Tuesday, 19, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Avinash Kumar vs The State Of Bihar
2023 Latest Caselaw 6077 Patna

Citation : 2023 Latest Caselaw 6077 Patna
Judgement Date : 18 December, 2023

Patna High Court

Avinash Kumar vs The State Of Bihar on 18 December, 2023

Bench: Chief Justice, Partha Sarthy

         IN THE HIGH COURT OF JUDICATURE AT PATNA
                   Civil Writ Jurisdiction Case No.14497 of 2023
     ======================================================
     Avinash Kumar S/o Sri Ashok Kumar Singh, R/o- Village, Post and P.S. -
     Bikram, Dist- Patna, PIN- 801104, Aadhar No. - 812743699041.

                                                                ... ... Petitioner/s
                                       Versus

1.   The State of Bihar through the Add. Chief Secretary, Minor Water Resources
     department, Vikas Bhavan, Bailey Road, Patna- 1.
2.   The Chief Engineer, Minor Water Resources department, Muzaffarpur.
3.   The internal financial advisor, Minor Water Resources department, Vikas
     Bhavan, Bailey road, Patna - 1.
4.   The Superintending Engineer, (Anusrawan) Minor Water Resources Depat,
     Vikas Bhavan, Bailey Road, Patna - 1.
5.   The Ex. Engineer, Minor Irrigation division- Hajipur.

                                               ... ... Respondent/s
     ======================================================
     Appearance :
     For the Petitioner/s   :      Mr.Shashi Bhushan Singh, Advocate
     For the Respondent/s   :      Mr.Sarvesh Kumar Singh, AAG 13
     ======================================================
     CORAM: HONOURABLE THE CHIEF JUSTICE
             and
             HONOURABLE MR. JUSTICE PARTHA SARTHY
     ORAL JUDGMENT
     (Per: HONOURABLE THE CHIEF JUSTICE)

      Date : 18-12-2023

                        The petitioner is aggrieved with the cancellation

      of a tender issued by the respondents and now re-notified.

                        2. The petitioner participated in the tender, NIT

      No. 1/2022-23 dated 30.11.2022, with appropriate bid and

      requisite documents, as on 27.12.2022 which was acknowledged

      on the very same day. The tender was for the construction of

      buildings to house Divisional and Sub-divisional Office at

      Hajipur. The petitioner quoted 10.21% below the tender value of
 Patna High Court CWJC No.14497 of 2023 dt.18-12-2023
                                           2/5




         Rs. 1,99,41,300/- and deposited the earnest money deposit

         (EMD) of Rs. 3,99,000/- and also additional performance

         guarantee. The petitioner was found qualified in the technical

         bid along with the other bids in the proceedings dated

         21.01.2023

, produced as Annexure-3. The financial bids were

opened on 09.02.2023 and the petitioner was found to be the

lowest bidder (L1), which is evident from Annexure-4, produced

along with the writ petition. Later on, when an objection was

filed by one of the bidders; based on an interim order dated

06.07.2023 in CWJC No. 9941 of 2022 the tender was

cancelled.

3. The petitioner contends that the objection

itself was time barred and there was no valid reason to cancel

the tender based on the interim order passed. The petitioner

issued a legal notice through his Advocate, produced as

Annexure-6, without consideration of which, a re-tender was

issued as NIT No. 3/2023-24 dated 08.08.2023, produced as

Annexure-7. The re-tender was without any justification is the

contention.

4. A counter affidavit has been filed wherein it

has been accepted that there was an objection filed by one of the

bidders pointing out the order dated 21.12.2022 passed in Patna High Court CWJC No.14497 of 2023 dt.18-12-2023

CWJC No. 9941 of 2022. The subject tender was one which

clearly fell within the interim order passed by this Court, is the

contention. It is also admitted that the Executive Engineer,

Minor Irrigation Division, Hajipur has specifically informed the

Chief Engineer that the tender evaluation committee has

considered the objection raised and allowed the re-tender. The

Committee, headed by the Additional Chief Secretary, Minor

Water Resources Department, decided to cancel the tender

issued vide NIT No. 1/2022-23 and instructed for re-tendering

of the same in the light of interim order passed by this Court.

5. The interim order passed was in a writ petition

challenging the decision taken by the Principal Secretary, Road

Construction Department to remove the minimum rate limit in

percentage rate tenders with effect from 16.01.2020. It is true

that by order dated 21.12.2022, there was a stay of operation of

the impugned notification dated 16.01.2020. It was also clarified

in the interim order that it would operate only for such of those

tenders, for which bids are yet required to be submitted.

6. The petitioner had already submitted the

tender, but, however, the last date of submission of tender was

on 27.12.2022, as is revealed from Annexure-2. The respondents

do not state whether the bids evaluated were submitted before Patna High Court CWJC No.14497 of 2023 dt.18-12-2023

the interim order or not. In any event, even the writ petition filed

was dismissed as is seen from the judgment dated 06.07.2023

produced along with this writ petition. We see from the

judgment that even the decision challenged was not produced in

the writ petition. The writ petition stood dismissed leaving

liberty to challenge the decision if required at the time when a

cause of action arises, by any fresh tender floated. Obviously, no

such challenge has been made.

7. The re-tender has been made by the State as

per Annexure-7. The date of notification is 08.08.2023 after the

writ petition stood dismissed. The contention of the petitioner is

that re-tender notification is exactly identical to the earlier

tender. The petitioner is prejudiced insofar as the bid is in the

public domain and the other bidders would quote lesser.

8. We have considered the matter and we are of

the opinion that no prejudice would be caused to the State by

awarding the work to the petitioner. The sole reason for

cancellation of the earlier tender was the interim order passed by

this Court, which writ petition stood dismissed later on; even

before the re-tender was notified. The conditions of tender

including the tender value is identical. In the interregnum,

almost a year has passed and there could be an escalation of Patna High Court CWJC No.14497 of 2023 dt.18-12-2023

price. It would be beneficial for the State, if the earlier tender is

accepted and hence, we directed the petitioner to file an affidavit

undertaking to carry out the work as per the quote earlier made.

9. An affidavit has been placed on record today

undertaking that the work would be carried out as per the earlier

tender submitted and all the tender conditions would be abided

and the rates quoted or submitted at the rate of 10.21% below

the estimated cost, scrupulously complied with.

10. We hence set aside Annexure-5 and

Annexure-7, the cancellation of the earlier tender and the re-

tender issued by the State. We direct the work order to be issued

to the petitioner, if the petitioner is otherwise qualified.

11. The writ petition would stand allowed,

leaving the parties to suffer their respective costs.

(K. Vinod Chandran, CJ)

( Partha Sarthy, J) Sujit/-

AFR/NAFR                NAFR
CAV DATE
Uploading Date          20.12.2023
Transmission Date
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter