Citation : 2023 Latest Caselaw 7001 Raj
Judgement Date : 11 September, 2023
[2023:RJ-JD:28056]
HIGH COURT OF JUDICATURE FOR RAJASTHAN AT
JODHPUR
S.B. Civil Writ Petition No. 1842/2020
M/s. Ummed Construction Company, Through Its Proprietor
Ummed Bishnoi S/o Shri Teja Ram Ji Bishnoi, Aged About 32
Years, Having Registered Office At C-333, Saraswati Nagar, Basni
1St Phase, Jodhpur.
----Petitioner
Versus
1. State Of Rajasthan, Through Principal Secretary,
Government Of Rajasthan Public Health And Engineering
Department, Jaipur.
2. Chief Engineer (Project), Public Health And Engineering
Department, Jodhpur.
3. Superintending Engineer, Public Health And Engineering
Department, Sirohi Circle, Sirohi.
4. Executive Engineer, Public Health And Engineering
Department, Sirohi Circle, Sirohi.
----Respondents
For Petitioner(s) : Mr. Sajjan Singh Rathore
For Respondent(s) : Mr. Pankaj Sharma, AAG with
Mr. Rishi Soni
HON'BLE DR. JUSTICE NUPUR BHATI
JUDGMENT
Judgment Reserved on <><><> 04/09/2023 Date of Pronouncement <><><> 11/09/2023
1. The instant writ petition has been filed by the petitioner-M/s.
Ummed Construction Company, through its Proprietor Ummed
Bishnoi, under Article 226 of the Constitution of India with the
following prayers:-
"A. By an appropriate writ, order, or directions, the order dated 07.01.2020 (Annex.9), recovery notice dated
[2023:RJ-JD:28056] (2 of 16) [CW-1842/2020]
28.01.2020 (Annex.11) and any notice, order or communication already passed or passed during pendency of the writ petition in pursuance to the order dated 07.01.2020 (Annex.9) may kindly be quashed and set aside.
B. By an appropriate writ, order or directions, any NIT if already issued or issued during the pendency of the writ petition in pursuance to the Order dated 07.01.2020 (Annex.9) for getting the remaining work done at the risk and cost of the petitioner company may kindly be quashed and set aside.
C. By an appropriate writ, order or directions, the respondents may kindly be directed to execute the agreement/contract in pursuance to the work order dated 15.12.2018 (Annex.2) and also to make available the lay out plans for the awarded work.
D. By an appropriate writ, order or directions, the respondents may kindly be restrained from taking any action against the petitioner company for stopping the work, awarded in pursuance to the order dated 15.12.2018 (Annex.2)."
2. With the consent of learned counsel representing the parties,
the matter is heard finally and is being decided today itself.
3. Brief facts of the case are that the petitioner, a proprietor
firm, applied in the NIT No.2018-2019/128 for the work of
'Providing Laying Jointing and Commissioning of various sizes
HDPE Pipeline, other allied works under UWSS Sirohi against Old
and Polluted Pipe Line.' The petitioner-company being the lowest
bidder, was issued the work order dated 15.12.2018 with a
condition that the petitioner-company should execute the formal
[2023:RJ-JD:28056] (3 of 16) [CW-1842/2020]
agreement with a non-judicial stamp of Rs.12,180/- on receipt of
this letter and further that the date of commencement of the work
will be the date of issuance of the order i.e. 15.12.2018 and the
date of completion was the date after two months from the date of
commencement, meaning thereby that the petitioner-company
was required to complete the said work within a period of two
months.
4. In the work order, it was also mentioned that the work is to
be started within ten days of the passing of the order or else, it
will be get done from the other party at the risk and cost of the
petitioner-company. The petitioner-company immediately
contacted the office of the respondent-Executive Engineer for
execution of formal agreement, but due to unavoidable
circumstances and the occupation of the office in some other
work, formal agreement was not executed.
5. The petitioner-company started working in pursuance of the
work order dated 15.12.2018. The formal agreement was not
executed even after about one and a half month and therefore,
the petitioner-company stopped the work and requested the
respondent to execute the formal agreement.
6. The respondents issued communication dated 07.02.2019
and 14.02.2019 (Annexure-3) to the petitioner-company to
complete the work. The petitioner approached the respondents
and requested them to execute the formal agreement in order to
start the work but no action whatsoever was taken in this regard.
[2023:RJ-JD:28056] (4 of 16) [CW-1842/2020]
The petitioner-company made a communication dated 12.04.2019
(Annexure-4) to the respondents that the rates which are being
reserved are not proper and therefore, the work order may be
cancelled. The petitioner-company again started the work upon
the assurance of the respondents that soon, the agreement would
be executed but when the agreement was not executed, the
petitioner-company again stopped the work on 14.06.2019.
7. The petitioner-company was issued several notices dated
16.09.2019, 19.09.2019, 14.10.2019 and 22.10.2019 (Annexure-
5), mentioning in it that the petitioner-company should start the
work and if the work is not started, then, the action as per clause
2 and 3 of the agreement/contract would be initiated. The
petitioner-company, again approached the respondents and
requested them to execute the formal agreement, but, despite
such request, the respondents issued final notice dated
29.11.2019 (Annexure-6), calling upon the petitioner to submit
reply in reference to the proposed action as per clause 2 and 3 of
the contract, or else, ex-parte proceedings would be initiated
against the petitioner-company.
8. The petitioner-company submitted the reply dated
12.12.2019 to the notice dated 29.11.2019, stating therein that
the petitioner-company was ready to perform the work and the
same was stopped as the formal agreement was not executed
between the parties. The respondents made a communication
dated 03.01.2020 amongst themselves while informing that the
petitioner-company has done the work of about Rs.1,03,653/- till
[2023:RJ-JD:28056] (5 of 16) [CW-1842/2020]
14.06.2019 and thereafter, the work was stopped and despite
several notices, the petitioner-company did not start the work
again and thus, the respondents proposed to take action against
the petitioner-company.
9. The respondent No.3-Superintending Engineer, passed an
order dated 07.01.2020 (Annexure-9) against the petitioner-
company and imposed penalty of Rs.4,76,764.61/- i.e. 10% of
remaining work of Rs.47,67,646.10/- and also directed to get the
remaining work done at the risk and cost of the petitioner-
company after issuing fresh NIT. The petitioner-company
submitted a representation dated 16.01.2020 (Annexure-10), but
the respondent No.4-Executive Engineer, vide recovery notice
dated 28.01.2020 (Annexure-11), directed the petitioner-company
to deposit the penalty amount in light of the order dated
07.01.2020, within 7 days and thus, the petitioner-company being
aggrieved of the impugned orders viz. 07.01.2020 (Annexure9)
and 28.01.2020 (Annexure-11), preferred the present writ
petition.
10. Learned counsel Mr. Sajjan Singh Rathore, appearing for the
petitioner, made following submissions that:-
(a) The action taken against the petitioner-company, is based on
the clauses and conditions of the agreement which was not
executed on a proper paged stamp duty and thus, in the absence
of any agreement having signatures of both the parties, the action
of the respondents is not sustainable.
[2023:RJ-JD:28056] (6 of 16) [CW-1842/2020]
(b) The petitioner-company on various occasions made a request
to the respondents to execute the formal agreement, but the
respondents did not pay any heed to it and despite the same not
being executed, the petitioner-company started the work on two
occasions but as the formal agreement was not executed, the
petitioner-company had no choice but to stop the work on
14.06.2019.
(c) The respondents in the notices dated 16.09.2019,
19.09.2019, 14.10.2019 and 22.10.2019, have not pointed out
anywhere that the agreement has not been executed, despite
that, the petitioner-company had been requested for execution of
the formal agreement time and again whereas, in all the notices,
the respondents have simply stated that the work has been
stopped by the petitioner-company but the particular reason for
stopping the work has not been mentioned.
(d) In accordance with clause 25.1 of the Tender Document
(Annexure-1), it is mandatory that the successful bidder shall sign
the contract agreement within ten days of the department notice,
but the respondents have failed to sign the contract agreement
with the petitioner-company.
(e) Under clause 25.1, only following documents can be
considered as a contract agreement i.e. agreement placed as
Annexure-3 in the tender document, letter of award and the bid
documents with all addendum contained in it. But in the present
case, as the agreement has not been signed between the parties,
therefore, the respondents could not have initiated proceedings
[2023:RJ-JD:28056] (7 of 16) [CW-1842/2020]
against the petitioner-company under clause 2 and 3 of the
contract agreement.
(f) The clause 26.3 of the tender document, stipulates that it
was mandatory upon the respondents to execute the agreement
with the petitioner-company and it was a prerequisite condition
and without fulfilling the prerequisite condition, the respondents
could not have initiated the proceedings against the petitioner-
company by imposing penalty and getting the remaining work
done at the risk and cost of the petitioner-company by third party.
(g) Learned counsel for the petitioner submitted that as per
Article 299 of the Constitution of India, the respondents were
under an obligation to execute the agreement on behalf of Hon'ble
the Governor of Rajasthan, but the respondents have failed to do
so.
11. Learned counsel for the petitioner placed reliance upon the
judgment rendered by Hon'ble Apex Court in the case of State of
Punjab Vs. Om Prakash Baldev Krishan reported in 1988 64
CCC 817, decided on 23.08.1988. Relevant portion of the said
judgment is reproduced hereinbelow:-
"This Court reiterated that under that section a contract entered into by the Governor of a Province must satisfy three conditions, namely, (i) it must be expressed to be made by the Governor; (ii) it must be executed; and (iii) the execution should be by such persons and in such manner as the Governor might direct or authorise. These three conditions are required to be fulfilled. This position was reiterated by this Court again in Seth Bikhraj Jaipuria v.
Union of India, (1962) 2 Scr 880: (air 1962 Se 113). This Court explained that three conditions as mentioned in State of Bihar v. Karam Chand Thapar (air 1962 Sc 110) (supra)
[2023:RJ-JD:28056] (8 of 16) [CW-1842/2020]
had to be fulfilled, and further reiterated that the object of enacting these provisions was that the State should not be saddled with liability for unauthorised contracts and, hence, it was provided that the contracts must show on their faces that these were made by the Governor-General and executed on his behalf in the manner prescribed by the person authorised. It is based on public policy. No question of waiver arises in such a situation. If once that position is reached, and that position is well-settled by the authorities over a long lapse of time, no question of examining the purpose of this requirement arises. In Union of India v. A.1. Rallia Ram (1964) 3 Ser 164 (air 1963 Sc 1685), this Court again reiterated that the agreement under arbitration with the Government must be in accordance with section 175(3) of the Government of India Act, 1935. These principles were again reiterated by this Court in Timber Kashmir Pvt. Ltd. v. Conservator of Forests, Jammu, (1977) 1 Scr 937: (air 1977 Sc 151). There, the Court was concerned with section 122(1) of the Jammu & Kashmir Constitution which corresponded to Article 299(1) of the Constitution of India. In that case all the three applications filed by the respondent State for a reference to an arbitrator under section 20 of the Jammu & Kashmir Arbitrator Act, were dismissed by a single Judge of the Jammu & Kashmir High Court on the ground that the arbitration clause was, in each case, a part of an agreement which was not duly executed in accordance with the provisions of section 122(1) of the Jammu & Kashmir Constitution which corresponded to those of Article 299(1) of the Constitution of India. But the Division Bench allowed the appeals holding that if contracts were signed by the Conservator of Forests in compliance with an order of the Government, the provisions of section 122(1) of the Jammu & Kashmir Constitution could not be said to have been infringed. This Court held that the contract could not be executed without the sanction. Nevertheless, if the sanction could be either expressly or impliedly given by or on behalf of the Government, as it could, and, if some acts of the Government could fasten some obligations upon the Government, the lessee could also be estopped from questioning the terms of the grant of the sanction even where there is no written contract executed to bind the lessee. But, once there had been a valid execution of lease by duly authorised officers, the documents would be the best evidence of sanction. In that case, the contracts were executed on behalf of the Government of Jammu and Kashmir. The only question with which the Court was concerned in that case was whether the contracts executed by duly authorised officials had been proved or not. It was held that it was so proved."
[2023:RJ-JD:28056] (9 of 16) [CW-1842/2020]
12. Learned counsel for the petitioner, thus, urged, that the writ
petition deserves to be dismissed and the impugned orders dated
07.01.2020 (Annex.9) and 28.01.2020 (Annex.11) may be
quashed and set aside.
13. Per contra, Mr. Pankaj Sharma, learned AAG assisted by Mr.
Rishi Soni, Advocate, vehemently opposed the submissions
advanced by the petitioner's counsel and made following
submissions that:-
(a) The petitioner-company raised the issue of alleged non-
execution of the agreement only after issuance of final notice
dated 19.11.2019 and prior to that, the petitioner-company never
came to the respondents for execution of the formal agreement so
much so, that the petitioner-company at the midst of the work,
asked for cancellation of the work order while raising objection
regarding the reserved rates by way of submitting an application
placed on record as Annexure-4 dated 12.04.2019.
(b) The said stand of the petitioner-company reveals the
intention and the fact that the petitioner-company was having the
complete knowledge and understanding that the letter of
acceptance and other documents, form a binding contract between
petitioner-company and the person authorized and there was no
valid reason that the petitioner-company stopped the work and
thus, to escape the consequential liabilities for non-completion of
the work, the petitioner-company has admitted to take undue
benefits while concocting false and cooked up story.
[2023:RJ-JD:28056] (10 of 16) [CW-1842/2020]
(c) The writ petition is liable to be dismissed as it has been
specifically stated in the writ petition that the formal agreement
has not been executed in regard to the work in question, which is
in itself false and no such ground exists in the matter as terms of
the tender document as well as the letter of acceptance are clear
and the two documents together constituted a binding contract
agreement to which, a number has also been allotted in favour of
the petitioner-company as 117/2018-19 and thus, there was no
requirement of a formal agreement to be executed between the
petitioner-company and the respondents.
(d) The objection raised by the petitioner-company before
issuance of final notice dated 29.11.2019, is only in respect to the
rates and thee is no whisper regarding the non-execution of
formal agreement between the parties and the petitioner-company
has also not placed on record any document whatsoever to
substantiate that the petitioner-company took the necessary steps
for execution of the formal agreement.
(e) The letter of acceptance (Annexure-2) also mentions the
duration of the period during which, the said work ought to have
been completed by the petitioner-company which is :-
"(a) Stipulated Dt. of commencement date of issue of this order.
(b) Stipulated Dt. of completion 02 (Two) Month after stipulated Dt. Of Commencement.
The work is to be started immediately, so in case of work is not started with in 10 days from date of issue of this order then it will allotted to other party on your risk and cost."
[2023:RJ-JD:28056] (11 of 16) [CW-1842/2020]
The petitioner-company though, started the work in time but
failed to complete the same within the stipulated time period of
two months and the letter dated 07.09.2019 issued by the Office
of Assistant Engineer, PHED, Sub-Division, Sirohi, reflected that
upon such non-completion of the said work by the petitioner-
company, it was causing grave inconvenience to the public at
large.
(f) The petitioner-company was served upon various
notices/letters, but the petitioner-company never replied to the
said notices/letters and never raised any objection that upon non-
execution of the formal agreement between the parties, the
petitioner-company had stopped the said work. The petitioner-
company chose to remain silent even after issuing various number
of notices (Annexure-5) and the impugned orders dated
07.01.2020 (Annexure-9) and 28.01.2020 (Annexure-11), were
passed after affording the petitioner-company a reasonable
opportunity of hearing and despite the fact that the period of
completion of the work order was over, the petitioner-company
was given several opportunities to complete the work order, but
the petitioner-company did not complete the same.
Learned AAG, thus, urged, that the writ petition deserves to
be dismissed with costs.
14. Heard learned counsel representing the parties as well as
perused the material available on record.
[2023:RJ-JD:28056] (12 of 16) [CW-1842/2020]
15. This Court finds that the petitioner-company was duly issued
the letter of acceptance (Annexure-2) dated 15.12.2018 wherein,
it was categorically stipulated that the said work was to be started
immediately within ten days from the date of issue of the order
dated 15.12.2018 or else, it will be allotted to other party at the
risk and cost of the petitioner-company. Also, in the said order
dated 15.12.2018, it was categorically mentioned that the said
work has to be completed within the stipulated time period of two
months. Undoubtedly, the petitioner started the said work well
within time. Though, the formal agreement on non-judicial stamp
paper of Rs.12,180/- was not executed between the petitioner-
company and the respondents but the petitioner company utterly
failed to complete the allotted work within the stipulated time
period.
16. It has been vehemently submitted by the learned counsel for
the petitioner that the petitioner-company time and again,
requested the respondents to execute the formal agreement so
much so, that the petitioner-company also personally approached
the respondents requesting them for the execution of the formal
agreement, but no heed was paid by the respondents. It has also
been contended that the petitioner-company stopped the work
and again started the work upon the verbal assurance of the
respondents that soon the agreement would be executed but the
work was again stopped on 14.06.2019 upon non-execution of the
agreement. The petitioner-company in order to substantiate the
steps taken by it, has not placed on record any document in order
[2023:RJ-JD:28056] (13 of 16) [CW-1842/2020]
to show that repeatedly, it requested the respondents to execute
the agreement and no action was taken by them and therefore,
the petitioner-company was left with no option but to stop the
work.
17. It is also seen that the respondents issued several notices to
the petitioner-company which have been placed on record as
Annexure-5 whereby, the petitioner-company was repeatedly
cautioned to complete the work and in the notice dated
16.09.2019, it has also been mentioned that vide letter dated
03.06.2019, issued by the Assistant Engineer, PHED, Sirohi, the
petitioner-company was directed to get the measurements of the
work done by him, but neither the petitioner-company was
present nor its representative for getting the measurement of the
said work done.
It is an admitted fact that despite several notices being
served upon the petitioner-company for completing the work
within a period of 15 days from the issuance of such notices, the
petitioner-company neither completed the work, nor showed its
inability to complete the work on the ground of non-execution of
the agreement, nor bothered to respond to the notice dated
16.09.2019, showing its or its representative's inability to get the
measurements of the work done by it. It is also important to note
that despite stipulated period of two months being over, the
respondents gave several opportunities to the petitioner-oompany
by way of repeated notices (Annexure-5) to complete the work but
the petitioner-company did not avail the said opportunities and left
[2023:RJ-JD:28056] (14 of 16) [CW-1842/2020]
the work incomplete. The petitioner-company was served upon the
final notice dated 29.11.2019 (Annexure-6), by the respondents
for submitting its explanation in regard to violation of the
condition No.2 and 3 of the contract and it was for the first time
that the petitioner-company responded to the said final notice by
filing reply dated 12.12.2019 (Annexure-7) stating therein that
the petitioner had stopped the said work as there was no
agreement entered between the petitioner and the respondents.
Thereafter, the respondent No.4-the Executive Engineer vide
communication dated 03.01.2020 (Anenxure-8) directed the
respondent No.3-the Superintending Engineer to take appropriate
action against the petitioner-company upon non-completion of the
said work, a copy of which was duly sent to the petitioner-
company as the same has not been denied.
18. The petitioner-company did not respond to the said
communication dated 03.01.2020 (Annexure-8), as nothing has
been placed on record, even though, the petitioner received a
copy of the said communication. This fact also cannot also be
ignored that the petitioner himself had written a letter to the
respondents dated 12.04.2019 (Annexure-4), requesting the
respondents to cancel the work order on the ground that the
reserved rates were improper. The said communication is
reproduced hereinbelow:-
"दिनां क : 12.04.19
श्रीमान अधिशाषी अभियन्ता
जन स्वा० अभि० विभाग
सिरोही
[2023:RJ-JD:28056] (15 of 16) [CW-1842/2020]
विषय :- आपके द्वारा दिया गया कार्य आदे श सं . 4821/2013-1 15.12.2018 के बारे में
उपरोक्त निवे दन है कि मेरी फर्म सं . UWES Sirohi against old and Polluted Pipe Lines का कार्य डाला था। जो की इस टे ण्डर से दरें गलत रक्षित हो गई थी जो की दरें कार्य करने से उचित दर नही ं है । अतः कार्य आदे श को निरस्त करवाने के आदे श करावे।
सही /-"
The said communication reflects that the petitioner was not
inclined to complete the work order allotted to it, as the
petitioner-company found the reserved rates to be improper and
thus, requested the respondents to cancel the said work order and
later on, while realizing the consequences of not discharging the
liability of completing the work order within the stipulated period
of two months, the petitioner took altogether a different stand
that the said work was not completed on account of the non-
execution of the agreement between the petitioner-company.
19. The respondents while issuing several notices to the
petitioner-company placed on record as Annexure-5, granted the
petitioner various opportunities to complete the said work despite
the fact that the period of two months had elapsed way back in
the month of 'February, 2019', but the petitioner-company neither
respondent any of the notices, nor completed the said work. This
fact also cannot be ignored that the respondents had also brought
to the notice of the petitioner-company that upon non-completion
of the said work, the people residing therein, were facing grave
hardship, as a regular water supply could be made available, but
the petitioner-company did not bother and chose not to complete
the allotted work.
[2023:RJ-JD:28056] (16 of 16) [CW-1842/2020]
20. In view of the above discussion, I do not find any merit in
the instant writ petition, and the same is, thus, dismissed. Stay
application as well as all other pending applications, if any, also
stand dismissed.
(DR. NUPUR BHATI),J
Devesh Thanvi/-
Powered by TCPDF (www.tcpdf.org)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!