Tuesday, 19, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Onkar Plaster Decorations ... vs Urban Improvement Trust
2022 Latest Caselaw 6066 Raj/2

Citation : 2022 Latest Caselaw 6066 Raj/2
Judgement Date : 7 September, 2022

Rajasthan High Court
M/S Onkar Plaster Decorations ... vs Urban Improvement Trust on 7 September, 2022
Bench: Pankaj Bhandari
           HIGH COURT OF JUDICATURE FOR RAJASTHAN
                       BENCH AT JAIPUR

                 S.B. Arbitration Application No. 17/2022

M/s    Onkar      Plaster    Decorations          Works,           (Registered       Govt.
Contractor) 642, Joshi Road, New Delhi-110005 Through K.v.
Singh.
                                                                            ----Applicant
                                       Versus
1.         Urban Improvement Trust, Bhilwara Through Secretary,
           Ajmer Road Bhilwara Raj.
2.         The Executive Engineer, Office Of Urban Improvement
           Trust Road Bhilwara.
                                                                     ----Respondents
For Applicant(s)            :     Mr. Sharad Purohit
For Respondent(s)           :     Mr. Nitin Sinsinwar



              HON'BLE MR. JUSTICE PANKAJ BHANDARI

                                       Order

RESERVED ON                               ::                            01/09/2022
PRONOUNCED ON                             ::                            07/09/2022


1. The applicant has filed this arbitration application under

Sections 10 & 11 of the Arbitration and Conciliation Act, 1996

(hereinafter referred to as "the Act") seeking appointment of an

arbitrator.

2. It is pleaded in the arbitration application that the

respondents-non-applicants floated a tender for a sum of

Rs.39,82,694/- for Acoustic Treatment in the auditorium, namely,

Rajeev Gandhi Auditorium, RC Vyas Colony, Bhilwara. The

applicant was awarded the entire contract work. The applicant

completed the entire work entrusted to him within the stipulated

time before 02.08.2011 and requested for final measurement of

(2 of 5) [ARBAP-17/2022]

the said work in the non-applicants' mathematical book. It is also

pleaded that the applicant also submitted a completion certificate

dated 02.08.2011 in the month of August, 2011 itself. The non-

applicants did not pay any heed to the repeated requests and

reminders and did not prepare any of the final bills till 2017.

Eighth and final bill was submitted, but the non-applicants did not

pay the amount. It is further pleaded that Clause 5.11 in the

tender document for Acoustical Treatment in the

Auditorium/Indoor Stadium is the Arbitration Clause.

3. It is contended that when even after preparation of the final

bill, payment was not made. The applicant served a legal notice

upon the non-applicants on 16.09.2020 seeking appointment of an

arbitrator for settlement of the dispute between the parties.

4. The non-applicants have filed reply to the arbitration

application. It is stated in the reply that the work was awarded in

the year 2006. The work was required to be completed till

19.11.2006, however, the same was extended time to time and

lastly extended till 31.08.2011. It is also stated that the final bill

was prepared in the month of December, 2017 with a delay of

about 7 years after completion of work and since, the applicant

has not complied with the Clauses of the Agreement, the claim is

time-barred. It is further stated in the reply that the tender limit

has been extended exceeding to the financial jurisdiction of the

non-applicants and the same is pending for approval of the State

Government and as and when same will be received, without any

delay, dues payable to the applicant as per his final bill will be

paid.

5. A rejoinder to the said reply has also been filed by the

applicant. It is contended by the counsel for the applicant that

(3 of 5) [ARBAP-17/2022]

admittedly, the final bill has not been paid. The final bill was

prepared in December, 2017 and has not been paid because of

financial jurisdiction of the non-applicants as mentioned in their

reply. It is also contended that the notice seeking appointment of

an arbitrator was given on 16.09.2020 i.e. within 3 years from

preparation of the final bill and is thus, within the prescribed

period of limitation. Counsel for the applicant has placed reliance

on Bharat Sanchar Nigam Ltd. & Anr. Versus M/s. Nortel Networks

India Pvt. Ltd.: (2021) 5 SCC 738.

6. Counsel for the non-applicants has vehemently opposed the

arbitration application. It is contended that the claim is hopelessly

time-barred. The claimant-applicant has not completed the work

in time and has not raised the final claim within the prescribed

time and thus, the claim is hopelessly time-barred.

7. I have considered the contentions and have carefully perused

the material on record.

8. The scope of rejecting the claim for referring a dispute for

arbitration has been restricted after insertion of Section 11(6)(A)

in the Act. In Bharat Sanchar Nigam Ltd. & Anr. Versus M/s.

Nortel Networks India Pvt. Ltd. (supra), the Apex Court after

relying on the various judgments has held that only in the very

limited category of cases, where there is not even a vestige of

doubt that the claim is ex facie time-barred, or that the dispute is

non-arbitrable, that the court may decline to make the reference.

However, if there is even the slightest doubt, the rule is to refer

the dispute to arbitration, otherwise it would encroach upon what

is essentially a matter to be determined by the tribunal.

9. In the present case in hand, admittedly the final bill as per

the reply of the non-applicant was prepared in December, 2017.

(4 of 5) [ARBAP-17/2022]

From perusal of the reply, it is also evident that the amount of the

final bill has not been paid by the non-applicants, as the tender

limit has exceeded the financial jurisdiction of the non-applicants

and the same is pending for the approval of the State

Government. The non-claimants have clearly mentioned in the

reply that as and when they will receive the approval of the State

Government, without any delay, dues payable to applicant as per

his final bill will be paid. Since the non-applicants have not

disputed that the final bill has not been paid and that the same is

pending before the State Government, the fact that the final bill

was prepared in December, 2017 is also not disputed and since

the notice has been given on 16.09.2020 i.e. within 3 years of the

preparation of the final bill, the same cannot be said to be barred

by limitation.

10. Admittedly, there is an arbitration clause, the claim is

pending and payment of final bill is also pending with the non-

applicants, hence, this Court deems it proper to allow the present

arbitration application and the same is accordingly, allowed. This

Court appoints Mr. Justice K.S. Chaudhari (Retired), B-231, Meera

Path, Vaishali Nagar, Jaipur, as the sole arbitrator to decide the

dispute.

11. The appointment of the sole arbitrator is subject to the

declarations being made under Section 12 of the Arbitration and

Conciliation Act, 1996 with respect to the independence and

impartiality, and the ability to devote sufficient time to complete

the arbitration within prescribed period.

12. Accordingly, arbitration application stands allowed. The

arbitrator shall be entitled to lay down fees as provided under

(5 of 5) [ARBAP-17/2022]

Manual of Procedure for Alternative Disputes Resolution, 2009 as

amended from time to time.

13. Registry is directed to intimate Mr. Justice K.S. Chaudhari

(Retired) and obtain his formal consent.

14. The observations made herein-above are only for the

purpose of deciding the present application and the same will not

disentitle the parties to raise all valid objections before the learned

Arbitrator and the Arbitrator will be free to dispose the said

objection without being influenced by the observations made by

this Court.

(PANKAJ BHANDARI),J

SUNIL SOLANKI /PS

Powered by TCPDF (www.tcpdf.org)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter