Citation : 2022 Latest Caselaw 9513 Raj
Judgement Date : 21 July, 2022
(1 of 5) [ARBAP-15/2019]
HIGH COURT OF JUDICATURE FOR RAJASTHAN AT
JODHPUR
S.B. Arbitration Application No. 15/2019 M/s Shiv Shakti Builders, Kandoi Kunj, J-86, Parshavnath City, Pal Bye Pass, Jodhpur Through Prop. Chand Kumar Kandoi S/o Shri Jagdish Prasad, Aged 66 Years.
----Petitioner Versus The Divisional Railway Engineer (West), North Western Railway, Jodhpur.
----Respondent
For Petitioner(s) : Mr. Kuldeep Kumar Shah For Respondent(s) : Mr. Kamal Kishore Dave Mr. Dhirendra Pandey Mr. Ramniwas Harnia
HON'BLE MR. JUSTICE VINIT KUMAR MATHUR
Order
21/07/2022
Heard learned counsel for the parties.
The present application has been preferred under Section 11
(6) of the Arbitration and Conciliation Act, 1996 for appointment
of the Arbitrator in the present case.
Brief facts giving rise to the present application are that the
petitioner entered into a contract with the Railways for performing
the certain works. On a dispute being arisen between the parties,
the applicant served a notice dated 15.03.2018 to the Divisional
Railway Engineer (West), North Western Railway, Jodhpur for
appointment of the Arbitrator which is placed on record as (Annex.
R/2). When the Divisional Railway Engineer (West), North Western
Railway, Jodhpur failed to appoint the Arbitrator, the applicant
preferred an application being S.B. Arbitration Application No.
11/2018 before this Court. This court vide judgment dated
(2 of 5) [ARBAP-15/2019]
23.10.2018 disposed of the said application in the following
terms:-
"In view of the above discussion, the applicant having failed to comply with the necessary pre-requisite conditions for invoking provisions of Section 11(6) of the Act, the application is not maintainable and, consequently, the same is dismissed leaving itd open for the applicant to act in accordance with law."
After the decision of the Arbitration Application No. 11/2018,
the applicant served a notice/representation on 27.10.2018 to the
General Manager (North Western Railway), Jaipur for appointment
of Arbitrator to resolve the dispute between the applicant and the
respondent. In pursuance of the representation dated 27.10.2018,
the respondents failed to appoint the Arbitrator in the matter and,
therefore, the present application has been filed.
Learned counsel for the applicant submits that as per the
Clauses 63 & 64 of the contract agreement between the applicant
and the respondent, if any dispute is arisen between the parties,
the same will be resolved by appointing an Arbitrator but the
respondent failed to appoint the Arbitrator in the present case,
thus, the present application has been preferred. It is prayed that
an Arbitrator may be appointed in the matter for resolving the
dispute between the applicant and the respondent.
Per contra, learned counsel for the respondent vehemently
opposed and submits that it is not open for the applicant to move
an application for appointment of the Arbitrator as the period of
limitation has expired which is 180 days as per Clause 64 of the
contract agreement. He further submits that the liberty was
granted by this court vide order dated 23.10.2018 to the applicant
to act in accordance with law and since the applicant has failed to
approach the correct authority in the first instance, therefore, the
(3 of 5) [ARBAP-15/2019]
applicant cannot be allowed to file representation/application for
appointment of an Arbitrator to the correct authority at this
belated stage. He further submits that as per Clause 64, the
period of limitation for approaching the appropriate authority for
appointment of an Arbitrator is 180 days and since the petitioner
failed to approach the correct authority in time, he cannot be
permitted at this stage to invoke the arbitration clause for
appointment of the Arbitrator.
Learned counsel for the respondent has relied upon the
judgments of Supreme Court in case of Union of India & Ors.
vs. M/s. Onkar Nath Bhalla & Sons reported in 2009 0
Supreme (SC) 755 and Wild Life Institute of India,
Dehradun, Appellant vs. Vijay Kumar Garg, Respondent
reported in 1997 0 Supreme (SC) 801 1997 10 SCC 528.
I have considered the submissions made at the Bar and gone
through the record of the case.
Admittedly, the arbitration Clause 63 & 64 of the contract
agreement exists between the applicant and the respondent as
and the same is not disputed by the parties before this Court. It is
also noted that in the earlier round of litigation, the application
preferred by the applicant was decided by this Court on
23.10.2018 and a liberty was granted to the applicant to act in
accordance with law. It is clear that the applicant was not right in
making the request of appointment of an Arbitrator to the
Divisional Railway Engineer (West), North Western Railway,
Jodhpur as the proper authority was General Manager (North
Western Railway), Jaipur. After the decision of this Court
23.10.2018, the applicant made a representation/application for
appointment of the Arbitrator as per Clause 64, the same by no
(4 of 5) [ARBAP-15/2019]
stretch of imagination can be treated as time barred as the
applicant was prosecuting his remedy and at no point of time, the
application so made by the applicant at earlier occasion to
Divisional Railway Engineer (West), North Western Railway,
Jodhpur was replied by the respondent by saying that it is not the
correct authority to appoint the Arbitrator and he should approach
General Manager (North Western Railway), Jaipur. Therefore, in
these circumstances the logical conclusion for resolution of dispute
entails that a person cannot be made remediless and, therefore,
the hypertechnical objection taken by the respondent that the
application preferred by the applicant is time barred is noted to be
rejected.
The judgments relied upon by the learned counsel for the
respondent in the present case has no application as this court on
23.10.2018 has ruled that applicant may act in accordance with
law and, therefore, the application/representation preferred by the
applicant for appointment of the suitable Arbitrator to resolve the
dispute in this case merits acceptance. The judgments relied upon
by learned counsel for the respondent are clearly distinguishable
in the facts and circumstances of the present case.
In the circumstances, the arbitration application is allowed.
Mr. G.R. Bhansali, R/o D-48 Kamla Nehru Nagar, Jodhpur is
appointed as a sole Arbitrator to adjudicate upon the dispute
between the parties in terms of arbitration agreement and as per
the Rajasthan Manual of Procedure for Alternative Dispute
Resolution, 2009, as amended up to date and also as per the
provisions of Arbitration and Conciliation Act.
The record of the case may be transmitted to the Mr. G.R.
Bhansali.
(5 of 5) [ARBAP-15/2019]
The above appointment is subject to the necessary
disclosure under Section 12 of the Act.
Needles to say that the fee of the Arbitrator will be paid as
per the Fourth Schedule of the Arbitration and Conciliation Act.
(VINIT KUMAR MATHUR),J 144-KashishS/Nitin-
Powered by TCPDF (www.tcpdf.org)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!