Tuesday, 19, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Mangal Rubber Products Pvt. Ltd vs Executive Engineer(O And M)
2024 Latest Caselaw 154 Guj

Citation : 2024 Latest Caselaw 154 Guj
Judgement Date : 8 January, 2024

Gujarat High Court

Mangal Rubber Products Pvt. Ltd vs Executive Engineer(O And M) on 8 January, 2024

Author: Sunita Agarwal

Bench: Sunita Agarwal

                                                                                   NEUTRAL CITATION




      C/LPA/1481/2023                              ORDER DATED: 08/01/2024

                                                                                   undefined




            IN THE HIGH COURT OF GUJARAT AT AHMEDABAD

               R/LETTERS PATENT APPEAL NO. 1481 of 2023
            In R/SPECIAL CIVIL APPLICATION NO. 10091 of 2010

                                   With

                CIVIL APPLICATION (FOR STAY) NO. 1 of 2023
               In R/LETTERS PATENT APPEAL NO. 1481 of 2023
==========================================================
                    MANGAL RUBBER PRODUCTS PVT. LTD.
                                 Versus
                      EXECUTIVE ENGINEER(O AND M)
==========================================================
Appearance:
MR ADIL R MIRZA(2488) for the Appellant(s) No. 1
for the Respondent(s) No. 1,2
==========================================================

 CORAM:HONOURABLE THE CHIEF JUSTICE MRS. JUSTICE
       SUNITA AGARWAL
       and
       HONOURABLE MR. JUSTICE ANIRUDDHA P. MAYEE

                             Date : 08/01/2024

                              ORAL ORDER

(PER : HONOURABLE THE CHIEF JUSTICE MRS. JUSTICE SUNITA AGARWAL)

1. Heard learned counsel for the appellant and perused

the record.

2. The instant appeal is directed against the judgment

and order dated 03.08.2023 passed by the learned Single

Judge, whereby the writ petition filed by the Electricity

Department seeking to challenge the order passed by the

NEUTRAL CITATION

C/LPA/1481/2023 ORDER DATED: 08/01/2024

undefined

Appellate Authority dated 27.01.2010 in Appeal No.02/1009-

1010 vide Order No.NAMVN/TPS/APPEAL/627 27-1-

2010/2010 has been allowed. While quashing the order

passed by the Appellate Authority, it is recorded by the

learned Single Judge that undisputed facts arising for

adjudication in the writ petition are that the respondent No.1

- appellant herein, is having electricity connection of 180 KV

for plot No.308 only. The said fact is evident from the details

in the application wherein power supply was required for plot

No.308, GIDC, Gundlav, Valsad. The electricity authority, on

an inspection of the premises found that the respondent No.1

had extended the usage of electricity beyond what was

applied for and supplied to him. Supplementary bill dated

01.05.2009 to the tune of Rs.6,14,215.78 had, thus, been

issued to the respondent. Further recording the provisions of

the Electricity Supply Code and Related Matters Regulations

and the decision of the Division Bench of this Court in Letters

Patent Appeal No.1368 of 2018 dated 16.07.2021, it was

noticed by the learned Single Judge that as per the provisions

of the Electricity Act, 2003 and the Electricity Supply Code

NEUTRAL CITATION

C/LPA/1481/2023 ORDER DATED: 08/01/2024

undefined

made thereunder, the applicant is required to apply for

supply of electricity in Form A-1 under Section 50 of the

Electricity Act, 2003. The respondent No.1 / appellant

herein, had applied for H.T. supply for electricity for plot

No.308, on the Form appended at page No. '39' as

Annexure-'E' to the writ petition to the writ petition and the

relevant column No.5 only mention was of plot No.308, GIDC,

Gundlav, Valsad.

3. The learned Single Judge has, thus, reached at the

opinion that with regard to the plot Nos. 309 and 310, the

extension of electricity connection granted by the department

for plot No.308, would fall within the ambit of unauthorised

use of electricity. It was, thus, concluded that when the

application seeking electricity connection-in-question, was for

plot No.308 and the same was considered by the Electricity

Department, the usage of plot Nos. 309 and 310 never

forming part of the said application, the act of the

department in raising supplementary bill for the said plot

cannot be said to be bad in law.

NEUTRAL CITATION

C/LPA/1481/2023 ORDER DATED: 08/01/2024

undefined

4. Assailing these findings returned by the learned

Single Judge, it is vehemently argued by the learned counsel

for the appellant that three plots namely plot Nos.308, 309

and 310 were finally allotted by GIDC to the appellant on

20.02.1988 and, thereafter, by getting the plan sanctioned

from GIDC, the construction of factory / manufacturing unit

along with other units was completed. The entire plan

sanctioned by GIDC was pertaining to three contiguous plots

namely plot Nos.308, 309 and 310 and the said plan was duly

placed before the electricity authority at the time of grant of

connection on 21.01.1989. The submission is that though the

electricity connection was applied in the prescribed form for

plot No.308 only, and was granted for that plot but in

principle, it was understood and agreed by the electricity

authority that the appellant would require electricity

connection for entire premises comprising of three plots

namely plot Nos. 308, 309 and 310.

5. The submission, thus, is that no fault can be attached

to the act of the petitioner in utilizing electricity connection

NEUTRAL CITATION

C/LPA/1481/2023 ORDER DATED: 08/01/2024

undefined

for the entire premises including the plot Nos. 309 and 310.

6. Further contention is that the reliance placed on the

decision of the Division Bench of this Court in Letters Patent

Appeal No. 1368 of 2018 is misplaced, inasmuch as, the fact

situation of the said case was completely different from the

present one. In the said case, the plots were allotted at

different point of time and the electricity connection granted

at an earlier point of time was extended to the subsequently

acquired / allotted plots. It is vehemently argued that the

present case cannot be said to be a case of unauthorized use

of electricity, inasmuch as, the petitioner has not supplied

electricity to any other person nor has extended it beyond the

premises wherein the factory / manufacturing unit was

established.

7. We find inherent fallacy in the arguments of the

learned counsel for the appellant, inasmuch as, there is no

dispute about the fact that the appellant, for the reasons best

known to it, had applied for electricity connection only for

one plot i.e. plot No.308 in the prescribed format, which was

NEUTRAL CITATION

C/LPA/1481/2023 ORDER DATED: 08/01/2024

undefined

placed on record of the writ petition. As was mentioned in

the application, the electricity connection was granted by the

department only with respect to plot No.308. The facts that

the plan for entire premises was sanctioned by the GIDC or

the same was before the Electricity Department or the

construction plan comprised two other plots namely plot

Nos.309 and 310 or that these three plots namely the plot

Nos.308, 309 and 310 are contiguous plots, are of no

relevance insofar as the electricity connection is concerned.

8. On a pointed query made by us, no explanation is

forthcoming as to why the appellant would not include two

other plots namely plot Nos.309 and 310 in the prescribed

format for seeking electricity connection when these three

plots were allotted and to be utilized for construction of the

entire manufacturing unit.

9. There was no occasion for the appellant not to

include the two plots Nos. 309 and 310 in the prescribed

format while applying for electricity connection. The

subsequent extension of electricity connection to the

NEUTRAL CITATION

C/LPA/1481/2023 ORDER DATED: 08/01/2024

undefined

premises constructed over plot Nos. 309 and 310 by the

petitioner is nothing but an act of unauthorized use of

electricity.

10. No infirmity, therefore, could be find in the findings

returned by the learned Single Judge. The Appeal is

dismissed being devoid of merit. Civil Application for stay as

well as any other pending application/s shall also stands

disposed of.

(SUNITA AGARWAL, CJ )

(ANIRUDDHA P. MAYEE, J.) AMAR SINGH

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter