Citation : 2023 Latest Caselaw 9023 Raj
Judgement Date : 3 November, 2023
[2023:RJ-JD:33410-DB]
HIGH COURT OF JUDICATURE FOR RAJASTHAN AT JODHPUR D.B. Civil Misc. Appeal No. 1481/2019
1. Executive Engineer, Survey And Investigation, Lift Division First, Ignp Rawatsar
2. The State Of Rajasthan, Through District Collector, Hanumangarh.
----Appellants Versus M/s Ashok Kumar, Contractor, 265 Durga Colony, Hanumangarh.
----Respondent
For Appellant(s) : Mr. Pankaj Sharma, AAG with
Mr. Deepak Chandak
For Respondent(s) : Mr. V.K. Aggarwal
Mr. Dalpat Singh Solanki
HON'BLE MR. JUSTICE VIJAY BISHNOI
HON'BLE MS. JUSTICE REKHA BORANA
Judgment
03/11/2023
(PER HON'BLE MS. JUSTICE REKHA BORANA)
1. The present appeal has been preferred against the order
dated 22.01.2019 passed by the Commercial Court, Jodhpur
(hereinafter referred to as 'the learned Court below') in Civil Misc.
'A' Case No.47/2018 (NCV No.31/2018) whereby the objections
under Section 34 of the Arbitration and Conciliation Act, 1996 (for
short 'the Act of 1996') preferred by the appellants against the
award dated 30.07.2016 passed by learned Arbitrator have been
rejected. Vide the award, the learned Arbitrator had proceeded on
to pass an award for an amount of Rs.30,23,450/- in favour of the
claimant-firm with interest @ 9% per annum till the date of award
which, the non-claimant was directed to pay within 3 months
failing which, further interest was awarded @ 9% per annum till
[2023:RJ-JD:33410-DB] (2 of 11) [CMA-1481/2019]
the date of actual payment. The counter claim as preferred by the
respondent State was rejected.
2. Before proceeding on merits of the present appeal, it is
relevant to note that an application under Order 6 Rule 17 of the
Code of Civil Procedure for amendment of the present appeal and
an application under Order 41 Rule 27, CPC with a prayer for
taking certain documents on record have been filed by the
appellants. Replies to both the applications have been filed on
behalf of the respondents.
Vide order dated 01.04.2022, it was observed that both the
applications would be considered at the time of admission/hearing
of the appeal.
3. So far as the application under Order 6 Rule 17, CPC is
concerned, this Court does not find any ground to entertain the
same for the following reasons :
Firstly, the present is in effect an appeal under Section 37
of the Act of 1996, assailing the order whereby the objections
under Section 34 of the Act of 1996, as preferred by the
appellant-State, had been rejected. As it is the settled position of
law, the scope of interference under Section 34 of the Act of 1996
is very narrow and limited and that under Section 37 is far more
narrower. When the scope of interference in the award as passed
by the Arbitrator itself is limited to the extent of the grounds as
provided under Section 34 of the Act of 1996, the scope to permit
amendment of the present appeal so as to add additional grounds
[2023:RJ-JD:33410-DB] (3 of 11) [CMA-1481/2019]
qua the claims as raised by the claimant-contractor, cannot even
be imagined of.
Secondly, the new grounds as sought to be added in the
present appeal vide the amendment application clearly pertain to
the facts which were not pleaded during the arbitral proceedings.
Further, all the grounds as sought to be raised now are totally
factual in nature. The facts, in terms of law, are not only to be
pleaded but even to be proved. Admittedly, the new facts/grounds
sought to be added vide amendment application were not pleaded
before the Arbitrator and hence were not proved on record.
Therefore, the same cannot be permitted to be raised at this
stage.
The application is therefore, rejected.
4. The application under Order 41 Rule 27, CPC also cannot be
entertained as the documents sought to be brought on record vide
the said application are the ones which were although in
possession of the Department during the arbitral proceedings, but
were not placed on record at that point of time. It is not the case
of the Department that these documents were not in their
possession during the arbitral proceedings. The Department,
having participated in and contested the complete arbitral
proceedings and having even raised objections against the arbitral
award before the Commercial Court, cannot, now at this stage, be
permitted to place on record the documents which were never
even a part of the arbitral proceedings. This Court, in its limited
[2023:RJ-JD:33410-DB] (4 of 11) [CMA-1481/2019]
scope under Section 37 of the Act of 1996, cannot permit any
such document to be taken on record in excess of jurisdiction.
The application under Order 41 Rule 27, CPC is therefore,
rejected.
5. Before proceeding on to the merits of the present appeal,
having perused the judgment passed by the Commercial Court, it
is relevant to take note of the fact that no reason worth the name
has been indicated by the Commercial Court for not accepting the
contentions raised by the appellants. The judgments as relied
upon by the Commercial Court while dealing with the scope of
Section 34 of the Act of 1996, no where prescribe that any order
can be passed by the Court dealing with the objections under
Section 34 of the Act of 1996 in a wholly cursory and slipshod
manner without even dealing with any of the objections as raised
by the objector.
This Court is of the clear opinion that the manner in which
the impugned judgment has been passed by the Commercial
Court cannot be appreciated.
6. Coming to the merits of the present appeal, the facts of the
case are as under:
(A.) Agreement No.10 of 1995-96 was entered into between
appellant no.1 and respondent firm for "Earth Work Excavation
and Double Tile Lining of Sahwa Lift Canal from Km 54.750 -
56.200". The stipulated date for commencement of work was
13.05.1995 and for completion of work was 12.02.1996. However,
there was a delay and the actual date of completion of work was
[2023:RJ-JD:33410-DB] (5 of 11) [CMA-1481/2019]
20.08.2002 and the said delay gave rise to dispute between the
parties.
(B.) Claimant-firm invoked the arbitration clause of the contract
and preferred an application under Section 11(6) of the Act of
1996 before the High Court for appointment of arbitrator. For
resolution of disputes as arisen, the sole arbitrator was appointed
vide order dated 13.11.2013.
(C.) The learned Arbitrator entered into reference and vide the
Award dated 30.07.2016, proceeded on to allow six claims and
reject two claims out of the eight claims raised by the claimant.
The counter-claim as preferred by the appellants was rejected.
(D.) Against Award dated 30.07.2016, the appellants preferred
objections under Section 34 of the Act of 1996 which were
dismissed vide order dated 22.01.2019 of the Commercial Court,
Jodhpur against which the present appeal has been preferred.
7. A brief detail of the claims as raised and the amount as
awarded, is reproduced herein:
Claim Brief description of Claim Amount Amount
No. claimed Awarded
1 Claim qua extra element for Rs.1,38,000/- Nil
placement of excavated earth at
distant place
2 Claim towards cartage of sand from Rs.33,38,240/- Rs.22,85,690/-
½ Km length
3 Claim towards hike in rates for Rs.1,33,500 Rs.54,000
execution of lining work in 600-meter
length after 5/97 because
department itself had increased the
Basic Schedule of rates
4 Claim on account of tiles consumed Rs.4,97,750 Nil
in 600-meter lining work done after
[2023:RJ-JD:33410-DB] (6 of 11) [CMA-1481/2019]
5 Claim for 82 MT coal which should Rs.1,18,900 Rs.1,18,900
have been given to claimant
contractor in view of norms fixed by
the Chief Engineer IGNP, Bikaner
being old coal and found having less
calorific value
6 Claim for final bill amount duly Rs. 2,88,272/- Rs. 2,88,272/-
passed and kept in deposit by non-
claimant without any notice to
claimant firm
7 Claim towards cartage of Bajri from Rs. 12,900/- Rs. 7,334/-
distant source which was not
available at site stipulated in
agreement
8 Claim towards S.D. deductions made Rs. 2,69,254/- Rs. 2,69,254/-
TOTAL Rs. 30,23,450/-
8. The sole ground raised by learned Additional Advocate
General Mr. Pankaj Sharma appearing for the appellant State
before this Court is that claim Nos.2 & 3 as awarded by learned
Arbitrator are totally erroneous as while computing the amount of
award qua the said claims, the learned Arbitrator applied BSR Rate
approved by the department subsequently in the year 1997.
Learned Arbitrator relied upon the BSR Rates of year 1997
whereby the rates were increased from 25% to 30% keeping in
view the hike in basic rates. Learned AAG submitted that
increased BSR Rates could not have been applied in the present
matter as the agreement in question pertains to the year 1995-96
and the BSR Rates as applicable on the date of acceptance of the
tender could only have been applied while computing the award
qua the claims. The subsequent enhanced rates, if any, could not
have been applied qua the agreement of year 1995-96.
9. Responding to the argument of learned counsel for the
appellants, learned counsel for the respondent submitted that
[2023:RJ-JD:33410-DB] (7 of 11) [CMA-1481/2019]
admittedly, there was a price escalation clause in the agreement
being Clause No.45. The claimant contractor was very well entitled
for the escalation amount due to hike in rates of labour. As the
amount was not claimed by the contractor qua the price/labour
escalation clause, it was very much entitled for the award amount
keeping into consideration the enhanced BSR Rates. Learned
counsel submitted that had the price escalation formula as
provided under Clause 45 been applied, the award amount would
have been far more than what has been awarded by learned
Arbitrator applying the enhanced rates of BSR. Therefore,
approach of learned Arbitrator was perfectly in consonance with
law and the amount as awarded qua claim Nos.2 & 3 deserves to
be affirmed.
10. In the alternate, learned counsel submitted that even if the
ground as raised by learned counsel for the appellants is accepted,
the award amount qua claim Nos.2 & 3 can only be modified to a
certain extent but cannot be set aside as a whole. He submitted
that the accepted rate for earth work excavation and cartage was
Rs.29.97 per cum and calculating the amount for 62,000 cum
excavation and cartage work, it would come to Rs.18,58,140/-
whereas the claim as awarded by learned Arbitrator is for
Rs.22,85,690/-. Therefore, the award amount qua claim No.2,
even if to be modified, has to be affirmed for Rs.18,58,140/-.
11. Heard learned counsel for the parties and perused the
material available on record.
12. Admittedly, the agreement in question was entered into in
the year 1995-96 (Agreement No.10 of 1995-96). The said
agreement was executed after the bid/tender of the contractor
[2023:RJ-JD:33410-DB] (8 of 11) [CMA-1481/2019]
being accepted on the rates as quoted by him. Meaning thereby,
the work contract was granted to the contractor on the rates as
specified in the agreement. If any contractor wishes to claim any
amount qua increase in price of material/labour component, the
same has to be raised in terms of Clause 45 of the agreement.
Once the claim qua price/labour escalation is raised, the
entitlement for the same in terms of Conditions specified in Clause
45, has to be proved before the learned Arbitrator and the learned
Arbitrator, after reaching to a finding that the contractor is entitled
to such escalation amount, would proceed on to award the same
in favour of the contractor.
Admittedly, in the present case, no claim for price/labour
escalation in terms of Clause 45 of the agreement was raised
before the learned Arbitrator. Once it is found that no claim qua
the price escalation was raised, the learned Arbitrator could not
have granted the same in the garb of the increased rates of BSR
and that too, on the rates which came into effect only in the year
1997.
13. As it is the settled position of law, arbitration is an outcome
of the agreement executed between the parties. The Arbitrator,
who derives its authority from the contract, is bound by the terms
of the same. The arbitral proceedings are governed by the
conditions of the contract as entered into between the parties and
the Arbitrator is also bound by the same. The Arbitrator cannot
travel beyond the contract and scope of his jurisdiction is limited
to the conditions of the contract which govern the parties.
[2023:RJ-JD:33410-DB] (9 of 11) [CMA-1481/2019]
14. In the matter of Steel Authority of India Limited vs. J.C.
Budharaja ;(1999) 8 SCC 122, the Hon'ble Supreme Court
observed as under :
"It was not open to the arbitrator to ignore the said conditions which are binding on the contracting parties. By ignoring the same, he has acted beyond the jurisdiction conferred upon him.
It is settled law that arbitrator derives the authority from the contract and if he acts in manifest disregard of the contract, the award given by him would be arbitrary one. This deliberate departure from the contract amounts not only to manifest disregard of the authority or misconduct on his part, but it may tantamount to mala fide action."
15. In Bharat Coking Coal Ltd. vs. Annapurna Construction;
(2003) 8 SCC 154, the Hon'ble Apex Court observed as under :
"22. There lies a clear distinction between an error within the jurisdiction and error in excess of jurisdiction. Thus, the role of the arbitrator is to arbitrate within the terms of the contract. He has no power apart from what the parties have given him under the contracts. If he has travelled beyond the contract, he would be acting without jurisdiction, whereas if he has remained inside the parameter of the contract, his award cannot be questioned on the ground that it contains an error apparent on the face of the records."
16. Applying the above ratio to the present matter, as observed
above, although there was a price escalation clause in the
[2023:RJ-JD:33410-DB] (10 of 11) [CMA-1481/2019]
agreement, no claim qua the same was raised by the claimant.
The claim, when not raised in terms of the contract, would be
deemed to have been waived. There was no other term/clause
available in the agreement which could entitle the claimant for
payment at enhanced rates. Therefore, in absence of any
term/clause in the agreement, there was no reason whatsoever
available to the Arbitrator to award the claim qua work done at the
escalated rates.
Moreover, the rates as applied by the Arbitrator came into
effect in the year 1997 and the said rates could definitely not have
been applied qua the agreement executed in the year 1995-96. In
the specific opinion of this Court, the award qua claim Nos.2 & 3
on enhanced BSR Rates by the Arbitrator was definitely beyond
the terms of the contract and hence cannot be affirmed to that
extent. The award in question qua claim Nos.2 & 3, hence,
deserves to be modified as the same could have been awarded
only at the accepted rates i.e. Rs.29.97 per cum.
17. In view of the above analysis, amount of Rs.22,85,690/- as
awarded by the Arbitrator qua claim No.2 deserves to be modified
to Rs.18,58,140/-. So far as the award amount of Rs.54,000/- qua
claim No.3 is concerned, the same is set aside and the award
amount qua claim No.3 is quantified to be NIL.
So far as the award qua other claims and award of interest is
concerned, this Court does not find any ground to interfere with
the same and are hence affirmed.
18. No ground qua the rejection of the counter claim of the
appellant State has been raised before this Court and hence, the
award to that extent is hereby, affirmed.
[2023:RJ-JD:33410-DB] (11 of 11) [CMA-1481/2019]
19. As observed at the inception, the Commercial Court passed
the order impugned dated 22.01.2019 without assigning any
reason whatsoever. The agreement in question relates to the year
1995-96 and the arbitral proceedings pertain to the year 2013,
hence this Court, instead of remanding the matter back to the
Commercial Court, in the interest of justice, proceeded on to
modify the award in question.
20. In view of above analysis, the present appeal is partly
allowed. The impugned order dated 22.01.2019 and award dated
30.07.2016 are hereby modified to the extent that the claimant-
contractor would be entitled for an amount of Rs.18,58,140/- qua
claim No.2 and an amount of NIL qua claim No.3. The award qua
other claims and the interest amount is hereby affirmed. The
award qua rejection of the counter claim of the appellant State is
also affirmed.
21. The stay petition and the pending applications, if any, also
stand disposed of.
(REKHA BORANA),J (VIJAY BISHNOI),J
Vij/-
Powered by TCPDF (www.tcpdf.org)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!