Citation : 2022 Latest Caselaw 11807 Raj
Judgement Date : 22 September, 2022
HIGH COURT OF JUDICATURE FOR RAJASTHAN AT JODHPUR S.B. Civil Writ Petition No. 1608/2013
Heera Lal S/o Uma Ram, B/c Mali (Solanki) aged about 59 years, R/o Near Railway Fatak, Bypass Road, Makrana, District Nagaur.
----Petitioner Versus
1. State Of Rajasthan through Chief Engineer, Public Works Department, Jaipur.
2. Tehsildar, Makrana.
3. Municipal Board, Makrana.
----Respondents
For Petitioner(s) : Mr. Rameshwar Dave
For Respondent(s) : Mr. Vinay Jain
Mr. Darshan Jain
Mr. Anil Bachhawat with
Mr. S.R. Paliwal
HON'BLE MR. JUSTICE VINIT KUMAR MATHUR
Order
22/09/2022
Heard learned counsel for the parties.
The present writ petition has been filed against the order
dated 21.01.2013 passed by the District Collector, Nagaur,
whereby the cost of construction of the building over the acquired
land in question was denied.
The brief facts giving rise to the present writ petition are that
the petitioner was having a piece of land in Makrana for which a
Patta was issued in his favour in the year 1957. The petitioner
applied for permission to the Municipal Board, Makrana to raise
certain constructions in the year 1987. The permission sought for
was granted vide order dated 15.04.1987.
(2 of 7) [CW-1608/2013]
In pursuance of the permission granted by the Municipal
Board, Makrana, the petitioner raised certain constructions over
his Pattashud land. The respondent - authorities, on account of
the proposed construction of a road, gave notice to the petitioner
for taking possession of the subject piece of land along with the
construction raised over it.
Being aggrieved of such notice, the petitioner preferred a
suit before learned Civil Court praying therein that he was issued a
Patta of the subject piece of land in the year 1957 and after
granting due permission by the Competent Authorities of the
Municipal Board, Makrana, the construction was raised and,
therefore, the respondent-State Government cannot dispossess
the petitioner. Learned trial Court decreed the suit in favour of the
petitioner vide judgment dated 26.10.2005.
Thereafter, the need being arisen for construction of Railway
Over Bridge, therefore, once again the petitioner's land was
sought to be used for the purpose. A notice under Section 91 of
the Land Revenue Act, 1956 to this effect was issued to the
petitioner on 03.12.2007. The petitioner challenged this notice
once again by way of filling a writ petition before this court which
was decided on 14.12.2012 and the matter was sent back to the
Collector, for deciding the claims of the parties. The Collector, in
pursuance of the directions issued by this Court after giving
opportunity of hearing to all the parties decided the issues vide
order dated 21.01.2013, which is the impugned order in the
present writ petition.
The controversy in the present writ petition is only with
respect to the denial of the cost of construction incurred by the
petitioner for raising the construction over his Pattashud land.
(3 of 7) [CW-1608/2013]
Learned counsel for the petitioner submits that the petitioner
is in possession of the land on the strength of a Jaggir Patta
issued by the Competent Authorities way back in the year 1957.
He further submits that the possession of the petitioner is not
disputed, more so the findings of the fact recorded by the learned
Civil court in its order dated 26.10.2005 have become final as the
order of the Civil Court was not challenged before the higher
forums. Learned counsel further submits that once the authorities
of the respondent-Department decided the issue with respect to
the possession of the petitioner vide order dated 21.01.2013 and
awarded the compensation of the land to the petitioner, then the
petitioner cannot be denied the cost of construction raised over
the subject piece of land.
Learned counsel for the petitioner submits that once the
Collector vide his order dated 21.01.2013 had come to the
conclusion that the petitioner is entitled for the possession of the
land in question, then the amount incurred for raising the
construction over that land cannot be denied to the petitioner.
Learned counsel further submits that the respondent-Collector had
not given any finding with respect to the ineligibility of the
petitioner to get the compensation of the construction raised over
the land which is sought to be used for construction of the Railway
Over Bridge. He therefore, prays that the writ petition may be
allowed and the order dated 21.01.2013 may be quashed to the
extent of denying the benefit of the construction cost incurred by
the petitioner over the Pattashud land and the same being
demolished for the use of construction of ROB.
Per contra, learned counsel for the respondents vehemently
argued before this court and supported the order passed by the
(4 of 7) [CW-1608/2013]
Collector, Nagaur on 21.01.2013. Learned counsel for the
respondents submits that the petitioner was not entitled to raise
the construction over the subject piece of land as the same
violated the guidelines issued by the Ministry of Road Transport
and Highways for construction over the land coming within 40
meters from the central line of the highway.
Learned counsel submits that since the construction raised
over the land was not in accordance with the Rules and, therefore,
the demolition of the same will have no effect and the petitioner
will not be entitled to get the cost of construction raised over such
land. He submits that the Collector had rightly passed the order of
denying the cost incurred by the petitioner over the land which is
sought to be used for the construction of Railway Over Bridge.
I have considered the submissions made at the Bar and gone
through the entire records of the case including the impugned
order dated 21.01.2013 passed by the District Collector, Nagaur.
The fact that the petitioner was holding a valid Patta in his
favour over the subject piece of land is not disputed by the parties
before this Court and the construction which was undertaken by
the petitioner was also raised after taking due permission from the
Municipal Board, Makrana on 15.04.1987. The construction
permission is also placed on record as (Annex. 2). Thus, in view of
the documents granting permission, it can safely be presumed
that the construction raised by the petitioner on the Pattashud
land was justified and legal.
It is noted that on the earlier occasion, when the State
Authorities tried to take possession of the land of the petitioner for
construction of the road, a Civil Suit was filed which was decided
(5 of 7) [CW-1608/2013]
by the respondents in the year 1986 before the Civil Court. The
Civil Court framed the following issues:-
"05 - वादपत्र व जवाब दावा के आधार पर न्यायालय द्वारा निम्न तनकीयात कायम की गई :-
01-आया वादी की दु काने व मकान उसके पट्टाशुदा जमीन में स्थित है १ जिम्मे वादी 02-आया प्रतिवादीगण के विरूद्ध वादी स्थायी निषेधाज्ञा इस आशय की पाने का अधिकारी हैं कि प्रतिवादी उसके मकान व दु कान को नहीं तोड़ें १ जिम्मे वादी 03-आया वादी ने खसरा नम्बर 634/1 राजस्व रे कर्ड में गैर मुमकिन सड़क दर्ज पर अतिक्रमण किया है ? जिम्मे प्रतिवादी 04-अनुतोष १"
The issues framed in the Civil Suit were decided in favour of
the petitioner and it was held by the learned Civil Court that the
petitioner is the rightful owner of the subject piece of land and the
respondents were not entitled to demolish the construction raised
over it as the petitioner is not a trespasser on this land. The
findings recorded by the learned trial court had become final as
the same was not challenged before the Appellate Court.
In view of the findings recorded, the petitioner is held legally
the owner of the land and the construction raised over such land
was adjudicated to be legal and right.
In view of the findings of the Civil Court also, it cannot be
said that the petitioner raised the construction in violation of the
Rules and Law. Therefore, the argument of the learned counsel for
the respondents that the petitioner raised the construction de hors
the law is not sustainable and the same is therefore, rejected. The
entire piece of land of the petitioner including the construction is
required by the respondents for construction of Railway Over
Bridge and once the right, title and ownership of the land and
(6 of 7) [CW-1608/2013]
building of the petitioner is established beyond doubt, there is no
question that the petitioner shall be deprived of the cost of the
construction raised over such land.
The order impugned discussed in detail reveals that the
petitioner is entitled for the compensation for the cost of land
being the owner of the land and since the land is required for the
construction of ROB, the respondents are required to pay
compensation to the petitioner. The only fact that the construction
of the building over such land was illegal, the finding of the
learned Collector does not say a word on it that the construction
raised by the petitioner over the subject piece of land was dehors
the law. Not only this, no court or authority has ever issued a
notice to the petitioner for the illegal construction having been
raised on the subject piece of land. Since the construction raised
over the subject piece of land was never found to be illegal, then it
cannot be presumed that construction was coming within 40
meters from the centre of the road in violation of the guidelines of
the Ministry of Road Transport and Highways and the same was
illegal. The fact that the construction raised has been demolished
by the respondents for construction of the ROB, the petitioner is
certainly entitled for the cost incurred in construction of the
building over the land which is sought to being acquired.
Therefore, learned Collector was not correct in refusing to pay (Rs.
9,45,261/-) the cost incurred for raising the construction which is
being demolished for the purpose of the construction of ROB.
It is also noted that the cost incurred for construction of the
building has been assessed by the PWD, Rajasthan as Rs.
9,45,261/-.
(7 of 7) [CW-1608/2013]
In view of the discussions made above, the writ petition
merits acceptance, the same is allowed and the respondents are
directed to pay compensation of amount of Rs.9,45,261/- which
was denied by the impugned order dated 21.01.2013 along with
5% interest from the date of the order passed by the Collector on
21.01.2013 within a period of eight weeks from today.
(VINIT KUMAR MATHUR),J
6-Nitin/-
Powered by TCPDF (www.tcpdf.org)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!