Tuesday, 19, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The State Of Madhya Pradesh vs M/S Mohanlal Heeralal Construction ...
2026 Latest Caselaw 2647 MP

Citation : 2026 Latest Caselaw 2647 MP
Judgement Date : 17 March, 2026

[Cites 11, Cited by 0]

Madhya Pradesh High Court

The State Of Madhya Pradesh vs M/S Mohanlal Heeralal Construction ... on 17 March, 2026

                                                                1

                                                                                      AA No. 16 of 2016

                                  IN THE HIGH COURT OF MADHYA PRADESH
                                               AT JABALPUR
                                                           BEFORE
                                          HON'BLE SHRI JUSTICE VIVEK JAIN

                                           ARBITRATION APPEAL No. 16 of 2016

                                         THE STATE OF MADHYA PRADESH AND OTHERS
                                                              Versus
                                    M/S MOHANLAL HEERALAL CONSTRUCTION COMPANY
                           .........................................................................................................
                           Appearance:

                                 Shri Mukund Agrawal - Govt. Advocate for the appellant / State.

                                 Shri Ram Chandra Somani - Advocate for the respondent
                           [CAVEAT].

                           ..........................................................................................................

                                                       JUDGMENT

(Reserved on 26.02.2026) (Pronounced on 17.03.2026)

The present appeal under Section 37 of Arbitration and Conciliation

Act, 1996 ( for short 'Act of 1996') has been filed arising out of the order

passed by the District Judge, Hoshangabad dated 01.12.2015 thereby

rejecting application under Section 34 of Act of 1996 against the award

passed by the sole arbitrator dated 01.11.2014. The arbitrator has given an

award of Rs.51,05,085/- for disputes arising between the parties in

connection to work of completion of incomplete works of railway

overbridge Itarsi, District Hoshangabad.

2. The counsel for the appellant-state has vehemently argued that the

impugned order passed by the District Judge rejecting the application under

Section 34 deserves to be set aside and the award was also liable to be set

aside and the District Court has erred in not setting aside the award for

which sufficient grounds were made out under Section 34 of Act of 1996.

Primarily it is argued that since the matter related to works contract,

therefore, in view of judgement of the Hon'ble Supreme Court in case of

M.P. Rural Road Development Authority v. L.G. Chaudhary Engineers

and Contractors, (2018) 10 SCC 826, the matter was cognizable by MP

Arbitration Tribunal constituted under M.P. Madhyastham Adhikaran

Adhiniyam, 1983 and the sole arbitrator could not have been appointed in

the present case. It is therefore argued that the award has been passed by

the arbitrator who was not having any jurisdiction in the matter.

3. The counsel for the State further argued that the contractor had failed

to approach the Superintending Engineer and the arbitration was

maintainable only after having decision of the Superintending Engineer and

after rejection of the claim by Superintending Engineer appeal ought to

have been filed before the Chief Engineer and therefore arbitration was not

maintainable as per clause 1.17 of the contract agreement. On merits also, it

is argued that no escalation could be awarded by the Tribunal and further

that the claims allowed by the arbitrator are extremely exorbitant and

unsustainable. Therefore, the award is criticized basically on the ground of

jurisdiction, on merits of the claims as well as the party not approaching the

Superintending Engineer.

4. So far as the jurisdiction aspect is concerned, it is not in dispute that

the party had first approached the MP Arbitration Tribunal constituted

under Adhiniyam 1983 and the MP Arbitration Tribunal rejected the

reference petition of the contractor as it did not have jurisdiction in the

matter and therefore, the contractor approached this Court in Arbitration

Case No.70 of 2010 and this Court then appointed a sole arbitrator vide

order dated 18.08.2011.

5. Though it cannot be doubted in view of judgement in the case of

L.G. Chaudhary (Supra) that the matter is cognizable before the M.P.

Arbitration Tribunal, but in this case the arbitrator had been appointed

when the earlier view of the Hon'ble Supreme Court was prevailing in the

case of VA Tech Escher Wyass Flovel Ltd. v. M.P. SEB, (2011) 13 SCC

261. Thereafter, the foresaid judgement was doubted in M.P. Rural Road

Development Authority v. L.G. Chaudhary Engineers & Contractors,

(2012) 3 SCC 495 and on some point there was difference of opinion and

ultimately in the judgement of L.G. Chaudhary (2) rendered in the year

2018 the curtains were drawn and now it is undisputed that matters

concerning works contract awarded by the Engineering Departments of the

State of Madhya Pradesh have to be raised before the MP Arbitration

Tribunal.

6. However, in the present case, the contractor initially approached the

said Tribunal as far back as in the year 2004 and then the Tribunal rejected

the reference proceedings on the ground of maintainability. Such issue has

been considered by the Hon'ble Apex Court in the case of Modern

Builders v. State of M.P., (2024) 10 SCC 637 and it has been held that in

such cases it would be unjust to set aside the award because the arbitrator

had been appointed much prior to the judgement in the case of L.G.

Chaudhary (Supra). The Hon'ble Supreme Court held as under:-

7. The order dated 22-7-2011 passed by the High Court on the said petition shows that the respondents' opposition was only on the merits of the claim. The objection based on the applicability of the 1983 Act was not raised. The respondents did not challenge the order of appointment of the arbitrator passed by the High Court under Section 11(6) of the Arbitration Act. Even before the learned arbitrator, Section 16(1) of the Arbitration Act was not invoked to raise the jurisdiction issue. However, in the written statement filed before the arbitrator, the contention regarding the applicability of the 1983 Act was raised.

xx xx xx

9. As noted earlier, in the facts of the case, before taking recourse to the Arbitration Act, the appellant had taken recourse to Section 7 of the 1983 Act. The order of the Arbitration Tribunal, holding that the Arbitration Act will apply, led the appellant to file a petition under Section 11(6) of the Arbitration Act, which was not objected to on the grounds of the applicability of the 1983 Act. The objection of the State Government was confined to the merits of the claim. The award is only in the sum of Rs 6,52,235 with interest. The award was made on 25-4-2014. Therefore, in the facts of the case, it will be unjust to set aside the award only on the ground of the failure of the appellant to take recourse to the 1983 Act. In fact, the

appellant had taken recourse to the 1983 Act before seeking the appointment of an arbitrator.

7. So far as the other objection regarding dispute not having been raised

before the Superintending Engineer and arbitration proceedings instituted

without prior adjudication of the Superintending Engineer is concerned, it

was contended by the applicant before the arbitrator that he had submitted

claim before the Superintending Engineer but no decision was taken by the

Superintending Engineer. The contractor had specifically contended that he

had approached the Superintending Engineer and this has not been disputed

by the Department. It was contended by the contractor in para-11 of his

reply before the District Judge in proceedings under section 34 that he has

submitted his claim on 20.11.2003 to the Superintending Engineer, Office

of Chief Engineer, Capital Zone Bhopal because there was no

Superintending Engineer, Hoshangabad circle between the period 1.7.1999

to 30.6.2006. This assertion could not be demolished by the learned counsel

for the State which is duly established from record and therefore, this Court

is of the opinion that the contractor had indeed approached the

Superintending Engineer prior to instituting the arbitration proceedings.

8. Furthermore, since in the present case arbitration had been instituted

prior to the amendment in the Act of 1996 carried out in the year 2015,

therefore, at that time the referral court while exercising jurisdiction under

Section 11(6) had some wider jurisdiction which has been restricted now

by the amendment of the year 2015.

9. If the dispute was non-arbitrable and appointment of arbitrator was

being sought under unamended Act, therefore objection to that effect ought

to have been raised before the referral Court by the State because reference

took place prior to the amendment

10. So far as merits of various claims are concerned, it is undisputed that

the jurisdiction of the appellate Court under Section 37 is not wider than

the jurisdiction as contained in Section 34 of Act of 1996. This Court would

not go into the merits of the case and not undertake accounting exercise

which the arbitrator had to undertake on merits of the claim. No

fundamental flaw in the quantification exercise carried out by the arbitrator

could be pointed out by the learned counsel for the State before this Court.

11. In view of the aforesaid, this Court is of the opinion that no

interference needs to be caused in the impugned order passed by the

District Court under section 34 of Act of 1996.

12. Consequently, the appeal fails and is dismissed.

(VIVEK JAIN) nks JUDGE

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter