Citation : 2024 Latest Caselaw 559 Meg
Judgement Date : 20 August, 2024
2024:MLHC:749
Serial No. 01
Supplementary List
HIGH COURT OF MEGHALAYA
AT SHILLONG
WP(C) No. 116 of 2024
Date of Decision: 20.08.2024
M/s RKI India Limited ... Petitioner(s)
- Versus -
1. State of Meghalaya,
Represented by the Commissioner & Secretary,
To the Govt. of Meghalaya, Power Department,
Shillong.
2. The Chairman cum Managing Director,
MePDCL, Lumjingshai, Shillong.
3. The Director (Distribution), MePDCL,
Meghalaya, Shillong.
4. The Chief Engineer (Projects) MePDCL,
Meghalaya, Shillong
5. The Superintending Engineer (Projects)
MePDCL, Tura
6. The Asian Development Bank,
Represented by its Project Manager ... Respondent(s)
Coram:
Hon'ble Mr. Justice H. S. Thangkhiew, Chief Justice (Acting)
Appearance:
For the Petitioner(s) : Ms. Liz Mathew, Sr. Adv. with Ms. B. Vennemalai, Adv.
Mr. S. Deb, Adv.
For the Respondent(s) : Mr. A.S. Pandey, Adv.
Ms. R. Colney, GA
2024:MLHC:749
___________________________________________________________
i) Whether approved for reporting in Yes/No Law journals etc.:
ii) Whether approved for publication
in press: Yes/No
JUDGMENT AND ORDER
1. The petitioner company on being the successful bidder in a
tender floated by the respondent No. 2, for the work titled 'East Garo
Hills Circle-Distribution System Improvement: 33/11 KV Sub-station
Development', was issued the Letter of Allotment (LoA) and a contract
agreement, was duly executed on 21.12.2020, between the respondent
No. 2 and the petitioner, for the said work amounting to Rs.
74,34,56,822/- with the completion time for the said works being 18
months from the effective date of commission.
2. It appears that though the contract was scheduled to be
completed in November, 2022, taking the effective date of contract to
have commenced from 29.05.2021, the work was delayed due to various
reasons which the petitioner company maintained was due to
circumstances beyond its control. On 02.05.2023, a show cause notice
was issued by the respondent No. 4, directing the petitioner to answer as
to why the contract should not be terminated failing which clause 42.2 of
2024:MLHC:749
the conditions of contract would be invoked. The petitioner replied to the
said show cause assuring the respondents that the project would be
completed by December, 2023. Thereafter the petitioner was called for a
review meeting, on 06.07.2023 which however, the representative of the
petitioner company did not attend citing reasons that he was suffering
from COVID, the absence whereof, was not taken kindly by the
respondents. Subsequent review meetings were then held on 06.07.2023
and 03.08.2023, and though the petitioner submitted a representation on
05.08.2023, replying to the issues raised in the minutes of the review
meeting, the respondent No. 4 on 22.8.2023 issued a notice of
termination, highlighting the slow progress of the work. The respondent
No. 4 then on 15.12.2023 issued the letter of termination and decided to
invoke clause 42.2.2 for termination w.e.f. 16.12.2023. Thereafter, the
respondent No. 4 floated a fresh tender on 08.02.2024, for the remaining
works, with the dead line for submission of bids on 25.04.2024. The
petitioner company being aggrieved is therefore before this Court
impugning the letter of termination dated 15.12.2023 and the tender
notice dated 08.03.2024.
3. Ms. Liz. Mathew, learned Senior counsel assisted by Mr. S.
Deb, learned counsel for the petitioner at the outset, has argued that
2024:MLHC:749
though the matter is a contractual dispute, there has been a considerable
shift in the scope of judicial review which would make the writ petition
maintainable. In the instant case, she submits the issue is not merely of a
termination of contract and computation of damages, which would
typically invoke arbitration, but instead the issues center on the
arbitrariness of the respondents in terminating the contract despite their
own lapses, and the subsequent re-tendering of the project, which would
result in loss being caused to the public exchequer and as such she
contends the case also has public law character. In support of these
contentions, the learned Senior counsel has placed reliance on the
following judgments:-
i) ABL International Ltd. vs. Export Credit Guarantee Corporation of India Ltd., (2004) 3 SCC 553
ii) Joshi Technologies International Inc vs. Union of India (2015) 7 SCC 728
iii) M.P. Power Management Co. Ltd. Jabalpur vs. Sky Power Southeast Solar India Pvt. Ltd. (2023) 2 SCC 703
iv) Subodh Kumar Singh Rathour vs. Chief Executive Officer, 2024 SCC OnLine 1682
4. It is further submitted that time is not of essence in the
contract, inasmuch as, from the initial stage though the contract was
entered into on 21.12.2020, the respondents had paid the advance only on
2024:MLHC:749
29.5.2021, thereby delaying the effective date of the contract, though the
petitioner promptly on the execution of the contract, had submitted the
performance bank guarantee on 30.12.2020, and also advance payment
bank guarantee on 12.01.2021. It is also submitted that substantial delay
was caused by the respondents in handing over the work sites, as also the
failure of the respondents to release payments on time. Learned Sr.
counsel then contends that the termination was illegal and arbitrary, as
the show cause notice which was issued on 2.5.2023 itself is
unwarranted, as at that point of time the completion of the project had
been extended to 30.6.2023. The respondents' non-cooperation she
contends, and their failure to take corrective action in time had resulted in
the delays in the project. Though substantial progress in the works had
been achieved, she submits the action of the respondents in re-tendering
the works, will result in unnecessary financial strain on the exchequer, as
the same will result in increase in costs and also delay the project's
completion, and further the re-tender decision being highly arbitrary, has
affected the petitioner's rights. On the point of the executed bank
guarantees made under clause 13 of the Conditions of Contract, the
learned Senior counsel submits that the claim for encashment of the
remaining bank guarantees is unsustainable as the respondents holds
approximately 3.15 crores as retention money and Rs. 1.85 crores worth
2024:MLHC:749
of work is completed but not billed. As such she submits, the respondents
cannot be allowed to encash the bank guarantees amounting to Rs.
3,32,30,000/-, at this stage.
5. The learned Senior counsel in furtherance of her
submissions, has relied upon the rejoinder affidavit filed on behalf of the
petitioner company, to argue in detail the various aspects of the
explanation given to the respondents for the delay caused, the extension
which was allowed till 30.06.2023, and has laid great emphasis on the
prayer of the petitioner company to allow it to complete the remaining
works by December, 2024, without any escalation in the rates. The
learned Senior counsel has then submitted that the situation has been
caused due to the unreasonable deadlines and arbitrary action resorted to
by the respondents, and further has contended that there is no claim for
any amount from the respondents to render the instant dispute arbitrable,
but the issues raised, squarely deal with the reasonableness of State
action in the illegal termination of the contract, and the re-tendering
process. The re-tendering she submits, apart from causing loss to the
public exchequer, is also not feasible as the works will never be able to
be completed within the time as scheduled. She therefore prays that the
impugned letter of termination as well as the tender notification be set
2024:MLHC:749
aside and quashed, and the petitioner company be allowed to complete
the remaining portion of the works.
6. Mr. A.S. Pandey, learned counsel on behalf of the respondents
Nos. 2 to 5, has submitted that the petitioner company has raised disputed
questions of facts, and in this context, has referred to the time schedule
annexed to the writ petition to show that the petitioner company was
required to adhere to the said schedule, which however it failed to do so.
He submits that the project was to be completed within the period of
18(eighteen) months from 21.12.2020, and though the package was made
effective on 29.05.2021, with the completion date being 28.11.2022, the
petitioner even by this date had not completed anything worthwhile in the
entire project. The learned counsel has vehemently argued that the writ
petition is not maintainable and that the petitioner company has
efficacious alternative remedy in the terms of the contract itself, wherein
at clause 45, it has been provided that any dispute arising out of the
contract would be settled through arbitration, and this aspect he submits
is fortified, more so by the prayers sought by the petitioner company in
the instant writ, which shows that the disputes relate to adjudication of a
contract, and therefore arbitration is the appropriate remedy. The
petitioner company, he submits is essentially seeking specific
2024:MLHC:749
performance of a contract, which stood terminated solely on account of
admitted delays and breaches on the part of the petitioner company. It is
further submitted that the petitioner company has not approached this
Court with clean hands and suppressed material facts, and has not even
placed the bank guarantee document on record before this Court, and
instead has filed incomplete bank guarantee documents through a Misc.
application. He then contends that the instant writ petition is an abuse of
the legal process, as the petitioner company is essentially seeking
directions from this Court to revive a contract that has been terminated,
even after being given due hearing and ample opportunity to complete the
project. It is further submitted that there can be no judicial review in
commercial matters, wherein a contract has been terminated when the
right has been vested on the Employer to terminate the same.
7. The learned counsel then submits that a bank guarantee is an
independent contract between the Bank and the beneficiary, and the Bank
is always obliged to honour its guarantee, and that the petitioner company
through the instant writ petition is essentially seeking to obtain illegal
benefits by retaining the bank guarantees as well as the advance
mobilization amounts already given. It has also been submitted that in
spite several attempts to encash the remaining bank guarantees from the
2024:MLHC:749
Union Bank of India, the Bank it appears, on instructions and pressure
applied by the petitioner company, has resisted to same though legally
bound to do so. Learned counsel has taken this Court through a series of
letters and emails dated 07.02.2024 onwards till 27.06.2024, whereby
requests have been made for revocation of the bank guarantees which are
still to be honoured.
8. The learned counsel further submits that though the
termination was as far back as 15.12.2023, no urgency was shown by the
petitioner company who has approached this Court only on 24.04.2024,
and without pursuing the matter effectively before this Court thereafter,
after a period of 3(three) months on 25.07.2024, had filed a Misc.
application praying for staying of the encashment of the bank guarantee.
He submits that the contract having exhaustively provided for dealing
with such situations, as can be seen from clauses 42.2, and 42.2.2, apart
from clauses 44.1 and 45, the actions of the respondents is justified in
terminating the contract and the petitioner company has adequate
alternate remedy to resort to, if aggrieved in any manner.
9. Heard learned counsel for the parties.
2024:MLHC:749
10. It is to be noted that essentially the dispute that has been
brought before the Court is contractual, which the petitioner however has
sought invocation of writ jurisdiction on the grounds as have been set
forth and argued by the learned Senior counsel for the petitioner. The
judgment of ABL International Ltd. vs. Export Credit Guarantee
Corporation of India Ltd., (supra) has been pressed in support of the
contention that a writ court can issue suitable directions to set right
arbitrary actions of the State. However, on a close examination of the
facts of the present case, especially the sequence of events in a contract
of great public utility, what can be seen is that the petitioner on the tardy
progress of work had been show caused and in reply thereto, apart from
the same not being satisfactory has also brought into play disputed facts
which are impossible to be determined by a writ court. It is not the case
that the disputed question of facts present are minor or ancillary to the
issue, but in fact strike at the very core of the dispute, as they involve
questions as to the cause of delay which the petitioner though has
attributed to certain circumstances and reasons, however has not
produced any tangible material to substantiate the same. Thus, the
decision rendered in ABL International Ltd. vs. Export Credit
Guarantee Corporation of India Ltd., is of no assistance to the writ
petitioner, especially with the detailed mechanism for alternate remedy
2024:MLHC:749
being present in the contract agreement itself. Further, the case of Joshi
Technologies International Inc vs. Union of India (supra) cited by the
petitioner in para 69 itself, has provided that though there is no absolute
bar to the maintainability of a writ petition even in contractual matters,
where there are disputed question of facts or even when a monetary claim
is raise but however at para 55 and 69.2 thereof, it has been held as
follows:-
"55. Law in this aspect has developed through catena of judgments of this Court and from the reading of these judgments it would follow that in pure contractual matters the extraordinary remedy of writ under Article 226 or Article 32 of the Constitution cannot be invoked. However, in a limited sphere such remedies are available only when the non-Government contracting party is able to demonstrate that it is a public law remedy which such party seeks to invoke, in contradistinction to the private law remedy simpliciter under the contract. Some of the case law to bring home this cardinal principle is taken note of hereinafter.
69.2. Whenever a particular mode of settlement of dispute is provided in the contract, the High Court would refuse to exercise its discretion under Article 226 of the Constitution and relegate the party to the said mode of settlement, particularly when settlement of disputes is to be resorted to through the means of arbitration."
11. In the case of M.P. Power Management Co. Ltd. Jabalpur
vs. Sky Power Southeast Solar India Pvt. Ltd. (supra) which has also
been relied upon by the petitioner, the same is also of no assistance as in
2024:MLHC:749
the facts of the present case, breaches in the contract had been
acknowledged by the petitioner itself, and the action of the respondent in
terminating the contract being based on cogent grounds after due notice
to the petitioner, natural justice had also been served. The dispute in view
of the facts, in the considered view of this Court being in the realm of
private law, no remedy is therefore available before a writ court. Coming
to the case of Subodh Kumar Singh Rathour vs. Chief Executive
Officer (supra) which has exhaustively discussed, the scope of judicial
review of the actions of the State in the matters relating to a
contract/tender disputes, it is worthwhile to note that the cancellation of
the contract in the said case was held to be illegal as there was an
arbitrary exercise of powers at the behest of State functionaries. Further,
in the same judgment the Supreme Court in para-43 thereof, had
highlighted the doctrines and principles guiding judicial review, such as
the principles of natural justice, reasonableness and proportionality,
which ensured that administrative actions are not arbitrary discriminatory
or capricious. In the case at hand however, none of these principles
having been breached, as the termination was made on the basis of an
elaborate decision making process, the said judgment does not come to
the aid of the petitioner.
2024:MLHC:749
12. As discussed earlier, without reiterating the events in detail,
the petitioner had been issued three show cause notices, the last being
dated 02.05.2023, whereof in reply thereto, the petitioner by letter dated
08.05.2023, had acknowledged the lapses on their part by citing various
reasons, and further in spite of the extension granted, failed to speed up
the progress of the work. It is also to be noted again herein that review
meetings had been held but as recorded and the picture that emerged was
that though the petitioner had already availed of mobilization advances, it
was not in a position to implement the project. In this context, it is
relevant to refer to a letter of the writ petitioner dated 05.08.2023,
wherein in the explanation that had been offered, at para-1 of the said
letter itself it was admitted that they had not been able to complete even
one Sub-station, due to various reasons, and had committed therein that
progress would be seen after 60 days. From the bare facts present in the
materials on record, the subsequent action of termination by the
respondent can in no manner be said to be arbitrary or illegal.
13. Another aspect that deserves consideration is that the
petitioner has sought stay orders in the encashment of bank guarantees
that have been furnished by the petitioner, the encashment thereof, so far,
as submitted, has been thwarted as is evident from the materials and
2024:MLHC:749
correspondence on record. A bank guarantee as is well known, is an
independent contract between the bank and the beneficiary and a bank is
always obliged to honour its guarantee. A dispute between the beneficiary
and the party on whose instance the bank guarantee has been furnished, is
immaterial, as it is settled law that courts should not ordinarily interfere
with the invocation or encashment of bank guarantees, so long as the
invocation is in the terms of the bank guarantee. Numerous judgments in
this regard have reiterated this position on the limited scope of
interference such as in the case of Atlanta Infrastructure Limited vs.
Delta Marine Company Ltd., (2021) 20 SCC 593, wherein it was held
that the only reason for interference could be egregious fraud and fraud
must be relatable to the bank guarantee, none of which is present in the
instant case.
14. On a footnote, another aspect that cannot be ignored is that
the petitioner has made a challenge to the notification for re-tendering,
and the termination of contract at a very belated stage. Even in the
conduct of the proceedings before this Court, the petitioner has been
tardy and as noted from the order sheets, the matter did not proceed as the
counsel appearing for the petitioner could not obtain instructions from
07.05.2024 and sought time repeatedly till 16.07.2024, when it is
2024:MLHC:749
submitted that they wanted to pursue the matter, and as such the matter
was listed for admission hearing on 25.07.2024. Thereafter only,
applications were made for stay of the encashment of the bank
guarantees, which was after a period of over 3(three) months since the
institution of the writ petition, that too when it was pointed out that no
details whatsoever had been provided in the writ petition of the bank
guarantees to warrant any consideration for stay of encashment.
15. In the given facts and circumstances of the case therefore, as
discussed above, there being no element of arbitrariness or
unreasonableness on the part of the respondents to warrant any
interference in exercise of powers under Article 226, and the dispute
being purely contractual and in the realm of private law, and more so
with alternative remedy being provided in the contract itself, the writ
petition is devoid of any merit and is accordingly dismissed.
Chief Justice (Acting)
Meghalaya 20.08.2024 "V. Lyndem PS"
Powered by TCPDF (www.tcpdf.org)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!