Tuesday, 19, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Ap-Com 135 Of 2024 (Old Ap 698 Of 2016) vs Laxmi Pat Surana & Anr
2025 Latest Caselaw 2679 Cal/2

Citation : 2025 Latest Caselaw 2679 Cal/2
Judgement Date : 19 September, 2025

Calcutta High Court

Ap-Com 135 Of 2024 (Old Ap 698 Of 2016) vs Laxmi Pat Surana & Anr on 19 September, 2025

                                           1


              IN THE HIGH COURT AT CALCUTTA
                Ordinary Original Civil Jurisdiction
                         Original Side

Present: -     Hon'ble Mr. Justice Subhendu Samanta.

                     IN THE MATTER OF
           AP-COM 135 of 2024 (Old AP 698 of 2016)
                Future Market Networks Ltd.
                            Vs.
                     Laxmi Pat Surana & Anr.

For the Petitioner                  :    Mr. S.N. Mookherjee, Ld. Sr. Adv.,
                                         Mr. Rishad Medora, Adv.,
                                         Mr. Naman Chowdhury, Adv.,
                                         Ms. Pooja Chakrabarti, Adv.,
                                         Mr. Aritra Deb, Adv.,
                                         Mr. Sagniok Aditya, Adv.,


For the respondents             :        Mr. Laxmi Pat Surana (In person)

Reserved on                     :       07.03.2025

Judgment on                     :       19.09.2025


Subhendu Samanta, J.

1. This is an application u/s 34 of the Arbitration and Conciliation

Act, 1996 filed by Future Market Networks Limited, challenging

an award dated May 19th, 2016 passed by Learned sole

Arbitrator Mr. Syama Prosad Sarkar in an arbitration

proceeding between respondent Laxmipat Surana (claimant in

the arbitration) and predecessor in interest of the petitioner and

respondent No. 2 herein.

2. By filling the present application the petitioner has challenged

the award on 04 grounds. They are--

1. License fee for entire lock-in period i.e. August 11,

2008 to July 31, 2013 for a sum of Rs. 13,26,56,751.

2. Loss of interest on security deposit for a sum of Rs.

50,00,000; and loss of income on account of additional

license fees for a sum of Rs. 3,95,50,500.

3. Electricity charges for a sum of Rs. 14,68,762.

4. Water Charges for a sum of Rs. 11,70,000.

3. Petitioner also challenges the award to the extent that counter

claims of the petitioner for cost of diesel for a sum of Rs.

3,30,23,904/- and for infrastructure for a sum of Rs.

21,00,00,000/- having been allowed.

4. Submission by the petitioner on Point No. 1 :- Mr. S.N.

Mookherjee, Ld. Senior Advocate, for Petitioner contends

Learned Arbitrator has erroneously awarded the license fees for

entire lock-in period of 5 years, commencing from August 11,

2008 to July 31, 2013, for a sum of Rs. 13,26,56,751/-, when

in fact, license fees could only have been awarded for the period

of August 11, 2008 to March 2012 for a sum of Rs.

8,96,14,514/-as the possession of the premises was admittedly

given up by the Petitioner to the Claimant in April 2012.

Therefore, no loss could have been suffered by the Claimant

from April 2012 to July 31, 2013 and no damages could have

been awarded on such account. Thus, an excess amount of Rs.

4,30,42,237 has been awarded in the award on account of

license fees for the period April 2012 to July 31, 2013.

5. Mr. Mookherjee further contended agreement was terminated by

letter dated 31st October, 2011, such termination was accepted

by the respondent No. 1 by his letter dated December 19th,

2011, and the respondent No. 1 also exercised lien form of

goods and materials stored in the premises. Petitioner submits

that having received possession of the premises there cannot be

any loss suffered by claimant on account of license fee for

compliance lock in period being April 2012, to July 31 st, 2013.

6. Petitioner further submits, following termination of the

agreement, the Sub-Sub- licensees inducted by the petitioner

under Clause 17 of the supplementary agreement dated June

14th , 2008, were paying rent directly to the banker of

respondent No. 1 and such arrangement was accepted by the

claimant. The petitioner further submits no proof of damage

had been proved by the Respondent No. 1 in the instant case, in

fact, it was the finding of the Learned Arbitrator that claimant

received benefit in view of the fact that the sub-sub-licensees

were making direct payment to claimants banker. Petitioner

submits there is no finding in the Award that the Petitioner

suffered any damage. Thus, no liquidated damages could have

been awarded for such period where, in fact, no loss has been

pleaded or proved by the claimant. Petitioner submits Proof of

loss is a sine qua non for award of damages, whether liquidated

or unliquidated and the same also applies to agreements

containing a lock in period.

7. In support of his contention Mr. Mookherjee cited following

decisions of Hon'ble Supreme Court in :-

i) Kailash Associates Vs. Delhi Development

Authority & Anr. (2015) 4 SCC 136

ii) M/s. Auto Craft Engineers Vs. Akash

Automobiles Agencies Private Limited.

8. It is further argued by the petitioner that the award has

therefore been passed in ignorance of binding precedents and is

contrary to the fundamental policy of Indian Law and thus

liable to be set aside u/s 34(2)(b)(ii) of the Arbitration and

Conciliation Act, 1996.

9. In support of their contention petitioner cited following

decisions:-

i) Associate Builders Vs. Delhi Development

Authority (2015) 3 SCC 49

ii) Ssangyong Engineers Vs. National Highway

Authority of India (NHAI) (2019) 15 SCC 131

10. Submission of respondent (Laxmi Pat Surana in person) on

point No. 1:- Mr. Surana Submits that Learned Arbitrator has

awarded license fee for 5 years lock-in period clearly holding, in

paragraph 30 of the Award, that while issuing the termination

letter dated October 31, 2011 (page/348-350, Vol-3) the

Petitioner did not give 30 days written notice in terms of the

agreement and held that the said letter complaining the breach

was a peremptory termination. Mr. Surana submits the

admission of the Claimant's claim is neither perverse nor

patently illegal nor against the law laid down by the Superior

Court nor against the fundamental policy of Indian law nor

contrary to public policy of India nor suffers from the vice of

justice or morality nor against the contractual terms nor

contrary to the provisions of law. He submits claim has been

admitted by the Ld. Arbitrator with full application of mind. Mr.

Surana Submits Arbitrator is bound to respect the terms of the

contract, according to legal precedent, if a tenant breaks a lease

agreement during a lock-in period, the tenant is obligated to pay

the rent for the remaining period of the lock-in term, as the

"balance rent" is considered a pre-estimated loss by the

landlord. Mr. Surana submits this principle has been upheld by

several courts in the country and have also held that such a

clause in a lease agreement as a valid and enforceable.

Similarly, if a reasonable amount is contemplated by the parties

to be the compensation payable upon a breach of the

agreement, actual loss need not be proved.

11. In support of his contention Mr. Surana cited decision of

Hon'ble Supreme Court passed in ONGC VS. Shaw Pipes

(2003) 5 SCC 705.

12. Mr. Surana further submits that there are two types of damages

(a) Liquidated (b) Unliquidated. As per the crystallised legal

position, sum ascertained as liquidated damages in the contract

is not in the nature of penalty, but is a pre-estimate of loss

estimated by the parties likely to be suffered by a party in the

event of breach of contract by the other party. Mr Surana

further submits since the execution of the agreement is not in

dispute, the onus would be on the Petitioner to demonstrate

that the relevant clause providing for payment of license fee

(liquidated damages) in the event of the sub-licensee

determining the sub-license within the lock-in period, is a

penalty that would fall foul of the Contract Act, He argued- It

would be the Petitioner's obligation to establish what the

Respondent No.1 (Claimant) could have done to mitigate its

damages and the consequential reduction, if at all, of the

Petitioner's liability as to liquidated damages knowing fully well

that the Petitioner was admittedly in wrongful occupation of the

premises. Mr. Surana submits Learned Arbitrator has awarded

the license fee for the 5 year lock-in period as per agreed rate of

license fee between the parties stated in the agreement since the

termination letter, in accordance with paragraph 30 of the

Award, was not issued in accordance with the provisions of

agreement. Such claim being in the nature of liquidated

damages, the Claimant was not required to prove the same

more so when the Petitioner was admittedly in wrongful

occupation of the premises even after passing of an Interim

Award on 8th April, 2013 on an unequivocal consent of the

Petitioner to deliver vacant khas and peaceful possession of the

premises in terms of prayer (b) of the Claimant's application for

Interim Award. He argued Vacant khas and peaceful possession

was never delivered by the Petitioner, there is neither any

evidence nor any record on the Arbitral Tribunal for delivery of

possession. In terms of Clause 22 of the Agreement only vacant,

khas and peaceful delivery of possession is recognised.

13. Heard the Learned Counsel for the parties perused the written

notes of argument has placed by the parties. To justify the point

raised by the petitioner. It is required to be set out. Paragraph

30 and 31 of Arbitral award-

30. It is not difficult to appreciate as to why such a clause

was inserted in the agreement. A project of such

magnitude, as undertaken by the Claimant, contemplated

huge initial investment. It was, therefore, reasonable for

the Claimant to safeguard his interest to a reasonable

measure. Mr. Saha's argument to the effect that many a

warning and prior notice of Claimant's various breaches

had been served in the past, though true, cannot, in any

event, be viewed as compliance with requirement of Clause

31. Under the said Clause, unless a 30 day prior notice

was served on the Claimant licensor, in accordance with

provisions of Clause 31 of the agreement, complaining of

breach committed by the Claimant, giving an opportunity

to the latter to have the same rectified within the period,

the Respondents, in any event, remained liable to pay the

license fee for a period of 5 years rendering the

controversy over the actual tenure referred to above

irrelevant. In absence of such prior notice, the

Respondents remained liable to pay the license fees to the

Claimant for the entire period of 5 years, regardless of

termination at an earlier point of time.

I therefore, hold that the 5 years lock-in period was

attracted since the Respondent (PRIL) as sub-licensee did

not give to the licensee (the Claimant) 30 day written

notice of such breach giving an opportunity to the latter to

have the same rectified by end of the said notice period.

Letter dated 31st October, 2011 of the Respondents

complaining the breach was a peremptory termination.

14. The above observations of Learned Arbitrator has materialised

in paragraph 42 to 45 regarding calculation of license fee. The

paragraph 42 to 45 set out hereinunder for better appreciation.

42. On the basis of aforesaid discussion as to parameters

of calculating license fees; I hold that the Respondents

were liable to pay lease rent for the period from 11th

August, 2008 till termination of the agreement on 31st

October, 2011 i.e. 39 months for the total chargeable area

of 109021 sq. ft. in the sum of Rs.8,35,48,243.20 /-

calculated on the following basis:

a) License fee for 36 months @ Rs.19.50 per sq. ft. Rs.

7,65,32,742.00/-

b) License fee for 3 months @ Rs.21.45 per sq. ft. Rs.

70,15,501.20/-

                                   Total       liability         Rs.

      8,35,48,243.20/-

43. In course of his argument, Ld. Counsel for the

Respondents, however, conceded that his clients were

liable to be pay licence fees till March, 2012. This

submission, I presume, was made on the footing that

possession of scheduled premises not being made over to

the Claimant until say 14th April 2012. In the view I have

taken is, it cannot be correct. I have held earlier that the

liability to pay rent must ends on 31st October, 2011 when

the agreement was terminated. The Claimant was,

however, free to make claim on the basis of mesne profit,

should he had chosen to file a suit for eviction and mense

profit, but for the purpose of calculation of licence fees,

such possible claim has to be ignored.

44. However, having regard to the fact that the

Respondents terminated the agreement within the 5 years

lock-in period without serving a 30 day prior notice, as

required by Clause 31 of the agreement, the Claimant

would be entitled to the lease rent for residue of 5 year

lock-in period i.e. till 31st July, 2013 covering 21 months

calculated at the rate of Rs.21.45p. per sq. ft. Accordingly,

the Claimant would be entitled to an additional rent of

Rs.4,91,08,507.80/-.

45. In the premises, the total liability of the Respondents

for License fee was for a sum of Rs. 13,26,56,751/- (Rs.

8,35,48,243.20/- + 4,91,08,507.80/-).

15. Basic objection of the petitioner against the award for granting

license fee in the lock in period is that the claimant has not or

proved pleaded loss or damages suffered by him during such

lock in period. Hence the same cannot be awarded legally.

16. In Kailsah Nath Associates (supra), is a suit for specific

performance of contract, the Single Judge of High Court's order

of refund of earnest money on the ground that "respondent did

not suffer any loss" has reached to the Hon'ble Apex Court

wherein the Hon'ble Supreme Court has held that Set out

Paragraph 43,43.1.

17. In Kailsah Nath Associates (supra) the Hon'ble Supreme Court

in dealing with refund of earnest money by a bidder has

overruled the view of Hon'ble Division Bench who set aside the

order of Single Judge, holding the proof of loss is not required to

recover earner money. In dealing with such issues the Hon'ble

Supreme Court is of view that proof of loss has already been

proved as the respondent was sold the same land to the third

party at about three and half times price of estimated cost. In

the present case the agreement itself stipulates regarding 5

years lock- in period, both the parties are agreed about such

conditions, so in my view the fact situation of Kailsah Nath

Associates (supra) is not similar to that of the present

agreement between the parties.

18. In M/s Autocraft Engineers, an ex-party award passed by a

sole arbitrator was under challenge before Hon'ble Apex Court.

It is admitted by the parties in M/s Autocraft Engineers

(Supra) that award in lock in period in respect of the property in

question was already occupied by previous tenants. The

petitioner never took possession of the suit property for a single

day and evidence suggests that respondent suffered no loss

during the lock in period. The premises was already occupied by

the previous licensee who running the show room of Mahindra

Jeep and continued to occupy the said premises.

19. In the present case it has been pleaded by the petitioner that

Sub-Sub- licensees are in possession, after the petitioner has

vacated the premises; it has further been pleaded that such

Sub-Sub-licensees are directly paying rent to the banker of the

claimant. Such fact was not categorically admitted by the

Learned Arbitrator in the entire proceeding. I have gone through

the award impugned wherein the argument and submission of

the parties were recorded and it has been categorically admitted

that instead of interim award on 8th April 2013, petitioner could

not delivered vacant, khas and peaceful possession of the

premises to the claimants. Reasons are numerous but facts

suggests that the learned Arbitrator has held that as the

petitioner failed to terminate the agreement within 05 years lock

in period without serving 30 days prior notice, as required by

Clause 31 of the agreement, the Learned Arbitrator awarded

lease rent for entire 05 years lock in period.

20. Let me consider whether the observation of Learned Tribunal is

not sustainable within "public police of India" or "fundamental

policy of Indian Law". Hon'ble Supreme Court in Ssangyong, in

dealing with an arbitral award passed by majority of the arbitral

tribunal has set aside of award on ground of being against

"most basic notions of justice". In the case of Ssangyong

Engineering and construction Company Limited (Supra) two

out of three members of arbitral tribunal, by their award held

that new circular could be applied to the cases as it was within

contractual stipulations. It has been held by Hon'ble Supreme

Court that the majority of arbitral tribunal created new contract

for the parties by applying the unilateral circular and by

substituting a workable formula under the agreement by

another formula de-hors the agreement. Further, it has been

held by the Hon'ble Supreme Court that the circular itself

expressly stipulated that it cannot apply unless the contractor

furnished an undertaking/affidavit that the price adjustment

under the circular was acceptable to them. Thus it has been

observed by the Hon'ble Apex Court that this is being the case

of "fundamental principles of justice" had been breached clearly

such a course of conduct would be contrary to the fundamental

principles of justice as followed in this country and shocks the

conscience of the court.

21. In the present case the Learned Arbitrator has passed the

award on license fees according to the terms of the agreement, it

has not travelled beyond the agreement. There may be certain

other views according to the petitioner. Moreover, there may be

some other end findings on the basis of the evidence on record,

which an appellate court may determine, but in the present

facts and circumstances of this case the observation of Learned

Tribunal is not such exceptional that can shocks the conscience

of the court by infraction of fundamental notions or principle of

justice. It appears to me that the learned arbitrators has

construed the contract in fair mind as reasonable person and

not wonders outside the contract. Thus, in my view he commits

no error.

22. Under the above observations the first ground raised by the

petitioner appears to me not meritorious, award by the Learned

Arbitrator on point No. 1 appears to me justified.

23. Submission by the petitioner on point No. 2 :- Mr. Mookherjee

Learned Counsel, for the petitioner submits that the Learned

Arbitrator has erroneously awarded loss of interest on security

deposit for a sum of Rs. 50,00,000/- and loss of income on

account of additional license fees for a sum of Rs. 3,95,50,500/-

although the same is contrary to and also outside the terms of

the Agreement executed between the parties read with the

Supplemental Agreement dated June 14, 2008.

24. Mr. Mookherjee further submits that Clause 17 of origninal

Agreement stood amended by the Supplementary Agreement

dated June 14, 2008, whereby the Petitioner was allowed to

induct third party sub-licensees into the licensed premises.

There was no stipulation of payment of any additional security

deposit or additional license fee to the Respondent No. 1 herein

and further, there was no documentary proof to reflect any

contrary understanding between the parties was on record

before the Learned Arbitrator.

25. Mr. Mookherjee submits that the reliance of the Respondent

no. 1 on the letter dated May 13, 2008 [@page 584, Vol. IV of

the Compilation of Documents] and the letter dated February

27, 2009 is misplaced as the aforesaid letters do not establish

any understanding for payment of any additional security

deposit or additional license fee to the Respondent No. 1.

26. Mr. Mookherjee contended that the Learned Arbitrator has thus

erroneously awarded the aforementioned two claims de hors the

Agreement(s) between the parties and the Award to such extent

is not only contrary to the fundamental policy of Indian law as it

fails to consider Sections 91 and 92, the Indian Evidence Act,

1872 and is also patently illegal as it is dehors the contract and

bad in law and is thus liable to be set aside under Section

34(2)(b)(ii) and Section 34(2-A) of the Arbitration and

Conciliation Act, 1996

27. Submission by the respondent on point No. 2 :- Mr. Laxmi Pat

Surana (in person) submits that Additional License Fee and

Security Deposit claims are based on the permission granted to

the Petitioner for further sub-licensing 30% of the total space

sub-licensed i.e. roughly 30,000 sq ft to third parties in

consideration of making over additional rent over and above

what the Petitioner is paying to the Claimant i.e. Rs.19.50 per

sq ft per month and the additional security deposit which shall

be collected from such third parties to the Claimant. Such

arrangement was apparent from the conduct of the parties as

well as from an e-mail of the Petitioner dated 13th May, 2008 at

page/582, Vol-IV (for transfer of security deposit) and also from

Petitioner's letter dated 27th February, 2009 at page/1179, Vol-

IX (paragraph 2 for transfer of security deposit) and para 2 of e-

mail dated 30th March, 2009 at page 1212, Vol-IX (for sharing

additional rent with the Claimant). Mr. Surana submits the

Claimant in course of his cross examination as Claimant's

witness, particularly in answer to Q. No. 91G at page/1293,

Vol-XI has said that in course of discussion it was agreed that

three conditions would be required to be observed in this regard

i.e. the respondent would follow the terms and conditions which

have been accepted by the Claimant while executing various

Term Sheets with other sub-licensees in other Blocks. Mr.

Surana submits such terms were not incorporated in the

Supplementary Agreement at the sole request of the Petitioner

on the ground that such agreement is required to be shared

with the new sub-licensees and such terms may send a wrong

wind and cause a stumbling block for attractive license fee from

the prospective sub-sub-licensees. However, the Petitioner

agreed to issue such acceptance/confirmation separately. Mr.

Surana submits, he accepted such request of the Petitioner in

good faith being a large corporate house and a leading force in

retail business in the country at that point of time. The

Petitioner, however, refused to comply with such confirmation

despite repeated requests by the Claimant by several letters and

e-mails at pages/583-585, 588, 589, 591-594, Vol-4, 676, 677,

690, 696, Vol-5 and others available on record of the Tribunal

except issuing few emails and a letter, stated above, which fully

and unequivocally confirms such understanding between the

parties leading to the liability of the Petitioner in respect of

additional license fee and security deposit. Mr. Surana submits

It is settled law that interpretation of the terms of the contract

is within the domain of the Arbitrator. The proposition of law is

clear that an Award can only be interfered with if found to be

perverse or contrary to the evidence or in conflict with public

policy. This evidence of the Claimant has not been contradicted

nor there has been any cross examination on this point. Mr.

Surana argued this has duly been recorded by the Ld.

Arbitrator in paragraph 73 of the Award.

28. Heard the Learned Counsel for the petitioner as well as Mr.

Laxmi pat Surana, it appears that Learned Arbitrator has dealt

with Point No. 2 i.e. loss of interest of security deposit and loss

of income on account of additional license fees in paragraph 73

to paragraph 76 of the impugned award. I perused the said

paragraphs. For the better appreciation of the fact paragraph 73

of the award is set out hereinunder.

Loss of Interest on Security Deposit.

Loss of income on account of additional Licence fees.

73. For the sake of convenience, I deal with the above two

claims together, as both are based on provisions of the

supplementary agreement made between the Claimant and

Pantaloons Retail (India) Limited on 14th June, 2008 (RD-I,

P 428) which modified Clause 17 of the original agreement

dated 30th January, 2007. The said agreement provided

that Pantaloons would be entitled to further sub-lease

30,000 sq. ft. area to third parties in consideration of

making over additional security deposit and additional

rent to the Claimant. Such arrangement was apparent

from conduct of the parties as well as from e-mail of the

Respondents dated 13th May, 2008 (CD-II, p 303) and also

from a letter dated 27th February, 2009 (RD-11 P 442). Mr.

Surana, the Claimant, in course of his cross -examination,

particularly in answer to Q. 91G, he said that in course of

discussion it was agreed that three conditions would be

required to be observed in this regard; (i) Respondents

would be obliged to pay additional rent to be received by

Pantaloons from their sub-licensees to the extent, exceeds

their rate of rent payable to be Claimant i.e. Rs. 19.50p

per sq. ft.; (ii) Security deposit to be received by the

Pantaloons from such sub-licensees would be transferred

to the Claimant and (iii) Such sub-licensee should be in

conformity with the terms of agreement between the

Claimant and other sub-licensees in other Blocks as

recorded in Terms Sheets. This evidence of Mr. Surana has

not been contradicted and nor there has been any cross

examination on this point. Claimant's further case is that

the Respondents neither gave any prior intimation before

execution of any agreement with sub-licensees nor did they

provide copies of the same at any stage. Hence, the

Claimant claims on these two items appearing as Serial

No.25 and 26 at Rs.50,00,000/- and Rs.3,95,50,500 and

pleaded in paragraphs 42, 43 and 50 was largely a guess

work. I accept Mr. Surana's version of facts credible and

his assessment of loss quite reasonable. Innumerable

demands were made by the Claimant as would appear

from pages 304, 306, 310, 315 of CD-II and pages 392,

393, 401-406, 409-412 of CD-IV. Those demands

apparently had not been disputed.

29. It has been argued by the petitioner that claim of loss of interest

on security deposit and loss of income on account of additional

license fees are out of ambit of the reference. Learned arbitrator

has observed that two claims are passed on provisions of

supplementary agreement between the parties dated 14th June,

2008 which modified Clause 17 of original agreement dated 30 th

January, 2007. The Learned Arbitrator has discussed the points

in detail and also referred the pleadings, communication

through e-mail between the parties and the evidences laid

before him. It is the observation of Learned Arbitrator that the

claim of the petitioner/Mr. Surana has not been contradicted by

the present petitioner or there has no cross-examination on that

point. On the basis of which Learned Arbitrator has came to

opinion that claimant is entitled to Rs. 50,00,000/- towards

loss of interest on security deposit and also Rs. 3,95,50,000/-

on account of additional license fees. The reference was made

before the Learned Arbitrator in respect of agreement between

the parties dated 30th January, 2007. It has been admitted

before the Arbitrator by the parties that Clause 17 of the

original agreement was modified by the parties by way of

supplementary agreement dated 14th June, 2018. Thus, in my

view the point No. 2 is not out of the ambit of the reference. The

Hon'ble Apex Court in Ssanyong Engineering (supra) in

paragraph 66 has referred some observation of High court of

Ireland regarding the scope of arbitration.

66. The High Court of Ireland, in Patrick Ryan & Ann Ryan

v. Kevin O'Leary ( Clonmel) Ltd. & General Motors 60, put it

thus:

"24. As regards the second principle which emerges from the case law, namely, that an application to set aside is not an appeal from the decision of the arbitrator and does not confer upon the court the opportunity of second-guessing the arbitrator's decision on the merits, it is sufficient to refer to a small number of the Irish cases and the observations made in those cases. In Snoddy, Laffoy, J. made it very clear that it was not open to the court to second-guess the construction of the relevant contractual issue in that case by the arbitrator by way of a set aside application. Laffoy, J. stated that if the court were to do so, it would be usurping the arbitrator's role (para 34. p. 16). In Delargy 62, Gilligan, J. stated:

It is no function of this Court to attempt in any way to second guess the decision as arrived at by the arbitrator and this Court does not propose to do so. (para 74, p. 37).

Later in his judgment, Gilligan, J.

stated that:

"This Court does not consider that it is appropriate to revisit the merits of the arbitrator's award." (para 78, p. 39).

30. After considering the entire circumstances and after considering

the argument it appears to me that the Learned Arbitrator has

not travelled beyond the scope of submissions to arbitration. He

also not misinterpreted the reference to him as the arbitrator

has only considered the impugned reference and subsequent

agreement which amounting particular clause of agreement

(subject of reference). Thus in my view the Learned Arbitrator

has not wondered outsider the contract and only dealt with the

matter allotted to him there is no jurisdictional error in passing

the impugned award.

31. On the above observation I find no justification regarding the

objection raised by the petitioner.

32. Regarding point no. 3 and 4

Learned Arbitrator has awarded Rs 14,68,762/- in favour of the

claims towards electricity charges and also awarded Rs.

11,70,000/- towards water charges. Mr. Mookherjee, submits

that Learned Arbitrator has gone beyond the terms of the

agreement the Learned Tribunal has categorically held such

claims were not within the contractual terms of the parties and

it is within the quasi contractual claims arising out of Section

70 of Contract Act 1872. Mr. Mookherjee further submits that

the water charge is a complete guess work of Learned Arbitrator

which cannot be excepted. Mr. Mookherjee further submits that

claims of electricity charges and water charges do not find basis

on the contractual terms. Therefore, the Learned Arbitrator has

committed jurisdictional error by wondering the outside the

agreement between the parties which is outsider the mandate of

his reference.

33. Mr. Surana, submits that the claim electricity and water

charges are completely within the reference there is clear

provision in agreement for payment of electricity charges and

water charges. He submits though the Learned Arbitrator has

awarded such charges u/s 70 of the Contract Act under the

concept of quasy contract, but the same observation is baseless

in the view of clear stipulations for payment of electricity and

water charges in the agreement itself. He submits the Learned

Arbitrator though have awarded the same the charges of

electricity and water charges but there are some typographical

errors, the calculation of electricity charges should be more. It

was calculated from "November 2010" it should be corrected as

"January 2010" and the payment for electricity charges and

water charges should be up to the date of publication of the

award.

34. Having heard the Learned Counsel for the parties considering

the submissions. I perused the necessary clauses of the

agreement dated 30th January, 2007. Wherefrom it appears that

water charges and electricity charges are take part of the

agreement. Though the Learned Tribunal has awarded said

claims in terms of quasi contract u/s 70 of Indian Contract Act

but I think it necessary to hold that claims are properly within

the scope of reference and Learned Arbitrator has correctly

observed the materials therein; the finding of the Learned

Arbitrator cannot be said to be perverse and outside the scope

of reference. Thus the points of objection raised by the

petitioner in point 3 and 4 is appeared to me not meritorious

and the same is hereby set aside.

35. It appears that in the instant application u/s 34 of Arbitration

and Conciliation Act, 1996, the petitioner claims for setting

aside the entire final award dated 19th May, 2016 (except potion

allowing petitioner's counter claim); during the course of

argument no other grounds are raised by the petitioner except

the above mentioned 04 grounds. Thus I refrain myself to dealt

with those other points of objection.

36. It further appears that Mr. Surana has also argued at length

regarding his claim for enhancement of award amount on the

above mentioned 04 claims; as Mr. Surana has already filed

another application u/s 34 of the said Act, 1996, the claim and

objection of Mr. Surana shall be dealt with properly in deciding

his application.

37. Under the above observations, I am of a view that the

application of the petitioner u/s 34 of Act, 1996, against final

award dated 19th May 2016, is not meritorious and the same is

hereby dismissed. Thus AP-COM/135/2024 is hereby disposed

of.

38. Parties to act upon the server copy and urgent certified copy of

the judgment be received from the concerned Dept. on usual

terms and conditions.

(Subhendu Samanta, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter