          IN THE HIGH COURT OF JUDICATURE AT PATNA
                    Civil Writ Jurisdiction Case No.15684 of 2018
     ======================================================

Shanti Kunwar W/o Mahadeo Vishwakarma, Resident of Quarter No. 51, Jhauakothi Jagdishpur, P.S. and District Bhagalpur, At Present Resident of C/o Pramod Sharma, Sone Ghat Road, Madanpur, P.S. Barun, District Aurangabad.

... ... Petitioner/s Versus

1. The State of Bihar

2. The Collector-Cum-Arbitrator, National Highway Division-2, Aurangabad.

3. The District Land Acquisition Officer, Aurangabad.

4. The Deputy Collector Land Reform, Aurangabad.

5. The Registration Registrar, Aurangabad.

6. The Circle Officer, Madanpur, District Aurangabad.

... ... Respondent/s ====================================================== Appearance :

For the Petitioner/s : Mr. Surendra Kishore Thakur, Advocate Mr. Chandra Shekhar Bimal, Advocate For the Respondent/s : Mr. Dhurjati Kumar Prasad, GP14 For the NHAI : Mr. S.N.Pathak, S.C.(NHAI) Mr. Saurav Nikunj, Advocate ====================================================== CORAM: HONOURABLE MR. JUSTICE PARTHA SARTHY ORAL JUDGMENT Date : 15-02-2023

Heard learned counsel for the petitioner and learned

counsel appearing for the NHAI.

The petitioner has filed the instant application for the

following reliefs:

"(i) For issuance of writ in the appropriate nature for quashing of the order dated 31.3.2017 passed by the Additional Collector-cum-

Arbitrator, National Highway Division-2, Aurangabad in L.A. Case No. 183/2016-17 whereby and where under the learned Court below has rejected the application filed by the petitioner for payment of compensation against the land acquisition @ commercial value but the learned court below has rejected the same Patna High Court CWJC No.15684 of 2018 dt.15-02-2023

without considering that in the adjacent land the commercial activity are going on likewise petrol pump, hardware shop and educational institution are there.

(ii) For further direction to the Respondents authority to reconsider the case of the petitioner in the light of the decision taken by the Arbitrator who in a similar situated case for the same project has granted compensation @ commercial value though in a case of the petitioner has rejected the same only on the basis of the report of the concerned officer.

(iii) And for any other relief/reliefs for which the petitioner is found to be entitled in the eye of law."

The case of the petitioner in brief is that the land of the

petitioner appertaining to Khata No.192, Plot no.22 measuring

an area of 1.2532 hectares situated in the village Madanpur, P.S.

Madanpur, District Aurangabad adjacent to the National

Highway was subject matter of the land acquisition case being

L. A. Case No.182 of 2016-17. Being aggrieved by the

assessment of compensation by the Land Acquisition Officer the

petitioner filed L.A. Case no.183 of 2016-17 for enhancement of

compensation, however, the same was rejected by the

respondent authorities. It is the case of the petitioner that

other similarly situated persons have got higher compensation.

Not having got any relief from the authorities, this writ

application was filed for the prayer mentioned hereinabove. Patna High Court CWJC No.15684 of 2018 dt.15-02-2023

A counter affidavit has been filed on behalf of the

respondent No.2 stating therein that the notices under section 3-

G of the National Highways Act, 1956 ('the Act' in short) was

issued to the petitioner informing her to appear before the

competent authority. The petitioner appeared and raised

objection and thereafter the award of her acquired land was

prepared under the Act. Being aggrieved by the said award, the

petitioner preferred a case before the Arbitrator-cum-Additional

Collector, vide L.A. Case no.183 of 2016-17 and the said

Arbitrator did not find any merit in the case of the petitioner.

Learned counsel appearing on behalf of the NHAI relying

on the provisions of section 3-G and section 3-H of the Act

together with the judgment of the Division Bench of this Court

in the case of Project Director, National Highway Authority,

Araria at Purnea, Bihar and Anr. vs Md. Gufran Alam &

Ors. reported in 2014 (1) PLJR 207 submits that it has

categorically been held therein that on determination of the

amount of compensation by the arbitrator, the remedy available

to the effected party would be an application under section 34 of

the Arbitration and Conciliation Act, 1996 for setting aside the

said arbitral award. As such it is submitted that the instant Patna High Court CWJC No.15684 of 2018 dt.15-02-2023

application would not be maintainable.

It would be relevant to quote paragraph nos. 8 and 9 of

the aforesaid judgment in the case of Project Director,

National Highway Authority (supra) which is as follows:

"8. We may look to the certain provisions of the Act of 1956 and the Act of 1996 which are relevant for resolution of dispute before us. Section 3-G of the Act of 1956 provides for determination of amount of compensation by the Competent Authority. Sub-section (5) thereof empowers either of the parties aggrieved by the award of the Competent Authority to seek arbitration against such award. Sub-section (6) of Section 3-G of the said Act provides that the proceeding before the Arbitrator shall be regulated by the provisions contained in the Act of 1956. Section 3-H of the Act of 1956 provides for deposit and payment of amount. Sub-section (1) thereof provides for deposit of the amount of compensation with the Competent Authority. Sub-section (2) thereof provides for payment of the amount to the claimants. Sub- section (6) thereof provides for deposit of the amount of difference in compensation awarded by the Arbitrator. It is this sub-section (6) which is pressed into service by the writ petitioner.

9. As recorded hereinabove, the proceedings before the Arbitrator are governed by the Act of 1996. Section 34 of the Act of 1996 provides for a remedy against the arbitral award by an application for setting aside the arbitral award before the Court. The "Court" is defined under Clause (e) of sub-section (1) of Section 2 of the Act of 1996 to mean, "the principal civil Court of original jurisdiction in a district, and includes the High Court in exercise of its ordinary original civil jurisdiction, having jurisdiction to decide the questions forming the subject-matter Patna High Court CWJC No.15684 of 2018 dt.15-02-2023

of the arbitration if the same had been the subject-matter of a suit, but does not include any civil Court of a grade inferior to such principal civil Court, or any Court of Small Causes." Hence, it is evident that the remedy against the arbitral award lies before the civil Court. Section 36 of the Act of 1996 provides for enforcement of the arbitral award under the Code of Civil Procedure, 1908 in the same manner as if it were a decree of the Court. Thus, the statutory remedy for enforcement of the arbitral award made under Section 3-G (5) of the Act of 1956 lies before the civil Court."

Having heard learned counsel for the parties and taking

into consideration the submissions made, this Court finds

substance in the submissions made by learned counsel appearing

for the NHAI.

Having regard to the facts and circumstances of the case

including the reference of the National Highways Act, 1956

together with the Arbitration and Conciliation Act, 1996 and the

ratio of the judgment in the case of Project Director, National

Highway Authority (supra), the Court is of the opinion that the

instant application is not maintainable and is accordingly

dismissed with liberty to the petitioner to pursue the remedy

available to him under law.

In case any application is preferred, while considering the

application for limitation, the authority concerned shall take into Patna High Court CWJC No.15684 of 2018 dt.15-02-2023

consideration the period for which the matter in issue was being

pursued before this Court.


                                                                     (Partha Sarthy, J)
Bibhash
AFR/NAFR
CAV DATE
Uploading Date                      20.2.2023
Transmission Date
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter