Citation : 2025 Latest Caselaw 2046 Patna
Judgement Date : 28 February, 2025
IN THE HIGH COURT OF JUDICATURE AT PATNA
Civil Writ Jurisdiction Case No.483 of 2022
======================================================
In Re- N.H.82 Four Lane Project Gaya- Hisua- Rajgir, Biharsharif Section.
... ... Petitioner/s
Versus
1. The Union of India through the Secretary, Ministry of Road Transport and
Highways, Government of India, New Delhi.
2. The Secretary, Ministry of Road Transport and Highways, Government of
India, New Delhi.
3. The National Highway Authority of India, New Delhi through its Chairman,
New Delhi.
4. The Chairman, National Highway Authority of India, New Delhi.
5. The State of Bihar, through the Chief Secretary, Government of Bihar, Patna.
6. The Chief Secretary, Government of Bihar, Patna.
7. The Principal Secretary, Secretary, Road Construction Department
Government of Bihar, Patna.
8. The Principal Secretary, Department of Revenue and Land Reforms,
Government of Bihar.
9. The District Magistrate, Gaya.
10. The Secretary, Department of Economic Affairs, Ministry of finance,
Government of India, New Delhi.
11. The Bihar State Road Development Corporation Ltd., Patna.
... ... Respondent/s
======================================================
Appearance :
For the Petitioner/s :
For the Respondents : Mr. P.K. Shahi, Advocate General
Mr. Anjani Kumar, AAG-4
Mr. Manish Dhari Singh, A.C. to AG.
Dr. K.N. Singh, Sr. Advocate
Mr. Shivaditya Dhari Sinha, Advocate
Ms Prakritita Sharma, Advocate
Patna High Court CWJC No.483 of 2022 dt.28-02-2025
2/3
Mr. Amarjet, Advocate
======================================================
CORAM: HONOURABLE THE ACTING CHIEF JUSTICE
and
HONOURABLE MR. JUSTICE PARTHA SARTHY
ORAL JUDGMENT
(Per: HONOURABLE THE ACTING CHIEF JUSTICE)
Date : 28-02-2025
The learned Advocate General has informed this
Court that the construction of the ROB at Rajgir is
completed to the extent of 86.5 percent and the expected
date when the entire ROB would be constructed is
31.03.2025.
2
. With respect to the ROB at Rasalpur, 73
percent of the work has been done and the rest of the
work is expected to be completed by 30th of June, 2025.
3. With this updated report about the stage of
construction, there would be no necessity of continuing
with this case.
4. We, therefore, close this petition with the
hope and trust that by the expected date, the construction Patna High Court CWJC No.483 of 2022 dt.28-02-2025
would be completed.
5. Records consigned.
(Ashutosh Kumar, ACJ)
(Partha Sarthy, J) P.K.P./-
AFR/NAFR CAV DATE Uploading Date 03.03.2025 Transmission Date
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!