Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The Chairman & Managing Director vs Alankar Construction Company
2024 Latest Caselaw 26884 Ker

Citation : 2024 Latest Caselaw 26884 Ker
Judgement Date : 6 September, 2024

Kerala High Court

The Chairman & Managing Director vs Alankar Construction Company on 6 September, 2024

Author: A.Muhamed Mustaque

Bench: A.Muhamed Mustaque

                                                           2024:KER:71511
W.A.No.7 of 2023
                                      1

            IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                PRESENT

 THE HONOURABLE THE ACTING CHIEF JUSTICE MR. A.MUHAMED MUSTAQUE

                                      &

                   THE HONOURABLE MR. JUSTICE S.MANU

 FRIDAY, THE 6TH DAY OF SEPTEMBER 2024 / 15TH BHADRA, 1946

                            WA NO. 7 OF 2023

         AGAINST     THE   JUDGMENT       DATED   26.05.2022   IN   WP(C)

NO.19299 OF 2021 OF HIGH COURT OF KERALA

APPELLANTS/RESPONDENTS:
    1     KERALA STATE ELECTRICITY BOARD,
          VYDUTHI BHAVANAM, PATTOM,
          THIRUVANATHAPURAM, PIN - 695004
             REPRESENTED BY ITS CHAIRMAN AND MANAGING DIRECTOR

     2       THE CHIEF ENGINEER (CIVIL),
             DAM SAFETY AND DRIP, PALLOM,
             KOTTAYAM, PIN - 686007

            BY ADV B.PREMOD, SC, KSEB
RESPONDENT/PETITIONER:
          ALANKAR CONSTRUCTION COMPANY,
          THOTTATHIL HOUSE, NADAKKAVU P.O,
          UDAYAMPEROOR,ERNAKULAM, PIN - 682307,
          REPRESENTED BY ITS MANAGING PARTNER T.P.ANTONY

            BY ADV C.S.AJITH PRAKASH

     THIS WRIT APPEAL HAVING COME UP FOR ADMISSION ON
06.09.2024, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
                                                      2024:KER:71511
W.A.No.7 of 2023
                                 2

                                                                      [CR]

   A.MUHAMED MUSTAQUE, Acg.C.J. & S.MANU, J.
  ---------------------------------------------------------------
                        W.A.No.7 of 2023
 -----------------------------------------------------------------
         Dated this the 06th day of September, 2024

                           JUDGMENT

S.MANU, J.

Appellants are the respondents in W.P.(C)No.19299 of

2021. The respondent herein approached this Court by

filing the writ petition praying mainly for a direction to the

2nd appellant to calculate, sanction and disburse the

amount as per the Adjudicator's decision with respect to

the disputes notified as per claim (m) and (n) in Ext.P7 and

decided by the Adjudicator by Ext.P12 within a time frame

and for interest on the said amount.

2. The petitioner, a partnership firm engaged in civil

construction works was awarded with a work by the Kerala

State Electricity Board Limited (KSEBL). Name of the work 2024:KER:71511

is "DRIP-Idukki Hydro Electric Project-Rehabilitation

including remedial measures and basic facilities-

improvement of approach roads to Idukki and Cheruthoni

Dam - (part-II works)". Agreement was executed on

16.6.2016. The agreement contains an adjudication clause.

As per the said clause if the parties to the contract notified

a dispute, same shall be referred to an Adjudicator at the

first instance. Whenever the Adjudicator takes decisions,

either party may refer the decision of the Adjudicator for

arbitration within 28 days of the Adjudicator's decision. If

no reference is made for arbitration within 28 days, the

decision of the Adjudicator will be final and binding.

3. After completing the works on 14.2.2018 the

respondent notified a dispute on 08.01.2019 before the

Adjudicator. The dispute included 25 claims under separate

and distinct heads. The Adjudicator, by Ext.P7, decided

claims under (m) and (n) in favour of the respondent. The 2024:KER:71511

respondent referred the remaining matters for arbitration

by the Arbitral Tribunal. KSEBL did not choose to approach

the Arbitral Tribunal against the claims decided in favour of

the respondent. Before the Arbitral Tribunal, the 2 nd

appellant filed a defence statement. However, no counter

claim against granting of claims under (m) and (n) in

favour of the respondent was raised. On 06.02.2021, the

Arbitral Tribunal passed an award. The respondent

preferred the writ petition aggrieved by non-quantification

and disbursal of the claims allowed in its favour by the

Adjudicator. The appellants resisted the writ petition.

According to the appellants, the Adjudicator's proceedings

were null and void since the contractors' complaints were

submitted much beyond 14 days' time limit under Clause

24 of the agreement. It was also contended that the

Adjudicator failed to consider claims (m) and (n) in a

proper manner and the decision of the Adjudicator cannot 2024:KER:71511

be implemented as there is no quantification of the amount

to be paid. Further contention of the appellants is that the

Adjudicator's decision is no more relevant as the Arbitral

Tribunal has passed an award subsequently. According to

the appellants, if the decision rendered by the Adjudicator

in favour of a party is not accepted by other party, the

dispute would not get crystallized and the parties will have

to go by the arbitration clause. Decision rendered by the

Adjudicator is only a procedural order preceding the

arbitration proceedings. The appellants never accepted the

authority of the Adjudicator as well as his decision. The

defence statement preferred before the Arbitral Tribunal

clearly shows that the appellants never accepted the

decision of the Adjudicator. The appellants therefore

contended that the prayer in the writ petition cannot be

allowed and the writ petition is liable to be dismissed.

2024:KER:71511

4. The learned Single Judge after hearing both sides

held that if any of the parties had any grievance against the

decision of the Adjudicator, the remedy was to refer the

matter for arbitration within a period of 28 days. The

learned Single Judge found that the KSEBL did not

challenge the decision of the Adjudicator with respect to

claims (m) and (n) by referring the same for arbitration.

Plea of the appellants that the respondent ought to have

sought the approval of the Arbitrator regarding the claims

decided by the Adjudicator in their favour was rejected by

the learned Judge. Writ Petition was allowed and the

appellants herein were directed to quantify the claims in

terms of money by calling upon the respondent herein or

the authorised representatives and to pay the same within

a period of 60 days from the date of receipt of certified

copy of the judgment, failing which the amount will carry

interest at the rate of 7.5%.

2024:KER:71511

5. Before us, the learned Standing Counsel for the

KSEBL Sri.B.Premod forcefully contended that the judgment

of the learned Single Judge is erroneous and the decision of

the Adjudicator sought to be enforced by the respondent is

void and not binding on the appellants. He reiterated the

contentions we have noted in the previous paragraphs. The

learned counsel for the respondent Sri.C.S.Ajith Prakash

opposed the submissions of the learned Standing Counsel

and contended that the judgment rendered by the learned

Single Judge is perfectly right. He submitted that the

appellants are bound to honour the decision of the

Adjudicator and reiterated the contentions raised in the writ

petition.

6. Bone of contention is regarding the effect of the

clauses in the agreement regarding disputes, especially

about Clause 25. The said Clause is therefore extracted

hereunder:-

2024:KER:71511

"25. Procedure for Disputes 25.1 The Adjudicator shall give a decision in writing within 28 days of receipt of a notification of a dispute. 25.2 The Adjudicator shall be paid daily at the rate specified in the Contract Data together with reimbursable expenses of the types specified in the Contract Data and the cost shall be divided equally between the Employer and the Contractor, whatever decision is reached by the Adjudicator. Either party may refer a decision of the Adjudicator to an Arbitrator within 28 days of the Adjudicator's written decision. If neither party refers the dispute to arbitration within the above 28 days, the Adjudicator's decision will be final and binding.

25.3 The arbitration shall be conducted in accordance with the arbitration procedure stated in the Special Conditions of Contract."

7. The highlighted component of Clause 25.2 gives

no room for any doubt and dispute in our view. The same

is crystal clear. If the decision of the Adjudicator is not 2024:KER:71511

acceptable to either party, the party may refer the decision

to an Arbitrator within 28 days of the Adjudicator's

decision. The decision of the Adjudicator will become final

and binding if neither party refers the dispute to arbitration

within 28 days. It is indisputable that two of the claims of

the respondent were decided in its favour by the

Adjudicator. The appellants did not approach the Arbitrator

within 28 days as stipulated in Clause 25.2. Therefore, the

decision of the Adjudicator regarding claims (m) and (n)

became final and binding on the parties. We do not find

anything in the relevant clauses, supporting the argument

of the appellants that the decision of the Adjudicator

required affirmation by the Arbitrator. So also the

provisions of the Clause do not give any room for disputing

the decision of the Adjudicator after expiry of 28 days.

There is no provision in the agreement enabling any party

to reject the decisions of the Adjudicator unilaterally. Even 2024:KER:71511

if the appellants had a contention that reference for

adjudication was beyond the time limit under Clause 24,

the remedy of the appellants was to refer the matter for

arbitration and challenge the decision of the Adjudicator on

that ground. Having not chosen to refer the decision of the

Adjudicator for arbitration, it is not open to the appellants

to depict it as void and refuse to honour the same.

Contention of the KSEBL that they confronted the decision

of the Adjudicator in the statement filed before the Arbitral

Tribunal is short of any merits. It was incumbent upon the

KSEBL to challenge the decision independently or to raise a

counter claim.

8. When the parties mutually agree to refer disputes

that may arise between them for decision by a referee,

decision by the referee shall bind the parties. Relying on

the principles of "vicarious admission" ingrained in Section

20 of the Evidence Act, the Apex Court in Hirachand 2024:KER:71511

Kothari (Dead) by Lrs v. State of Rajasthan and

another [1985 (Supp) SCC 17] held as follows:-

"7. Section 20 of the Evidence Act reads as follows:

20. Admissions by persons expressly referred to by party to suit-Statements made by persons to whom a party to the suit has expressly referred for information in reference to a matter in dispute are admissions.

Section 20 is the second exception to the general rule laid down in Section 18. It deals with one class of vicarious admissions that demand of persons other than the parties. Where a party refers to a third person for some information or an opinion on a matter in dispute, the statements made by the third person are receivable as admissions against the person referring. The reason is that when a party refers to another person for a statement of his views, the party approves of his utterance in anticipation and adopts that as his own. The principle is the same as that of reference to arbitration. The reference may be by express words or by conduct, but in any case there must be a clear admission to refer and such admissions are generally conclusive."

2024:KER:71511

9. The same principle has been dealt with in the

commentary to Evidence Act by Ratanlal and Dhirajlal as

follows:-

"An admission by a person referred to by the party comes very near to the case of arbitration (STEPHEN DIG. 7th Edn., Note to Art. 19, p. 1789). If a reference is made over a disputed matter to a third person, not in the nature of a submission to arbitration, but rather as an aid to the settlement of the differences existing between the parties and to enable the parties themselves to effect a settlement on the information, in such cases the party is bound by the declaration of the person referred to in the same manner and to the same extent as if it was made by himself. A referee is deemed to be an arbitrator and his decision is an award. It may be noted here that under the Arbitration Act the parties to a dispute in a court of law may request the court to refer the dispute to an arbitrator. Apart from that, there may be a provision in the contract between two parties, to refer if any dispute arises, to arbitration. In such cases the arbitrator, after going through the evidence that may be placed before him, comes to a finding, If that happens in the proceedings before the court, the 2024:KER:71511

parties will have an opportunity to raise objections which have to be considered by the court, which will pass a decree either in terms or in modification of certain findings of the award. All that procedure will not be available if a reference is made to a third party for his opinion under this section. So it would not be proper to call the statement of the referee as an award."

10. In Halsbury's Laws of England (4th Edition, Vol.17,

Para 74) the selfsame rule has been expressed as extracted

hereunder :

"74. Admissions by referees-

When a party agrees to be bound by what a third person says, or refers an opposite party to a third person for information or an opinion on a given subject, the third person's reply is admissible against the party so agreeing or referring; and if the reference has been made by agreement it will be conclusive."

11. Thus, when parties agree by a contract to refer

disputes that may arise between them for 2024:KER:71511

opinion/resolution/adjudication by a third party who may be

described as a referee/adjudicator, the opinion rendered

or decision taken by the referee/adjudicator shall be

binding on the parties in view of the principle of "vicarious

admission". It is not open to the parties to dishonour such

a decision. Challenge to such decisions can be made as

provided for in the contract and not otherwise. Purpose of

incorporating dispute resolution clauses in contracts is to

have a reciprocally agreed built-in mechanism for easy and

swift resolution of disputes and the aforesaid cannot be

permitted to be subjugated by any sides under normal

circumstances.

12. We are of the view that the above said principles

squarely apply to the facts of this case. Appellants and the

respondent agreed to the dispute resolution mechanism as

provided under Clause 25. Neither party can be permitted

to wriggle out of the same. The decision of the Adjudicator 2024:KER:71511

regarding claims (m) and (n) binds the appellants as they

did not chose to contest it by invoking the provision of the

contract, i.e. by resorting to arbitration.

Hence, we uphold the judgment of the learned Single

Judge. Writ appeal is dismissed.

Sd/-

A.MUHAMED MUSTAQUE, ACTING CHIEF JUSTICE

Sd/-

S.MANU, JUDGE

skj 2024:KER:71511

APPELLANTS' ANNEXURES Annexure A1 THE TRUE COPY OF THE AGREEMENT NO.

07/CE(C) DSDRIPMLM/2016-17 DATED 16.06.2016 Annexure A2 THE TRUE COPY OF THE SUPPLEMENTAL AGREEMENT EXECUTED BY THE WRIT PETITIONER/RESPONDENT DATED 12-12-2017 Annexure A3 THE TRUE COPY OF THE SUPPLEMENTAL AGREEMENT EXECUTED BY THE WRIT PETITIONER/RESPONDENT DATED 30-6-2018

Annexure A4 THE TRUE COPY OF THE LETTER ISSUED TO THE RESPONDENT DATED 29-06-2019

Annexure A5 THE TRUE COPY OF THE LETTER OF APPOINTMENT THE ARBITRATOR SRI. M.V GEORGE DATED 11-07-2019

Annexure A6 THE TRUE COPY OF THE LETTER ISSUED TO THE RESPONDENT DATED 1 1 -07-2019

Annexure A7 THE APPELLANT BOARDS DECISION TO OPT FOR ARBITRATION AND APPOINTMENT OF ARBITRATOR

Annexure A8 THE TRUE COPY OF THE SUPPLEMENTARY AWARD PASSED BY THE ARBITRAL TRIBUNAL ON 30-03-2021

Annexure A9 THE TRUE COPY OF THE LETTER DATED 6-09-2021

Annexure A10 THE TRUE COPY OF THE MINUTES OF THE MEETING CONVENED BY THE CHIEF ENGINEER ON 27-05-2017

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter