Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

R S P L Limited vs C.G. Environment Conservation ...
2022 Latest Caselaw 1240 Chatt

Citation : 2022 Latest Caselaw 1240 Chatt
Judgement Date : 10 March, 2022

Chattisgarh High Court
R S P L Limited vs C.G. Environment Conservation ... on 10 March, 2022
                                    1

                                                                    NAFR

             HIGH COURT OF CHHATTISGARH, BILASPUR


                           WA No. 298 of 2020

R S P L Limited Through Mr. Jaswinder Singh, S/o Mr. Babu Singh, Aged
About 42 Years, Plant Manager Having It's Unit At Ph No.- 100/28,
Khasra No. Ph 31, 33, 34 And 37 Village Achholi District- Raipur,
Chhattisgarh. Having It's Registered Office At 199-121 (Part) Block P And
T Fazal Ganj, Kalpi Road Kanpur- 208012 (Up)

                                                             ---- Appellant

                                 Versus

C.G.   Environment    Conservation    Board    (Respondent)  Board

(Respondent) Through Its Regional Officer Commercial Complex, C.G. Housing Board Colony Kabir Nagar, Raipur, Chhattisgarh

---- Respondent

(Cause-title taken from Case Information System)

For Appellant : Mr. Daleep Dhayani, Advocate.

For Respondent : Mr. Animesh Tiwari, Advocate.

Hon'ble Shri Arup Kumar Goswami, Chief Justice

Hon'ble Shri Gautam Chourdiya, Judge

Judgment on Board

Per Arup Kumar Goswami, Chief Justice

10.03.2022

Heard Mr. Daleep Dhayani, learned counsel for the appellant. Also

heard Mr. Animesh Tiwari, learned counsel, appearing for the respondent.

2. This appeal is directed against an order dated 27.02.2020, passed

by the learned Single Judge in WPC No. 761 of 2020, refusing to

entertain the writ petition on the ground that an appeal lies before the

National Green Tribunal.

3. The writ petition was instituted challenging an order dated

06.02.2020, issued by the Regional Officer, Chhattisgarh Environment

Conservation Board, which was passed in exercise of powers conferred

under Section 31A of the Air (Prevention and Control of Pollution) Act,

1981 (for short, 'the Air Act, 1981') and in terms of the order dated

10.07.2019 of the National Green Tribunal, Principal Bench, New Delhi,

directing the appellant to deposit a sum of Rs.1.14 crore as

environmental compensation with the Chhattisgarh Environment

Conservation Board by way of Demand Draft.

4. Order dated 10.07.2019, which is quoted in the order dated

06.02.2020, reads as follows:

"i. Para-22. In view of water pollution caused by

absence/dysfunctional CETPs/ETPs/STPs, the

Tribunal has, in the case of Aryavart Foundation Vs

M/s Vapi Green Enviro Ltd. & Ors. 18, directed all

defaulting industries, other than green and white

category, connected with CETP, to make deposit

with the CPCB towards interim environmental

compensation, pending assessment of actual

compensation and further action, on the following

scale:

(i) Large Insdustries - Rs. 1 crore each

(ii) Medium Industries - Rs. 50 Lakhs each

(iii) Small Industries - Rs. 25 Lakhs each.

(ii) Para-23. In the present case, in view of massive

exercise already done by CPCB, it is not necessary

to require any further verification about the

existence of pollution in the said PIAs. The Tribunal

can direct that the polluting activities cannot be

allowed to continue till adequate measures are

taken as the Tribunal is bound to apply the

'Sustainable Development' 'Precautionary' and

'Polluter Pays' principle under Section 20 of the

National Green Tribunal Act, 2010 to protect the

environment and the victims. The statutory

regulatory bodies can be required to straightaway

identify the particular industrial units int eh said PIAs

that are causing pollution, particularly those units

which fall under the red and orange category and

take action against them by way of closing the

polluting activity, initiating prosecution and

assessing and recovering compensation. Pending

such assessment, interim compensation may be

recovered on the scale adopted by this Tribunal in

the case of Vapi industrial area.

(iii) Para-28, Accordingly, we direct the CPCB in

coordination with all State PCBs/PCCs to take steps

in exercise of statutory powers under the Air

(Prevention and Control of Pollution) Act, 1981,

Water (Prevention and Control of Pollution) Act,

1974 Environment (Protection) Act, 1986 or any

other law to prohibit operation to polluting activities

int eh said CPAs and SPAs within three months and

furnish a compliance report to this Tribunal. The

Central Pollution Control Board, in coordination with

the State Boards/PCBs may make assessment of

compensation to be recovered from the said

polluting units for the period of last 5 years, taking

into account the cost of restoration and cost of

damage to the public health and environment and

the deterrence element. The scale of deterrence

may be related to the period and the frequency of

defaults. Such other factors as may be found

relevant may also be taken into account. No 'orange'

category units till the said areas are brought within

the prescribed parameters or till carrying capacity of

area is assessed and new units or expansion is

found viable having regard to the carrying capacity

of the area and environmental norms. Pending

assessment of compensation, interim compensation

be recovered at the scale adopted by this Tribunal in

the case of Vapi Industrial area as mentioned in

para 22 above."

5. A perusal of the order dated 06.02.2020 goes to show that the

industry of the appellant falls in a Critically Polluted Area (CPA) and that

under the provisions of Micro, Small and Medium Enterprises

Development Act, 2006, it is a 'Large' industry. It also falls under the Red

category as per Final Document on Revised Classification of Industrial

Sectors under Red, Orange, Green and White Categories (February 29,

2016) published by Central Pollution Conservation Board (CPCB). The

order also goes to show that the appellant was directed to increase the

height of all stacks attached to the emission sources as auxillary process

equipment / bag filter/scrubber to minimum 30 meters latest by August

2019 vide order dated 06.06.2019. On an inspection carried out on

31.01.2020, it was found that the height of the chimney installed with the

bag filter in the detergent powder unit was below the prescribed norms

i.e. 30 meter.

6. Mr. Dhayani submits that the learned Single Judge was in error

inasmuch as no appeal lies to the National Green Tribunal against an

order passed under Section 31A of the Air Act, 1981. He, however, fairly

submits that an appeal lies against such an order under Section 31A of

the Air Act, 1981 to the Appellate Authority and against the order of the

Appellate Authority, an appeal lies before the National Green Tribunal

under Section 31B of the Air Act, 1981. He submits that notwithstanding

the provision of appeal before the Appellate Authority, the impugned order

directing to deposit a sum of Rs. 1.14 crores by way of Environmental

Compensation having been passed without affording any opportunity of

hearing, writ court ought to have entertained the writ petition and

therefore, the learned Single Judge was in error in relegating the

appellant to avail alternative remedy. He also submits that order of the

National Green Tribunal, which is referred to in the impugned order, is not

applicable to the petitioner as the said order was passed in the context of

Common Effluent Treatment Plants (CETP). He submits that the

appellant did not receive the letter dated 06.06.2019, which was referred

to in the order dated 06.02.2020 and to buttress the contention, he has

drawn our attention to paragraph 8.8 of the writ petition.

7. Mr. Animesh Tiwari, learned counsel for the respondent, on the

other hand, endorses the submission of Mr. Dhayani to the extent that the

observation of the learned Single Judge that appeal lies against the order

of the Chhattisgarh Environment Conservation Board under Section 31B

of the Air Act, 1981 before the National Green Tribunal, was not correct.

He also endorses the submission of Mr. Dhayani that appeal, in fact, lies

before Appellant Authority under Section 31 of the Air Act, 1981. It is

submitted by him that despite notices issued to increase height of the

chimney, the same was not complied with by the appellant.

8. Relying on the affidavit filed, Mr. Tiwari submits that the amount of

Rs. 1.14 crores was determined in accordance with the guidelines issued

by the Central Pollution Board, which was adopted by Chhattisgarh

Pollution Control Board. He refutes the contention of Mr. Dhayani that

order dated 10.07.2019 of the National Green Tribunal is not applicable to

the petitioner.

9. On a query of the Court as to whether chimney has been increased

to 30 meters, Mr. Dhayani submits that, subsequently, height of the

chimney had been increased and the same was also intimated to the

authorities.

10. A perusal of paragraph 8.8 would go to show that there is no

categorical assertion that the notice dated 06.06.2019 has not been

received by the petitioner. However, we have not drawn any conclusion

on this aspect of the matter as well as in respect of other contention

advanced before us, as after hearing the learned counsel for the parties

and on perusal of the materials on record, we are of the considered

opinion that in a matter of present nature, as held by the learned Single

Judge, it will be appropriate for the appellant to prefer an appeal, if so

advised, before the Appellate Authority.

11. In view of the above discussion, the appeal is dismissed.

12. Before parting with the records, we, however, observe that in the

event of appellant preferring an appeal, the appellant will be entitled to

raise all contentions as may be available in law and facts and the

Appellate Authority shall consider the same in accordance with law.

                      Sd/-                                     Sd/-
            (Arup Kumar Goswami)                        (Gautam Chourdiya)
                 Chief Justice                                Judge
Hem
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter