Tuesday, 19, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Damodar Ropeways & Infra Ltd. ... vs Jammu & Kashmir State Cable Car ...
2024 Latest Caselaw 1620 j&K/2

Citation : 2024 Latest Caselaw 1620 j&K/2
Judgement Date : 25 October, 2024

Jammu & Kashmir High Court - Srinagar Bench

M/S Damodar Ropeways & Infra Ltd. ... vs Jammu & Kashmir State Cable Car ... on 25 October, 2024

Author: Chief Justice

Bench: Chief Justice

IN THE HIGH COURT OF JAMMU & KASHMIR AND LADAKH
                   AT SRINAGAR


                             Arb P No.50/2023

                                                  Reserved on :17.10.2024.
                                                Pronounced on: 25.10.2024.


M/s Damodar Ropeways & Infra Ltd. through its
Authorized Representative, Mr Partha Kumar, Son of
Late Gour Hari Kumar, Aged about 58 years, Having
its office at onstantia, Wing A, 11 Dr U N
Bhramachari Street Kolkata-700017.                          ...Petitioner(s).

Through:       Mr. Shariq J. Reyaz, Advocate.

                                     Vs.
 Jammu & Kashmir State Cable Car Corporation Ltd.
 through its Managing Director, Corporate Head
 Office Batmaloo Qamarwari Road, Near Bemina
 Woolen Mills, Srinagar, J&K-700017.              ....Respondent(s)

Through:       Mr. Faheem Nissar Shah, GA.

CORAM:
HON'BLE THE CHIEF JUSTICE


                             JUDGMENT

01. The instant petition has been filed by the petitioner seeking appointment of an arbitrator by invoking Section 11(6) of the Arbitration and Conciliation Act, 1996 (for short the 'Act').

02. The case set up by the petitioner is that being a Public Limited Company, was allotted the work "Design, Manufacture, Supply, Erection, Testing and Commissioning of Detachable Grip Monocable Ropeway from Mubarak Mandi to Mahamaya and Pulsated Ropeway from Mahamaya to Shahabad near Bagh-I-Bahur at Jammu, J&K". On acceptance of the tender document of the petitioner by the respondent, letter of acceptance dated 29.08.2012 was signed and entered between the parties and an agreement bearing No.JKSCCC/Jammu ROPEWAY/2014 dated 26 th May, 2014 was also executed interse parties. It is stated that the work on the

project commenced on 29th March, 2014 after a delay of nineteen months because of the reasons attributable to the respondent and the same was commissioned in the month of September, 2019. It is stated that despite successful commissioning of the project, the bills of the petitioner duly certified by the Project Management Consultants (RITES) have remained unpaid. While giving details of the bills, it is submitted that the bill certified by RITES on 20th April, 2021 to the tune of Rs.12,00,000/-, on 11th November, 2021 to the tune of Rs.2,09,08,800/- and another on 3rd January, 2022 to the tune of Rs.80,22,812/- totaling to Rs.3,01,31,612/- are unpaid. Besides, these bills the petitioner has furnished the details of the payments which the respondent owes to the petitioner. It is stated that despite numerous requests having been made for release of the due payments in favour of the petitioner, the respondent despite the repeated assurances has failed to release the payments to the petitioner. It is further stated that the respondent in fact on 24.02.2022 convened a tripartite meeting in which claims of the petitioner were considered but the said meeting was not taken to its logical conclusion. The petitioner, therefore, being dissatisfied with the omissions of the respondent, invoked the arbitration clause contained in the agreement by serving a notice dated 17.10.2023 and subsequently filed the present petition before this Court on 27th December, 2023.

03. On notice of the petition to the respondent, the respondent appeared and filed his objections to the petition. In the objections, amongst other grounds, the respondent has disputed the claim of the petitioner on the ground that the claim raised by the petitioner is time barred. It has further been pleaded in the objections that the petitioner has approached the Court directly without seeking reference of the dispute under Section 21 of the Act, which is against the mandate as laid down by the Hon'ble Supreme Court in catena of judgments.

04. Heard learned counsel for the parties.

05. After having heard learned counsel for the parties and while going through the rival contentions of the parties, the issues which arise for consideration of this court are that whether the petition is barred by limitation and whether the petitioner has directly approached this Court

without seeking reference of the disputes to arbitration in terms of Section

06. It is settled position of law that limitation period for making an application under Section 11(6) of the Act, 1996, is three years from the date when the right to apply accrues. In the present case, as can be seen from the records, one of the bills/invoices submitted by the petitioner on 27.12.2021 to the tune of Rs.8022,812/- has been verified by the RITES being the Project Management Consultants, on 3 rd January, 2022. Thereafter, on 24.02.2022 a tripartite meeting between the petitioner, respondent and RITES was also convened with regard to the claims of the petitioner in relation to the subject contract, however, the said meeting is stated to have not been taken to its logical conclusion.

07. After perusal of the aforesaid documents, it becomes crystal clear that the claims raised by the petitioner with the respondent were under active consideration and finally when the respondent failed to release the payment, the petitioner served a notice dated 17 th October, 2023 under Section 21 of the Act upon the respondent seeking reference of the dispute to an arbitrator. The respondent having failed to refer the matter to arbitration, the petitioner filed the present petition under Section 11(6) of the Act on 27.12.2023. Thus, it is evident that the present petition is in no way barred by limitation and the same is held to be within time.

08. As observed above, the petitioner before seeking indulgence of this Court in terms of Section 11(6) of the Act, served notice dated 17th October, 2023 upon the respondent seeking invocation of arbitration under Clause 25 of the General Conditions of Contract in terms of Section 21 of the Act. Therefore, the objection raised by the respondent that petitioner has directly approached this Court without complying with the provisions of Section 21 of the Act is without any basis and is, as such, turned down.

09. In view of the aforesaid facts and circumstances as despite invocation of the arbitration clause, the request of the petitioner has not been acceded to, it is considered to be a fit case where the arbitrator is required to be appointed by this Court. Accordingly, Mr. Justice Mansoor Ahmad Mir, Retd. Chief Justice of Himachal Pradesh High Court, Resident of Canal Avenue Sector-C Old Airport Road, Srinagar (Mob.

No.9419000993), is appointed as the sole arbitrator who shall proceed in the matter in accordance with the provisions of the Act to make an award within the time provided in the Act itself after charging the prescribed fee along with incidental expenses to be shared by the parties.

10. The Petition is, accordingly, disposed of and the learned Arbitrator be informed accordingly.

(TASHI RABSTAN) Chief Justice Srinagar 25.10.2024 Abdul Qayoom, Secy.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter