Wednesday, 20, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

D.B.S. Constructions Pvt. Ltd vs The State Of Bihar
2025 Latest Caselaw 3336 Patna

Citation : 2025 Latest Caselaw 3336 Patna
Judgement Date : 19 April, 2025

Patna High Court

D.B.S. Constructions Pvt. Ltd vs The State Of Bihar on 19 April, 2025

Author: Partha Sarthy
Bench: Partha Sarthy
         IN THE HIGH COURT OF JUDICATURE AT PATNA
                   Civil Writ Jurisdiction Case No.10478 of 2024
     ======================================================
     D.B.S. Constructions Pvt. Ltd. having its Registered Office at Tar Banglow
     More, Dehri On Sone, P.S.- Dehri, District Rohtas, Bihar through its Director,
     Sunil Kumar Singh, aged about 60 years, Male, Son of Sri Daroga Singh,
     resident of Mohalla Samdika Nagar, P.S.- Dehri, District- Rohtas, Bihar.

                                                                   ... ... Petitioner/s
                                        Versus

1.   The State of Bihar through Principal Secretary, Department of Energy cum
     Chairman, Bihar State Hydroelectric Power Corporation, (A Government of
     Bihar Enterprise), Sone Bhawan, Patna.
2.   Managing Director, Bihar State Hydroelectric Power Corporation, (A
     Government of Bihar Enterprise), Sone Bhawan, Patna.
3.   The Chief Engineer, Bihar State Hydroelectric Power Corporation Ltd., (A
     Government of Bihar Enterprise), Sone Bhawan, Patna.
4.    The Executive Engineer, Bihar State Hydroelectric Power Corporation Ltd.,
      (A Government of Bihar Enterprise), Sone Bhawan, Patna.
                                                            ... ... Respondent/s
     ======================================================
     Appearance :
     For the Petitioner/s   :      Mr. Prabhat Ranjan, Advocate
     For the Respondent/s   :      Mr. Mritunjay Kumar, Advocate
     ======================================================
     CORAM: HONOURABLE THE ACTING CHIEF JUSTICE
                           and
             HONOURABLE MR. JUSTICE PARTHA SARTHY
                     CAV JUDGMENT
     (Per: HONOURABLE MR. JUSTICE PARTHA SARTHY)

      Date : 06-05-2025


                  1. Heard learned counsels for the parties.

                  2. The petitioner has filed the instant application

      praying for quashing the order contained in Letter no. 105 dated

      1.3.2024

issued under the signature of the Chief Engineer of the

Bihar State Hydroelectric Power Corporation Ltd. (herein after

referred to as the 'Corporation') whereby while closing the

agreement entered into with the petitioner, order was passed Patna High Court CWJC No.10478 of 2024 dt.06-05-2025

blacklisting the petitioner for a period of three financial years

and further the security deposit was directed to be forfeited.

3. The relevant facts in brief are that the respondent-

Corporation having come out with a Notice Inviting Tender no.

05/Civil/18-19 dated 6.3.2019 which was for completion of the

balance work of projects in various stages of construction, the

petitioner applied for the work of Amethi MHP (1x500 kW). A

Letter of Intent dated 21.8.2019 was issued for execution of

work at a total cost of Rs.5,33,68,345/- and an agreement was

entered into between the Corporation and the petitioner on

14.10.2019. The work was to be completed within a period of

12 months from the date of agreement.

4. It is the case of the petitioner that the site of work

having been flooded, on the water receding, there was

considerable change in the condition of the site and a year

having passed since the agreement was entered into and the site

not having been handed over to the petitioner, he prayed that the

site be handed over, the same be dewatered and further a

representation was filed for revision of the rates at the rate of

5% of the agreed amount. The petitioner has brought on record

his representations dated 10.10.2020, 18.12.2020 as also

22.1.2021 to substantiate his above contention. Patna High Court CWJC No.10478 of 2024 dt.06-05-2025

5. Learned counsel for the petitioner submits that not

having received any response to the representations filed by

him, the petitioner moved this Court in CWJC no. 371 of 2023

which was disposed of by order dated 20.7.2023 directing the

Chief Engineer of the Corporation to consider the petitioner's

representations in accordance with law and pass a speaking

order thereon.

6. The respondent-Corporation by their order

contained in Letter no.105 dated 1.3.2024 was pleased to close

the agreement, blacklist the petitioner for three financial years

and ordered for forfeiture of the security deposit.

7. Learned counsel for the petitioner submits that

against the time for completion of work being 12 months though

the agreement was entered into between the parties on

14.10.2019, the site for the work was not handed over to the

petitioner even on the time for completion of the work having

expired. It was further submitted that the order of blacklisting

was not preceded by a show-cause contemplating such an

action. Further, there was no application of Clause 1.2.21 of the

General Conditions of the Contract which deals with

negligence. It is thus submitted that the order impugned is

illegal, arbitrary and not sustainable and thus be set aside. Patna High Court CWJC No.10478 of 2024 dt.06-05-2025

8. In response, Mr. Mritunjay Kumar, learned counsel

appearing for the respondent-Corporation submitted that though

the agreement was signed between the Corporation and the

petitioner on 14.10.2019, however the petitioner did not intend

nor took interest to start the work for reasons best known to

him. It is for this reason that the Corporation sent several letters

including dated 6.10.2020 and 15.1.2021 asking him to start the

work, failing which steps would be taken in accordance with the

agreement. The petitioner Firm not having submitted any bar/

part chart of the projects works to the Corporation and the work

which was to be concluded in 12 months, as such the

Corporation sent a notice to the petitioner on 15.1.2021 as to

why the agreement be not cancelled. On receiving the reply of

the petitioner and considering the contents thereof as also

complying with the directions contained in order dated

20.7.2023 passed in CWJC no. 371 of 2023, the Corporation

issued the order dated 1.3.2024, impugned herein.

9. Heard Mr. Prabhat Ranjan, learned counsel for the

petitioner and Mr. Mritunjay Kumar, learned counsel for the

Corporation. Perused the material on record.

10. Pursuant to the petitioner having applied against

N.I.T. dated 6.3.2019 floated by the respondent-Corporation, the Patna High Court CWJC No.10478 of 2024 dt.06-05-2025

petitioner was issued with the L.O.I. with respect to the work for

Amethi MHP (1x500 kW) and an agreement was entered into

between the parties on 14.10.2019. As per the terms of the

agreement, the work was to be executed at a total cost of

Rs.5,33,68,345/- and the same had to be completed within a

period of 12 months ie by 14.10.2020.

11. From the record it transpires that the Corporation

wrote a letter dated 6.10.2020 to the petitioner stating therein

that the period of the agreement was coming to an end on

14.10.2020. Further referring to the communication on

telephone, the petitioner was requested to submit the part chart

and revised item and quantity as per the approved drawings

within a period of one week and to commence work at site at the

earliest or else further action would be taken as per the

agreement. The petitioner in response mentioned about the work

site being inundated with water, the site having changed

considerably and also with respect to the revision, deviation and

variation in the plan and estimate proposed by the Corporation.

12. On further perusal of the communications it

transpires that though the petitioner kept reminding the

Corporation of handing over the site after dewatering the same

and also to provide them with a copy of the agreement with the Patna High Court CWJC No.10478 of 2024 dt.06-05-2025

revised item and quantity, the Corporation only proceeded to

write to the petitioner about the fact that the work had to be

completed by 13.10.2020 and the same had not been started yet.

The response/letters of the Corporation do not show that any of

the issues raised by the petitioner were dealt with. Not having

received any effective response to his representations led to the

petitioner filing CWJC no. 371 of 2023, which was disposed of

by this Court on 20.7.2023 directing the respondent-Corporation

to dispose of the petitioner's representations by a speaking

order.

13. Subsequent thereto, the respondent-Corporation

sent a letter dated 12.1.2024 to the petitioner which contained

the schedule of the deviated quantities and prices, however it

needs to be noted that by this time more than 4 years had passed

of the petitioner having entered into an agreement with the

Corporation. It is soon thereafter that the respondent-

Corporation came out with the order dated 1.3.2024, impugned

herein.

14. In view of the facts and circumstances of the case

and as dealt with herein above, the Court is of the opinion that

the Corporation itself having delayed in handing over the site

for carrying out the work, free from water, the further inordinate Patna High Court CWJC No.10478 of 2024 dt.06-05-2025

delay in issuing the schedule of deviated quantities and prices

which was done more than 4 years after the parties entered into

an agreement and of which the work was to be completed within

12 months, the petitioner cannot be held solely responsible for

non-performance of the work in question.

15. Clause 1.2.21 of the Terms and Conditions of the

Contract deals with negligence and provides that if the

contractor neglects to execute the work with due diligence and

expedition or refuses to comply with the orders given to him in

writing by the Engineer in connection with the work, after

giving due notice the owner shall have the option to take the

work out of the contractor's hand and to get the same done

himself. Further Clause 1.1.12(iii) reserves to the owner the

right to encash the Bank guarantees if sufficiently convinced of

the contractor's negligence and lack of dedication to work and

failing the milestones against the agreed date on part of the

contract. It is in exercise of these two Clauses 1.2.21 and

1.1.12(iii) that the order impugned has been passed closing the

agreement blacklisting the petitioner for three financial years

and forfeiting the Bank guarantee.

16. As already held, in the facts of the case, it cannot

be said that the petitioner was solely responsible for the work Patna High Court CWJC No.10478 of 2024 dt.06-05-2025

not being done in view of the facts as narrated herein above.

17. In view of the facts and circumstances of the case,

the order impugned is not sustainable and the same is set aside

so far as the blacklisting of the petitioner for a period of three

financial years and forfeiture of his Bank guarantees are

concerned.

18. The writ application is allowed to the above extent

and is accordingly disposed off.

(Partha Sarthy, J)

Ashutosh Kumar, ACJ: I agree.

(Ashutosh Kumar, ACJ)

avinash/-

AFR/NAFR
CAV DATE                18.02.2025
Uploading Date          06.05.2025
Transmission Date
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter