also stand disposed of.

(Bipin Chander Negi) Judge

09th May, 2025 (T.B/Gaurav Rawat)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter