Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Date Of Decision: 20.08.2024 vs State Of Meghalaya
2024 Latest Caselaw 559 Meg

Citation : 2024 Latest Caselaw 559 Meg
Judgement Date : 20 August, 2024

High Court of Meghalaya

Date Of Decision: 20.08.2024 vs State Of Meghalaya on 20 August, 2024

Author: H. S. Thangkhiew

Bench: H. S. Thangkhiew

                                                      2024:MLHC:749




 Serial No. 01
 Supplementary List
                   HIGH COURT OF MEGHALAYA
                       AT SHILLONG
WP(C) No. 116 of 2024
                                 Date of Decision: 20.08.2024

      M/s RKI India Limited                    ... Petitioner(s)
            - Versus -
  1. State of Meghalaya,
      Represented by the Commissioner & Secretary,
      To the Govt. of Meghalaya, Power Department,
      Shillong.
   2. The Chairman cum Managing Director,
      MePDCL, Lumjingshai, Shillong.
   3. The Director (Distribution), MePDCL,
      Meghalaya, Shillong.
   4. The Chief Engineer (Projects) MePDCL,
      Meghalaya, Shillong
   5. The Superintending Engineer (Projects)
      MePDCL, Tura
   6. The Asian Development Bank,
      Represented by its Project Manager     ... Respondent(s)

Coram:

Hon'ble Mr. Justice H. S. Thangkhiew, Chief Justice (Acting)

Appearance:

For the Petitioner(s) : Ms. Liz Mathew, Sr. Adv. with Ms. B. Vennemalai, Adv.

Mr. S. Deb, Adv.

For the Respondent(s)   :    Mr. A.S. Pandey, Adv.
                             Ms. R. Colney, GA




                                                           2024:MLHC:749




___________________________________________________________

i) Whether approved for reporting in Yes/No Law journals etc.:


ii)   Whether approved for publication
      in press:                                          Yes/No
                 JUDGMENT AND ORDER


1. The petitioner company on being the successful bidder in a

tender floated by the respondent No. 2, for the work titled 'East Garo

Hills Circle-Distribution System Improvement: 33/11 KV Sub-station

Development', was issued the Letter of Allotment (LoA) and a contract

agreement, was duly executed on 21.12.2020, between the respondent

No. 2 and the petitioner, for the said work amounting to Rs.

74,34,56,822/- with the completion time for the said works being 18

months from the effective date of commission.

2. It appears that though the contract was scheduled to be

completed in November, 2022, taking the effective date of contract to

have commenced from 29.05.2021, the work was delayed due to various

reasons which the petitioner company maintained was due to

circumstances beyond its control. On 02.05.2023, a show cause notice

was issued by the respondent No. 4, directing the petitioner to answer as

to why the contract should not be terminated failing which clause 42.2 of

2024:MLHC:749

the conditions of contract would be invoked. The petitioner replied to the

said show cause assuring the respondents that the project would be

completed by December, 2023. Thereafter the petitioner was called for a

review meeting, on 06.07.2023 which however, the representative of the

petitioner company did not attend citing reasons that he was suffering

from COVID, the absence whereof, was not taken kindly by the

respondents. Subsequent review meetings were then held on 06.07.2023

and 03.08.2023, and though the petitioner submitted a representation on

05.08.2023, replying to the issues raised in the minutes of the review

meeting, the respondent No. 4 on 22.8.2023 issued a notice of

termination, highlighting the slow progress of the work. The respondent

No. 4 then on 15.12.2023 issued the letter of termination and decided to

invoke clause 42.2.2 for termination w.e.f. 16.12.2023. Thereafter, the

respondent No. 4 floated a fresh tender on 08.02.2024, for the remaining

works, with the dead line for submission of bids on 25.04.2024. The

petitioner company being aggrieved is therefore before this Court

impugning the letter of termination dated 15.12.2023 and the tender

notice dated 08.03.2024.

3. Ms. Liz. Mathew, learned Senior counsel assisted by Mr. S.

Deb, learned counsel for the petitioner at the outset, has argued that

2024:MLHC:749

though the matter is a contractual dispute, there has been a considerable

shift in the scope of judicial review which would make the writ petition

maintainable. In the instant case, she submits the issue is not merely of a

termination of contract and computation of damages, which would

typically invoke arbitration, but instead the issues center on the

arbitrariness of the respondents in terminating the contract despite their

own lapses, and the subsequent re-tendering of the project, which would

result in loss being caused to the public exchequer and as such she

contends the case also has public law character. In support of these

contentions, the learned Senior counsel has placed reliance on the

following judgments:-

i) ABL International Ltd. vs. Export Credit Guarantee Corporation of India Ltd., (2004) 3 SCC 553

ii) Joshi Technologies International Inc vs. Union of India (2015) 7 SCC 728

iii) M.P. Power Management Co. Ltd. Jabalpur vs. Sky Power Southeast Solar India Pvt. Ltd. (2023) 2 SCC 703

iv) Subodh Kumar Singh Rathour vs. Chief Executive Officer, 2024 SCC OnLine 1682

4. It is further submitted that time is not of essence in the

contract, inasmuch as, from the initial stage though the contract was

entered into on 21.12.2020, the respondents had paid the advance only on

2024:MLHC:749

29.5.2021, thereby delaying the effective date of the contract, though the

petitioner promptly on the execution of the contract, had submitted the

performance bank guarantee on 30.12.2020, and also advance payment

bank guarantee on 12.01.2021. It is also submitted that substantial delay

was caused by the respondents in handing over the work sites, as also the

failure of the respondents to release payments on time. Learned Sr.

counsel then contends that the termination was illegal and arbitrary, as

the show cause notice which was issued on 2.5.2023 itself is

unwarranted, as at that point of time the completion of the project had

been extended to 30.6.2023. The respondents' non-cooperation she

contends, and their failure to take corrective action in time had resulted in

the delays in the project. Though substantial progress in the works had

been achieved, she submits the action of the respondents in re-tendering

the works, will result in unnecessary financial strain on the exchequer, as

the same will result in increase in costs and also delay the project's

completion, and further the re-tender decision being highly arbitrary, has

affected the petitioner's rights. On the point of the executed bank

guarantees made under clause 13 of the Conditions of Contract, the

learned Senior counsel submits that the claim for encashment of the

remaining bank guarantees is unsustainable as the respondents holds

approximately 3.15 crores as retention money and Rs. 1.85 crores worth

2024:MLHC:749

of work is completed but not billed. As such she submits, the respondents

cannot be allowed to encash the bank guarantees amounting to Rs.

3,32,30,000/-, at this stage.

5. The learned Senior counsel in furtherance of her

submissions, has relied upon the rejoinder affidavit filed on behalf of the

petitioner company, to argue in detail the various aspects of the

explanation given to the respondents for the delay caused, the extension

which was allowed till 30.06.2023, and has laid great emphasis on the

prayer of the petitioner company to allow it to complete the remaining

works by December, 2024, without any escalation in the rates. The

learned Senior counsel has then submitted that the situation has been

caused due to the unreasonable deadlines and arbitrary action resorted to

by the respondents, and further has contended that there is no claim for

any amount from the respondents to render the instant dispute arbitrable,

but the issues raised, squarely deal with the reasonableness of State

action in the illegal termination of the contract, and the re-tendering

process. The re-tendering she submits, apart from causing loss to the

public exchequer, is also not feasible as the works will never be able to

be completed within the time as scheduled. She therefore prays that the

impugned letter of termination as well as the tender notification be set

2024:MLHC:749

aside and quashed, and the petitioner company be allowed to complete

the remaining portion of the works.

6. Mr. A.S. Pandey, learned counsel on behalf of the respondents

Nos. 2 to 5, has submitted that the petitioner company has raised disputed

questions of facts, and in this context, has referred to the time schedule

annexed to the writ petition to show that the petitioner company was

required to adhere to the said schedule, which however it failed to do so.

He submits that the project was to be completed within the period of

18(eighteen) months from 21.12.2020, and though the package was made

effective on 29.05.2021, with the completion date being 28.11.2022, the

petitioner even by this date had not completed anything worthwhile in the

entire project. The learned counsel has vehemently argued that the writ

petition is not maintainable and that the petitioner company has

efficacious alternative remedy in the terms of the contract itself, wherein

at clause 45, it has been provided that any dispute arising out of the

contract would be settled through arbitration, and this aspect he submits

is fortified, more so by the prayers sought by the petitioner company in

the instant writ, which shows that the disputes relate to adjudication of a

contract, and therefore arbitration is the appropriate remedy. The

petitioner company, he submits is essentially seeking specific

2024:MLHC:749

performance of a contract, which stood terminated solely on account of

admitted delays and breaches on the part of the petitioner company. It is

further submitted that the petitioner company has not approached this

Court with clean hands and suppressed material facts, and has not even

placed the bank guarantee document on record before this Court, and

instead has filed incomplete bank guarantee documents through a Misc.

application. He then contends that the instant writ petition is an abuse of

the legal process, as the petitioner company is essentially seeking

directions from this Court to revive a contract that has been terminated,

even after being given due hearing and ample opportunity to complete the

project. It is further submitted that there can be no judicial review in

commercial matters, wherein a contract has been terminated when the

right has been vested on the Employer to terminate the same.

7. The learned counsel then submits that a bank guarantee is an

independent contract between the Bank and the beneficiary, and the Bank

is always obliged to honour its guarantee, and that the petitioner company

through the instant writ petition is essentially seeking to obtain illegal

benefits by retaining the bank guarantees as well as the advance

mobilization amounts already given. It has also been submitted that in

spite several attempts to encash the remaining bank guarantees from the

2024:MLHC:749

Union Bank of India, the Bank it appears, on instructions and pressure

applied by the petitioner company, has resisted to same though legally

bound to do so. Learned counsel has taken this Court through a series of

letters and emails dated 07.02.2024 onwards till 27.06.2024, whereby

requests have been made for revocation of the bank guarantees which are

still to be honoured.

8. The learned counsel further submits that though the

termination was as far back as 15.12.2023, no urgency was shown by the

petitioner company who has approached this Court only on 24.04.2024,

and without pursuing the matter effectively before this Court thereafter,

after a period of 3(three) months on 25.07.2024, had filed a Misc.

application praying for staying of the encashment of the bank guarantee.

He submits that the contract having exhaustively provided for dealing

with such situations, as can be seen from clauses 42.2, and 42.2.2, apart

from clauses 44.1 and 45, the actions of the respondents is justified in

terminating the contract and the petitioner company has adequate

alternate remedy to resort to, if aggrieved in any manner.

9. Heard learned counsel for the parties.

2024:MLHC:749

10. It is to be noted that essentially the dispute that has been

brought before the Court is contractual, which the petitioner however has

sought invocation of writ jurisdiction on the grounds as have been set

forth and argued by the learned Senior counsel for the petitioner. The

judgment of ABL International Ltd. vs. Export Credit Guarantee

Corporation of India Ltd., (supra) has been pressed in support of the

contention that a writ court can issue suitable directions to set right

arbitrary actions of the State. However, on a close examination of the

facts of the present case, especially the sequence of events in a contract

of great public utility, what can be seen is that the petitioner on the tardy

progress of work had been show caused and in reply thereto, apart from

the same not being satisfactory has also brought into play disputed facts

which are impossible to be determined by a writ court. It is not the case

that the disputed question of facts present are minor or ancillary to the

issue, but in fact strike at the very core of the dispute, as they involve

questions as to the cause of delay which the petitioner though has

attributed to certain circumstances and reasons, however has not

produced any tangible material to substantiate the same. Thus, the

decision rendered in ABL International Ltd. vs. Export Credit

Guarantee Corporation of India Ltd., is of no assistance to the writ

petitioner, especially with the detailed mechanism for alternate remedy

2024:MLHC:749

being present in the contract agreement itself. Further, the case of Joshi

Technologies International Inc vs. Union of India (supra) cited by the

petitioner in para 69 itself, has provided that though there is no absolute

bar to the maintainability of a writ petition even in contractual matters,

where there are disputed question of facts or even when a monetary claim

is raise but however at para 55 and 69.2 thereof, it has been held as

follows:-

"55. Law in this aspect has developed through catena of judgments of this Court and from the reading of these judgments it would follow that in pure contractual matters the extraordinary remedy of writ under Article 226 or Article 32 of the Constitution cannot be invoked. However, in a limited sphere such remedies are available only when the non-Government contracting party is able to demonstrate that it is a public law remedy which such party seeks to invoke, in contradistinction to the private law remedy simpliciter under the contract. Some of the case law to bring home this cardinal principle is taken note of hereinafter.

69.2. Whenever a particular mode of settlement of dispute is provided in the contract, the High Court would refuse to exercise its discretion under Article 226 of the Constitution and relegate the party to the said mode of settlement, particularly when settlement of disputes is to be resorted to through the means of arbitration."

11. In the case of M.P. Power Management Co. Ltd. Jabalpur

vs. Sky Power Southeast Solar India Pvt. Ltd. (supra) which has also

been relied upon by the petitioner, the same is also of no assistance as in

2024:MLHC:749

the facts of the present case, breaches in the contract had been

acknowledged by the petitioner itself, and the action of the respondent in

terminating the contract being based on cogent grounds after due notice

to the petitioner, natural justice had also been served. The dispute in view

of the facts, in the considered view of this Court being in the realm of

private law, no remedy is therefore available before a writ court. Coming

to the case of Subodh Kumar Singh Rathour vs. Chief Executive

Officer (supra) which has exhaustively discussed, the scope of judicial

review of the actions of the State in the matters relating to a

contract/tender disputes, it is worthwhile to note that the cancellation of

the contract in the said case was held to be illegal as there was an

arbitrary exercise of powers at the behest of State functionaries. Further,

in the same judgment the Supreme Court in para-43 thereof, had

highlighted the doctrines and principles guiding judicial review, such as

the principles of natural justice, reasonableness and proportionality,

which ensured that administrative actions are not arbitrary discriminatory

or capricious. In the case at hand however, none of these principles

having been breached, as the termination was made on the basis of an

elaborate decision making process, the said judgment does not come to

the aid of the petitioner.

2024:MLHC:749

12. As discussed earlier, without reiterating the events in detail,

the petitioner had been issued three show cause notices, the last being

dated 02.05.2023, whereof in reply thereto, the petitioner by letter dated

08.05.2023, had acknowledged the lapses on their part by citing various

reasons, and further in spite of the extension granted, failed to speed up

the progress of the work. It is also to be noted again herein that review

meetings had been held but as recorded and the picture that emerged was

that though the petitioner had already availed of mobilization advances, it

was not in a position to implement the project. In this context, it is

relevant to refer to a letter of the writ petitioner dated 05.08.2023,

wherein in the explanation that had been offered, at para-1 of the said

letter itself it was admitted that they had not been able to complete even

one Sub-station, due to various reasons, and had committed therein that

progress would be seen after 60 days. From the bare facts present in the

materials on record, the subsequent action of termination by the

respondent can in no manner be said to be arbitrary or illegal.

13. Another aspect that deserves consideration is that the

petitioner has sought stay orders in the encashment of bank guarantees

that have been furnished by the petitioner, the encashment thereof, so far,

as submitted, has been thwarted as is evident from the materials and

2024:MLHC:749

correspondence on record. A bank guarantee as is well known, is an

independent contract between the bank and the beneficiary and a bank is

always obliged to honour its guarantee. A dispute between the beneficiary

and the party on whose instance the bank guarantee has been furnished, is

immaterial, as it is settled law that courts should not ordinarily interfere

with the invocation or encashment of bank guarantees, so long as the

invocation is in the terms of the bank guarantee. Numerous judgments in

this regard have reiterated this position on the limited scope of

interference such as in the case of Atlanta Infrastructure Limited vs.

Delta Marine Company Ltd., (2021) 20 SCC 593, wherein it was held

that the only reason for interference could be egregious fraud and fraud

must be relatable to the bank guarantee, none of which is present in the

instant case.

14. On a footnote, another aspect that cannot be ignored is that

the petitioner has made a challenge to the notification for re-tendering,

and the termination of contract at a very belated stage. Even in the

conduct of the proceedings before this Court, the petitioner has been

tardy and as noted from the order sheets, the matter did not proceed as the

counsel appearing for the petitioner could not obtain instructions from

07.05.2024 and sought time repeatedly till 16.07.2024, when it is

2024:MLHC:749

submitted that they wanted to pursue the matter, and as such the matter

was listed for admission hearing on 25.07.2024. Thereafter only,

applications were made for stay of the encashment of the bank

guarantees, which was after a period of over 3(three) months since the

institution of the writ petition, that too when it was pointed out that no

details whatsoever had been provided in the writ petition of the bank

guarantees to warrant any consideration for stay of encashment.

15. In the given facts and circumstances of the case therefore, as

discussed above, there being no element of arbitrariness or

unreasonableness on the part of the respondents to warrant any

interference in exercise of powers under Article 226, and the dispute

being purely contractual and in the realm of private law, and more so

with alternative remedy being provided in the contract itself, the writ

petition is devoid of any merit and is accordingly dismissed.

Chief Justice (Acting)

Meghalaya 20.08.2024 "V. Lyndem PS"

Powered by TCPDF (www.tcpdf.org)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter