Tuesday, 19, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S.Kesari Marine Service vs The Indian Oil Corporation Limited
2025 Latest Caselaw 6339 Tel

Citation : 2025 Latest Caselaw 6339 Tel
Judgement Date : 7 November, 2025

Telangana High Court

M/S.Kesari Marine Service vs The Indian Oil Corporation Limited on 7 November, 2025

Author: Nagesh Bheemapaka
Bench: Nagesh Bheemapaka
        HON'BLE SRI JUSTICE NAGESH BHEEMAPAKA

              WRIT PETITION No. 16559 OF 2025

O R D E R:

The case of petitioner is that pursuant to the

Tender Notice issued by the 1st respondent for Bunker supply of

black oil and white oil through tanker barges to the

coastal/foreign run sea going vessels berthed at inner harbor,

outer harbor, and outer anchorage of Vizag Port, Petitioner

along with others submitted tenders. The name of Petitioner's

barge is CAPSTAR-1. After getting fully satisfied about

Petitioner's barge, the 1st Respondent accepted the tender

submitted by them. Petitioner tendered for 30% transportation

of the Oil and it stood as L2 among the Tenderers, L1 being for

50% transportation. It is submitted that the 1st Respondent

issued Letter of Acceptance (LOA) dated 20.02.2025, as per

which, the period of contract is three years from the date of the

LoA, extendable for a further period of 9 months on mutual

consent, in line, with GeM conditions. It is stated Petitioner had

complied with all the formalities for clearance of its berth from

Kakinada Port to Vizag Port for transporting the black oil/white

oil, as per the requirement and the work orders of the 1st

Respondent in accordance with the LOA.

1.1. It is stated, the 1st Respondent issued Petitioner

Work Order dated 12.03.2025 for transporting white oil and

black oil to coastal and foreign-run vessels stationed at Vizag

Port through tanker barges (small category barges). Under the

relevant Rules and Regulations governing the movement of

barges, petitioner applied on 03.03.2025 for clearance of its

Barge from Kakinada port; the said port delayed issuance of

clearance. Thereafter, on 12.03.2025, the 1st Respondent issued

work order which should be followed by due execution of the

prescribed Contract and issuance of LOA. As Kakinada port was

delaying clearance, petitioner re-submitted its Application on

22.03.2025. As there was no response, petitioner filed Writ

Petition No. 8234 of 2025 and Kakinada Port issued clearance.

By an e mail, petitioner informed the 1st Respondent that its

Barge would be ready in all respects at Vizag port by

27.03.2025.

1.2. As per normal practice and procedure in vogue, the

1st Respondent has to follow up the said LOA with a written

prescribed contract and issuance of LOA for transportation of

the oil, pursuant to the said work order. The 1st Respondent did

not get the prescribed contract duly executed by Petitioner and

no LOA was issued to petitioner. Petitioner received an e mail

dated 21.03.2025 from the 1st Respondent to position the Barge

within 30 days from the date of LOA i.e by 21.03.2025 failing

which, the said LOA is liable for cancellation. According to

petitioner, this communication is illegal and impermissible, as,

by 21.03.2025, 30 days did not expire from the date of the LOA.

The 1st Respondent failed to notice that February has only 28

days.

1.3. Petitioner sent e mail dated 28.03.2025 informing

that its Barge arrived at Vizag port on 28.03.2025 and is ready

for the procedural inspections by the 1st Respondent, followed

by e mail dated 29.03.2025 informing the 1st Respondent that

survey of its Barge by Vizag port was completed and that VPT

Harbour Craft license was also issued by the said port. Again,

on 01.04.2025 at 12.58 hours, by another e mail all these

aspects were communicated to the 1st Respondent requesting

them to issue Letter of Intent for transportation of oil, as per the

said work order given to petitioner. However, Petitioner received

an e-mail dated 01.04.2025 (at 19.25 hours) from one of the

officials of the 1st Respondent stating that as per the earlier

e mail dated 21.03.2025, the said LOA issued to petitioner

stands cancelled, as, by 21.03.2025, they did not keep its barge

ready. It referred to "Point 4 in the Tender conditions" which has

no application at the stage of LOA. The 1st Respondent did not

notice that February month has only 28 days and that even 30

days did not expire by 21.03.2025 from the date of LOA which is

dated 20.02.2025. It failed to bear in mind that LOA was

received by petitioner on 22.02.2025. In law, under the General

Clauses Act the day on which any communication was received

has to be excluded for computation of any period prescribed.

1.4. It is also stated, the action of the 1st Respondent in

cancelling the LOA is arbitrary, illegal and is in gross violation of

the principles of natural justice. Challenging the e mail dated

01-04-2025, petitioner filed Writ Petition No. 15034 of 2025

which was disposed of on 07.05.2025 observing that in view of

the fact that LOA dated 20-02-2025 issued by the 1st

respondent in favour of petitioner indicated the period of

contract as three years from the date of LOA with a clear

stipulation that the said period is extendable for a further period

of nine months on mutual consent in line with GeM conditions

and the same had been cancelled unilaterally without following

the principles of natural justice, this Court was of the opinion

that Respondents 1 and 2 had acted hastily in dealing with the

subject issue and passed the order impugned mechanically,

erroneously, without application of mind mala fidely. Hence,

the 1st Respondent was directed to reconsider the impugned

decision dated 01.04.2025, within four weeks from the date of

the order and further directed that till then, no coercive steps

shall be taken against petitioner and against its Barge.

1.5. Pursuant to the said direction, petitioner made a

detailed representation dated 11-05-2025, however, the 1st

respondent issued the impugned order on 06-06-2025 declining

their request. Challenging the said order, this Writ Petition is

filed.

2. This Court by order dated 01.07.2025, granted

status quo existing as on date till filing the counter-affidavit and

the said order was extended from time to time.

3. The 1st respondent filed counter stating that Barge

of petitioner was at Kakinada Port and was required to be

placed at Vizag with all Clearances and Permissions. As per the

mail of petitioner dated 29-03-2025, they informed that Barge

would be ready in all aspects by 27-03-2025 whereas it was

supposed to be produced for inspection within 30 days of LOA

i.e. by 21-03-2025 (both days inclusive). Hence, the contention

of petitioner that February has 28 days and 30 days did not

expire on 21-03-2025 from the date of LOA 20-02-2025 is

baseless and petitioner is again and again bringing the same

into the matter. The fact mentioned in the mail of the petitioner

dated 28-03-2025 that their barge has arrived at

Visakhapatnam Port and berthed at GREEN CHANNEL berth on

28-03-2025, therefore the constant repetition by the petitioner

that February has 28 days has no significance since 28-03-2025

is well beyond 30 days. Looked from any angle, petitioner could

not produce the barge for inspection within 30 days. It was also

mentioned that the licenses applied/submitted by paying all

necessary fees and documents required for them on 12-03-2025

and it is still under process. Only on 29-03-2025 afternoon,

petitioner had informed that survey by Visakhapatnam port is

completed and VPT Harbour craft license is received. LOA

clearly states that "All tender documents including NIT, offer,

special terms and conditions of contract, specifications, general

description of works and relevant drawings, subsequent

negotiations and all other correspondences connected with the

above referred tender including this letter shall form part of the

Work Order/Contract". Hence the contention of the petitioner

that point-4 in the tender conditions is not applicable at the

stage of the LOA is wrong and mis-understood.

3.1. It is stated, the contract would commence after

work is undertaken complying with the conditions of LOA in

accordance with tender terms and conditions. The Work Order

was issued only to acknowledge the Security Deposit submitted,

but the contract is deemed to commence only after inspection of

Barge which is ready in all aspects. Barge was supposed to be

produced for inspection ready in all aspects within 30 days of

issuance of LOA which petitioner could not do. Hence, LOA was

cancelled. It is also stated, based on the direction in Writ

Petition No. 15034 of 2025, opportunity of personal hearing was

provided to petitioner on 29-05-2025 and speaking order was

passed by the competent authority on 06-06-2025.

3.2. It is stated, the entire tendering process is done in a

transparent manner within the set terms & conditions.

Moreover, the fact that petitioner selection for placement of LOA

was based on the higher annual turnover criteria and hence

contrary to their own statement of being a small contractor. For

all the aforesaid reasons, this respondent prays that Writ

Petition may be dismissed.

4. The 2nd respondent filed the counter stating that

Writ Petition is not maintainable as the issues raised are

contractual disputes involving disputed questions of facts,

which cannot be decided in a Writ Petition under Article 226 of

the Constitution of India and the parties be relegated to the Civil

Courts of competent jurisdiction to seek appropriate reliefs.

4.1. It is stated, the 2nd Respondent is a Registered

Partnership firm constituted for the purpose of bunker

transportation and its allied activities and has been established

in 1997 and since then has been serving all its industrial

customers with quality service in the field of Marine/Industrial

lubricants market operating and gained immense expertise and

experience in supplying and trading of servo industrial trade

lubricants. The 1st respondent issued tender notification and

one day before the last date of submission of bids (thereafter the

last date was extended to January, 2025), the 1st Respondent

had issued a Corrigendum dated 26.12.2024 stating that in

case of tie at L-1 position, GeM shall select the successful L1

bidder through 'system determined vendor selection'. It was also

added that in case of tie at other than L-1 position, Bidder with

the highest turnover in any of the last three years as submitted

against turnover criteria shall be considered for selection of L-2

and L-3 bidders. In exceptional cases, where turnover is also the

same, the bid submitted earlier in the Portal in terms of both

date and time, shall be considered for selection of L-2 and L-3

bidders. It is pertinent to mention that Clause No 23 (xxiii) of

the Tender Notification stated that in case of tie between two or

more bidders at L-1 position, GeM Modalities shall be

applicable. If the price bid of the parties is one and the same, it

is meaning thereby that under the said system, randomly

somebody would be selected. It is submitted that the price bids

of the five technically-qualified bidders were opened on

17.02.2025 and it was found that all the five have quoted the

same price for Lot-1, therefore, all of them were shown as L-1

and the tendering authority had selected Supreme Marine

Services as L-1 as per GeM system selection. Be that as it may,

bearing the nature of work, which requires bulk supply of Oil to

be made at Visakhapatnam Port, the notification also stated

that contract would also be awarded to two more persons who

are L2 and L3 in the ratio of 50 : 30 : 20, being L-1: L-2: L-3

respectively Accordingly, Petitioner was selected as L-2 and this

Respondent has been selected as L-4. The 1st respondent issued

LoA to Petitioner on 20.02.2025. It is relevant to mention,

under Clause 14 (17)(d) of the Notice Inviting Tender (NIT),

bidder is required to give an undertaking on notarized 100/-

Non Judicial stamp paper that he shall position the offered

barrage ready in all aspects along with required licences within

30 days of issuance of LOI/LOA at Vizag Port. Further, Clause 4

under Condition B Requirements of Barrage of Special Terms &

Conditions (STC)/Special Condition of Contract (SCC)

specifically states that barge should be inspected by IOC or

authorized surveyors and be ready in all aspects for effecting

bunker supplies within 30 days of LOI and that the LOA/LOI is

liable to be cancelled in case any party fails to comply the said

condition. Therefore, the said clauses goes to show that it is a

mandatory requirement for the bidders in whose favour LOA has

been issued that the barge shall be ready in all aspects at the

Vizag port within 30 days from the date of issuance of LOA.

4.2. Though LOA was issued on 20.02.2025, Petitioner

failed to berth the barge within 30 days therefrom, therefore in

terms of the Condition B clause 4 of the STC/SCC, the LOA was

cancelled and the same was communicated to Petitioner vide

email dated 01.04.2025. Thereafter, LOA dated 06.06.2025 was

issued in favour of this Respondent for carrying out the subject

work and requested to deposit security deposit as per the tender

conditions. Accordingly, they paid Rs. 12,77,747/- as Bank

Guarantee for the said work as per the tender conditions.

4.3. As the matter stood thus, the present Writ Petition

came to be filed with frivolous grounds and vexatious claim and

this Court by order dated 01.07.2025 directed to maintain

status as on that day. As a result of the same, it is stated,

respondents have been facing heavy pecuniary losses, therefore,

it is prayed to vacate the interim order.

5. The 3rd respondent filed counter stating that

petitioner (L2) was issued LOA on 20.02.2025 and worked order

on 12.03.2025 . It is stated, L3 was awarded to M/s KK Marine

Service (20%), Letter of Acceptance (LOA) was issued on

20.02.2025 and work order issued on 12.03.2025. Both L2 and

L3 have not placed their barge in Visakhapatnam Port and not

obtained any 'No Objection Certificate' from Visakhapatnam

Port within the stipulated time as per Tender Norms of Indian

Oil Corporation Limited. As such the 1st Respondent cancelled

their work orders and further allocated the Work of 30% to L4-

KAN Enterprises (Respondent No.2) and 20% to L5 Gayatri

Marine Services (Respondent No.3) through Letter of Acceptance

dated 06.06.2025. Subsequently, Respondent No.1 sent e mail

on 07.06.2025 to Respondent No.3 to submit all necessary

documents along with PBG (Performance Bank Guarantee) &

Security Deposit for a total amount of Rs 8,51,131/-. Pursuant

thereto, Respondent No.3 submitted all documents along with

Performance Bank Guarantee & Security deposit on 17.06.2025

and offered Barge 'VASPARI' for inspection to Respondent Indian

Oil Corporation Limited on 20.06.2025.

5.1. Respondent No.1 Officers inspected the barge on

23.06.2025 and Respondent No.3 has been waiting for orders

and also sent an e mail on 28.06.2025 requesting for allowing

them to commence the work allotted and again on 04.07.2025,

apart from that, a representation was submitted on 14.07 2025

at IOCL Terminal Vizag and also a copy of the representation

was sent to IOCL Hyderabad Office by post on 14.07.2025.

Aggrieved by the inaction, Respondent No.3 preferred Writ

Petition No. 21780 of 2025, wherein this Court by order dated

25.07.2025, disposed of the Writ Petition directing respondent

authorities to consider representation dated 13.07.2025 and

after giving a fair opportunity of hearing to petitioner therein,

respondent shall pass appropriate orders in accordance to law,

within four weeks from the date of receipt of a copy of this order

and communicate the same to Petitioner therein.

5.2. It is stated, while issuing the LOA to Respondent

No.3, Respondent No. 1 mentioned therein that LOA is subject

to outcome of Writ Petition No.13863 of 2025 filed by M/s K.K.

Marine Services, and the said Writ Petition was disposed of by

order dated 30.06.2025 directing respondent authorities to

consider representation dated 27.06.2025 and after giving a fair

opportunity of hearing pass appropriate orders in accordance to

law within four weeks from the date of receipt of a copy of

Order. It is stated, Petitioner is not a party to Writ Petition No.

13863 of 2025. Petitioner who is L2 filed this Writ Petition and

Respondent No.3 has been made a party in the present Writ

Petition, although the Respondent No.3/L5 (20% work allottee)

has been allotted the work from a separate component, which is

not concerned with Petitioner, and by suppressing the facts has

got interim stay order, as a result, the Respondent No.3 is facing

lots of financial hardships.

5.3. It is stated, Respondent No.3 is a successful

financial and technical bidder and submitted all documents to

Respondent No.1 and also furnished Performance Bank

Guarantee and Security Deposit, even then, Respondent No.1

delayed permitting Respondent No.3 to start work in pursuance

of LOA dt.06.06.2025. Respondent No.3 had already incurred

Rs.28.00 (Twenty-Eight Lakhs) for the work, and the same has

been informed to Respondent No.1 also. The work originally

allotted to Petitioner (30% work) was subsequently allotted to

Respondent No.2, but it was not allotted to Respondent No.3.

The alleged component of work allotted to Petitioner does not

pertain to Respondent No.3. Even then, Petitioner made them as

a party, by suppressing the facts and got stay order. If at all,

there is any grievance, it ought to be against Respondents 1 and

2 and not wit the Respondent No.3.

5.4. The work component of 20% allotted to Respondent

No.3 is from a separate component of work and nothing to do

with the allegations of Petitioner. Except naming Gayatri Marine

Services as Respondent No.3, no specific allegations are made

by Petitioner.

6. Petitioner filed reply stating that the impugned

order is in violation of the orders in Writ Petition No. 15034 of

2025 dated 07-05-2025. In view of this, the counter affidavit

filed by the deponent of the counter affidavit, is neither proper

nor permissible. The deponent has no authority to represent the

1st respondent. It is for the competent officer of the 1st

respondent to depose and answer the averments made in the

affidavit filed in support of the above writ petition. It is for the

signatory of the impugned order to explain as to how the

impugned order is in compliance with or in conformity with the

order dated 07-05-2025 in Writ Petition No. 15034 of 2025.

Petitioner reiterated the averments in the Writ Petition.

7. Petitioner also filed reply to the counter of the 2nd

respondent almost reiterating his case.

8. Heard Sri S.S. Prasad, learned Senior Counsel

representing Sri S.N. Chidambara Sastry, learned counsel for

petitioner, Sri Vedula Srinivas, learned Senior Counsel

representing Sri Dominic Fernandes, learned Standing Counsel

for Respondent No.1, Sri G. Vidya Sagar, learned Senior

Counsel appearing on behalf of Sri M. Avinash Reddy, learned

counsel for the 2nd respondent and Sri S. Ravi, learned Senior

Counsel for Sri M.P. Kashyap, learned counsel for Respondent

No.3.

9. From a perusal of the material on record, it is

evident that this is the second round of litigation. Petitioner has

already approached this Court in Writ Petition No. 15034 of

2025 challenging the e mail dated 21.02.2025 at 17.00 hours

and e mail dated 01.04.2025 at 19.25 hours, cancelling the LOA

dated 20.02.2025 issued to them on a wrong premise that by

21.03.2025, 30 days have lapsed from the date of LOA making it

liable for cancellation. This Court by order dated 07.05.2025,

made the following observations in the said Writ Petition:

" This court taken into consideration the fact as borne on record that the prayer sought for by the petitioner herein in W.P.No.8234/2025 on the file of the A.P. High Court and the prayer sought for in the present writ petition i.e. W.P.No.15034/2025 on the file of the Telangana High Court being different from each other opines that the present writ petition is maintainable as per Clause 22.7 (b) of the notice inviting tender.

This Court opines that even though the date of LOA issued to the petitioner is dated 20-02-2025, fact remains that admittedly, the work order issued to the petitioner is only on 12-03-2025 and the petitioner admittedly can commence his work only after receipt of the work order from the 1st respondent and not earlier than that, and

therefore this court opines that the action of the 1st and 2nd Respondents in cancelling the work order on the ground that petitioner failed to offer the barge for inspection by IOC/IOC authorised Independent Surveyors ready in all respects for effecting bunkers supplies before the due date 21-03-2025 i.e. within 30 days from the date of LOA is not only arbitrary, whimsical, mechanical but also highly unreasonable, unfair and unjust".

c) "It is also borne on record and even admitted by the learned standing counsel appearing on behalf of the respondents that admittedly, prior to the issuance of the impugned proceedings of the 1st and 2nd respondents dtd.01-04-2025 communicated by e-mail to the petitioner informing the petitioner that its LOA dtd.20-02-2025 and the work order stands cancelled, the petitioner was not provided with an opportunity of personal hearing and admittedly, as borne on record, no specific Show Cause notice was issued to the petitioner informing the petitioner about the proposed action contemplated by the respondents 1 and 2 and further calling for explanation from the petitioner".

d) "This court opines that in view of the fact as borne on record that the LOA dtd 20-02-2025 issued by the 1st respondent in favour of the petitioner indicated the period of contract as three years from the date of the LOA with a with a further clear stipulation that the said period is extendable for a further period of nine months on mutual consent in line with GeM conditions and the same had been cancelled unilaterally without even providing an opportunity of personal hearing to the petitioner and without issuing a prior show cause notice intimating the petitioner about the proposed cancelation of LOA by the respondent nos. 1 and 2 and calling for explanations from the petitioner specifically referring to the grounds on which the said action was proposed, this court opines that the respondents 1 and 2 had acted hastily in dealing with the subject issue and had passed the order impugned mechanically, erroneously, without application of mind, malafidely."

13. It is submitted that with the above conclusions this Hon'ble court, "in the light of the discussion, reasoning and conclusions arrived

at paras 4 to 12" of its order disposed of the said writ petition, inter alia directing the 1st Respondent to re consider the impugned decision of the 1st and 2nd Respondents, dated 01.04.2025 communicated by email to the petitioner, informing the petitioner that its LOA dated 20.02.2025 and the work order stands cancelled, in accordance with law....."

10. Having considered the respective contentions and

perused the record, it is to be noted that undisputedly LOA was

issued on 20.02.2025, however, the actual work order was

issued only on 12.03.2025, and when respondent-authorities

cancelled the contract on the ground of delay in readying the

barge by petitioner (which is supposed to be within 30 days

from the date of LOA), this Court has held that work order

having been issued on 12.03.2025, cancellation of contract on

21.03.2025 (i.e., within 10 days) is arbitrary, and illegal;

therefore, directed the authorities to reconsider the decision.

The said order has become final.

11. However, it is curious to note that respondent-

authorities, after the alleged re-consideration of the earlier

cancellation decision, has once again passed the impugned

order upholding their previous decision of cancellation on the

very same ground of delay in readying the barge within 30 days

period. A perusal of the impugned order would not reveal any

other legally-tenable ground, except reiterating the very same

stand of delay that has already been adjudicated and answered

in the earlier Writ Petition. At the cost of repetition, this Court

notes that LOA was dated 20.02.2025 and the period of

calculation adopted under LOA is in "days" and not "months",

therefore, when the period of readying the barge is specified as

"30 days", calculation of 30 days commencing from 20.02.2025

would end by 22.03.2025. Therefore, even on this calculation

aspect, the impugned order is liable to be set aside.

12. Further, when once this Court has adjudicated the

earlier cancellation on the ground of delay as illegal and

arbitrary, with a further direction to reconsider the decision,

duly giving petitioner an opportunity of hearing, the action of

the respondent-authority in cancelling the contract of the

petitioner on the very same ground of delay is a blatant violation

of the order of this Court. It is also not the case of respondent

authorities that petitioner is not technically-competent and has

no wherewithal to provide/ready the barge within a stipulated

time. In that view of the matter, the impugned order is liable to

be set aside.

13. Coming to the aspect of maintainability, learned

Senior Counsel Sri G. Vidyasagar contends on behalf of the 2nd

respondent that in matters of contracts / tenders, even if Courts

find that there is total arbitrariness, still Courts should refrain

from interfering and instead relegate the parties to seek damage

and that the attempts by persons / firms such as petitioner

with imaginary grievances wounded pride and business rivalry,

to make mountains out of molehills of some technical /

procedural violation should be resisted. Therefore, balance of

convenience is in favour of the 2nd respondent. In support of his

contention, learned Senior Counsel relied on the renowned

judgment on the subject of the Hon'ble Supreme Court in

N.G.Projects Limited v. Vinod Kumar Jain 1, wherein, it has

been held at para 23 as under:

" In view of the above judgments of this Court, the writ court should refrain itself from imposing its decision over the decision of the employer as to whether or not to accept the bid of a tenderer. The Court does not have the expertise to examine the terms and conditions of the present day economic activities of the State and this limitation should be kept in view. Courts should be even more reluctant in interfering with contracts involving technical issues as there is a requirement of the necessary expertise to adjudicate upon such issues. The approach of the Court should be not to find fault with magnifying glass in its hands,

(2022) 6 SCC 127

rather the Court should examine as to whether the decision-making process is after complying with the procedure contemplated by the tender conditions. If the Court finds that there is total arbitrariness or that the tender has been granted in a mala fide manner, still the Court should refrain from interfering in the grant of tender but instead relegate the parties to seek damages for the wrongful exclusion rather than to injunct the execution of the contract. The injunction or interference in the tender leads to additional costs on the State and is also against public interest. Therefore, the State and its citizens suffer twice, firstly by paying escalation costs and secondly, by being deprived of the infrastructure for which the present day Governments are expected to work."

14. Learned Senior Counsel Sri Vedula Srinivas

appearing on behalf of the 1st respondent also relied on the

judgments of the Hon'ble Supreme Court in Jagdish Mandal v.

State of Orissa 2 and Agmatel India (P) Ltd. v. Resoursys

Telecom 3. He contends that when the power of judicial review

is invoked in matters relating to tenders or award of contracts,

certain special features should be borne in mind. A contract is

a commercial transaction. Evaluating tenders and awarding

contracts are essentially commercial functions. Principles of

equity and natural justice stay at a distance. If the decision

relating to award of contract is bona fide and is in public

interest, courts will not, in exercise of power of judicial review,

(2007) 14 SCC 517

(2022) 5 SCC 362

interfere even if a procedural aberration or error in assessment

or prejudice to a tenderer, is made out. The power of judicial

review will not be permitted to be invoked to protect private

interest at the cost of public interest, or to decide contractual

disputes. The tenderer or contractor with a grievance can

always seek damages in a civil Court. He also submitted that a

Court before interfering in tender or contractual matters in

exercise of power of judicial review, should pose to itself the

following questions: i) whether the process adopted or decision

made by the authority is mala fide or intended to favour

someone; ii) whether public interest is affected. According to the

learned Senior Counsel, the technical evaluation or comparison

by the Court is impermissible, and even if the interpretation

given to the tender document by the person inviting offers is not

as such acceptable to the constitutional Court, that, by itself,

would not be a reason for interfering with the interpretation

given.

15. In the light of the above submissions, it is to be

noted that though this Court does not sit in judicial review in

contractual matters, for the reason that respondent-authorities

requiring execution of a certain work are better equipped to

determine and prescribe the eligibility conditions and

qualifications for a contractor to participate in a particular

tender/contract and execute a given task under the contract.

However, in case of any alleged irregularities in the tendering

process itself, or in providing equal opportunity as per law with

regard to participation in the tendering process, or in observing

the principles of natural justice, the powers of this Court are

broad and it can entertain a Writ Petition to strike down any

such illegal action.

16. In this context, it is to be noted that in this Writ

Petition, this Court is not sitting in determining the eligibility of

petitioner per se to execute the work issued under the LOA; and

admittedly, work order was issued to petitioner after

determining his eligibility. However, the same was cancelled on

the ground of delay in readying the barge for inspection (which

was already adjudicated in an earlier writ petition and held to

be illegal). Therefore, the action of the respondent-authority in

passing the impugned Order, cancelling the contract is a

mechanical exercise and the impugned Order herein was passed

without application of mind and in violation of the Orders

passed by this Court in Writ Petition No.15034 of 2025, wherein

it was specifically held that cancellation of contract of petitioner

on the ground of delay was illegal as the 30-day period has not

expired. Further, this Court has also considered the aspect that

LOA was dated 20.02.2025 and the Work Order was dated

12.03.2025, and the cancellation was dated 21.03.2025, and

after adjudicating the issue, held that such cancellation was

illegal and therefore, the decision requires reconsideration.

17. However, interestingly, the respondent-authorities

quote the very same ground of delay in readying the barge

within 30 days and again passed the same order of cancellation

of tender by way of the impugned order. Therefore, the

impugned order is liable to be set aside. Further, the contention

of learned Senior Counsel for Respondent No.2 that their client

has been performing the contract consequent to cancellation of

tender of petitioner, and that there are interim orders (status

quo) in their favour, cannot be countenanced, for the reason

that the very cancellation of contract of petitioner is illegal, and

further they cannot claim equities on the basis of status quo

orders passed by this Court.

18. Insofar as Respondent No.3 is concerned, the

essential contention is that petitioner was awarded 30% of

contractual work and later Respondent No.3 was awarded 20%

of work and there is no overlap between the works allotted to

petitioner and Respondent No.3. This specific submission has

not been disputed by petitioner.

19. This Court desires to place on record its displeasure

over the manner in which Respondent - Indian Oil Corporation

passed the impugned order. The Corporation being an

instrumentality of the State under Article 12 of the Constitution,

is bound under writ jurisdiction and to comply with the orders

of this Court. It is unexpected from the Corporation to have

passed the impugned proceedings again on the very same

ground that has already been held as untenable in an earlier

Writ Petition.

20. The Writ Petition is therefore, allowed, setting aside

the impugned proceedings dated 06.06.2025. The 1st

respondent is directed to take all the necessary consequential

action to issue the required proceedings permitting petitioner to

carry on its contractual obligations as per LOA and work order

issued as expeditiously as possible, preferably within two weeks

from the date of receipt of a copy of this order. No costs.

21. Consequently, Miscellaneous Applications, if any

shall stand closed.

-------- -----------------------------

NAGESH BHEEMAPAKA, J

07th November, 2025

ksld

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter