Citation : 2025 Latest Caselaw 8650 Mad
Judgement Date : 17 November, 2025
OP.No.957 of 2019
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED : 17.11.2025
CORAM
THE HONOURABLE Mr.JUSTICE N.ANAND VENKATESH
OP.No.957 of 2019
Union of India
Rep. By Chief Engineer (AF)
Bengaluru – 560 022. .... Petitioner
Vs
M/s.VCC Enterprises
Chalam Nivas, No.19, 1st Main Road
Krishnapuram, Thirunindravur
Chennai – 602 024. .... Respondent
Prayer : Original Petition (Commercial Division) filed under Section 34 of
Arbitration and Conciliation Act, 1996, praying (a) to set aside the award
made and published on 27.02.2018 (received on 06.03.2018) and Amended
award dated 14.03.2018 (received on 28.03.2018) passed by the Sole
Arbitrator in Arbitration proceedings Ref.C.A.No.CE(AF)BANG/18 of
2007-08 PROVISION OF CERTAIN SINGLE ACCOMMODATION FOR
279 WIRMEN AT TAMBARAM, CHENNAI; (b) cost of the present
petition and pass orders.
For Petitioner : Mr.G.Ilangovan
Senior Panel Counsel
For Respondent : Mr.T.V.Lakshmanan
1/15
https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )
OP.No.957 of 2019
ORDER
This petition has been filed under Section 34 of the Arbitration and
Conciliation Act, 1996 [for brevity referred to as 'Act'] challenging the
award passed by the sole Arbitrator dated 27.02.2018.
2. The respondent/claimant is a Contractor who participated in the
tender called for by the petitioner for undertaking a work of “Provision of
Certain Single Accommodation for 279 Airmen at Tambaram, Chennai”.
The contract was for a total sum of Rs.5,87,34,962.37. The tender
submitted by the respondent was accepted on 14.01.2008 and the work
order was issued on 23.01.2008. The date of commencement of work was
fixed on 28.01.2008 and it was supposed to be completed by 27.09.2009.
However, due to various reasons, the commencement of work was getting
prolonged and the period was extended from time to time. Ultimately, the
contract was cancelled on 05.10.2013.
3. As a result of the above dispute, as agreed in the terms and
conditions of the tender, the dispute was referred to a sole Arbitrator.
https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )
4. The respondent/claimant made the following claims :
Claim No (1) - Loss due to delay in decision on hard rock Rs.1,66,10,000.00 Claim No (2) - Reimbursement of Addl cost Rs.81,65,000.00 Claim No (3) - Under pricing of DOs Rs.6,62,000.00 Claim No (4) - Loss of profit & establishment Rs.4,63,00,000.00 Claim No (5) - Loss due to interests paid to other Rs.37,00,000.00 establishment Claim No (6) - Loss due to confiscated T&P Rs.28,88,750.00 Claim No (7) - Balance payment in Final bill Rs.47,47,700.00 Claim No (8) - Risk & cost of UOI Rs.Nil Claim No (9) - Loss due to illegal cancellation Rs.65,76,824.00 Claim No (10) - Damage due to mental agony Rs.1,00,00,000.00 Claim No (11) - Interest past, Pendente lite and future To be calculated Claim No (12) - Cost of Arbitration Reference = To be decided during hearing TOTAL Rs.9,97,49,274.00 Say Rs.9,97,49,000
5. The petitioner submitted a statement of defence and denied all the
claims made by the respondent. The petitioner also made a counter claim
for a sum of Rs.38,85,210.21 under the head of “Minus Amount of Final Bill
on Account of Execution of Work at the risk and cost of the Contractor,
Levy of Compensation, Security Deposit for ATT, Roof Treatment etc.,” and
a further sum of Rs.4,00,000.00 under the head of “Miscellaneous
Expenditure Consequent on Cancellation, Arbitration and Legal
Procedures”.
https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )
6. The sole Arbitrator on considering the pleadings and also the claim
and counter claim made by the respective parties, and also considering the
evidence let in by both sides, allowed Claim Nos.3, 6, 7 and 9 in favour of
the respondent/claimant, and also Claim Nos.11 & 12 which pertain to
interest and costs. The other claims were rejected and the counter claim
made by the petitioner was also rejected. Aggrieved by the award passed
by the sole Arbitrator, the Union of India has approached this Court by
filing a petition under Section 34 of the Act.
7. Heard Mr.G.Ilangovan, learned Senior Panel Counsel appearing for
the petitioner and Mr.T.V.Lakshmanan, learned counsel appearing for the
respondent.
8. Mr.G.Ilangovan, learned Senior Panel Counsel appearing on behalf
of the petitioner confines his arguments to the claims that were awarded in
favour of the respondent viz., Claim 3, 6, 7 and 9, and consequently also
questioned the interest that were awarded as against these claims and the
costs that was imposed by the sole Arbitrator.
https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )
9. Claim No.3 pertains to 'Under pricing of the Deviation Orders
[DOs] and certain DOs due for payment but not initiated / paid'. This
claim was made by the respondent on the ground that such a deviation order
was necessitated either due to design fault or improper soil investigation
carried out, than what was specified in the contract. In view of the same,
the pricing had to be fixed based on the costs actually incurred by the
claimant. This costs was fixed by the Board of Officers [BOO] at
Rs.4,940.91 per cubic metre and whereas, what was allowed / permitted was
only Rs.3,304.26 per cubic metre.
10. The main ground on which the learned Senior Panel Counsel
appearing for the petitioner questioned the award passed by the sole
Arbitrator under Claim No.3 is that the claimant had accepted the finalised
rate of Rs.3,304.26 per cubic metre on 19.03.2012 and it was signed in the
presence of the witnesses. Therefore, whatever that was accepted by the
claimant alone must be awarded and the original amount that was fixed,
cannot be taken into account for calculating the compensation under this
head.
https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )
11. In order to appreciate the findings of the learned sole Arbitrator, it
will be relevant to take note of the background facts of this case. As per the
work order, the date of commencement of work was fixed on 28.01.2008
and the date of completion was fixed on 27.09.2009. The sole Arbitrator on
considering the evidence, found that there were various obstructions right
from the commencement of the work. Even the layout of the building was
shifted 5 mtrs. away from the edge of the existing road as against 10 mtrs.,
as per the original site plan. Apart from that, the CI water supply lines that
was running across the entire stretch of the building, required removal and
re-routing. One of the major obstructions encountered by the claimant was
that the excavation of hard rock required chiselling. The BOO has assessed
the rates for excavation of hard rock and recommended Rs.4940.91 per
cubic metre. However, the petitioner/UOI allowed only Rs.3,304.20 per
cubic metre.
12. The petitioner relied upon Amendment No.2 dated 19.03.2012,
where the Chief Engineer had reduced the rate to Rs.3,304.20 per cubic
metre. There is no doubt that the petitioner has also signed this document.
https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )
13. The sole Arbitrator while dealing with this issue, took into
consideration the fact that, originally under Amendment No.1 dated
02.08.2010, the rate was provisionally fixed at Rs.3,304.20 per cubic meter
and this was subsequently refixed by BOO at Rs.4,940.91 per cubic metre.
The sole Arbitrator who is the Additional Director General (Contracts), is
well-versed in such contracts, came to a conclusion that the BOO had
recommended the rate at Rs.4,940.91 per cubic metre and that the same
cannot be reduced by the Union of India. Apart from that, the respondent
through its letter dated 04.03.2012 had agreed for the provisional rates fixed
by BOO and not the final rates, as the subsequent rate was fixed by BOO, by
its letter dated 14/18 May 2010. Hence, the sole Arbitrator held that the
rates fixed by BOO cannot be unilaterally reduced by the petitioner, without
assigning any reasons. Therefore, the sole Arbitrator has awarded the
compensation by fixing it at the rate of Rs.4,940.91 per cubic metre.
14. The above reasoning given by the sole Arbitrator does not suffer
from any perversity or patent illegality. The sole Arbitrator who has
experience in such contracts, has come to the conclusion that the final rate
https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )
fixed by BOO cannot be reduced by the Chief Engineer. This finding,
arrived by the sole Arbitrator, based on the background facts of the case,
does not warrant interference of this Court.
15. The next issue pertains to Claim No.6 namely “Loss due to
confiscated T &P”. This claim was questioned by the petitioner on the
ground that whatever that was available in the site, was taken away by the
claimant and nothing remained in the site and inspite of the same, the sole
Arbitrator had assumed that, only 50% of the materials were removed from
the site and for the balance 50%, the compensation has been fixed and
awarded in favour of the respondent. It was further contended that under
Clause 54 of the General Conditions of Contract [GCC], the respondent has
the power to confiscate the materials in the event of default in completing
the contract. In the case on hand, the sole Arbitrator on considering the
repeated delays caused in completing the contract work and the extension of
time that was granted by the petitioner, came to a conclusion that time is not
the essence of this contract. However, after the expiry of last extension
which came to an end on 30.04.2012, the contract was cancelled on
05.10.2013, when the contract was not even in subsistence. In fact, the
https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )
claimant was continuing to hold the materials till 05.10.2013.
16. Exhibit-C49, pertains to the materials that were removed from the
site. It is seen that vide Ext.C49, letter dated 06.08.2013, the claimant had
requested the Security Officer, Tambaram, (through AGE B/R(P),
Tambaram) for removal of 850 nos. of Old Cementing Steel Sheets; 300
nos. of Old Spans Steel and 550 nos. of Old Props Steel. However, the
claimant was permitted to remove only 425 nos, 150 nos., and 175 nos. of
the respective materials. The same is apparent from the endorsement that
has been made in Ext.C49.
17. The sole Arbitrator, after considering the fact that there was
absolutely no explanation forthcoming from the petitioner regarding the
remaining materials, has rightly calculated the value of those materials and
awarded a sum of Rs.19,71,250/- to the claimant. This finding cannot be
held to be perverse or patently illegal. In fact, the claimant had sought for
nearly Rs.28,88,750/-. However, the sole Arbitrator took the effort of
making an independent calculation and assessed the claim of Rs.19,71,250/-
This also shows that the sole Arbitrator has assigned proper reasons and
https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )
calculated the correct compensation amount payable to the claimant.
18. The next issue pertains to Claim No.7, which is the “Balance
Payment of Final Bill”. It was contended on the side of the petitioner that
the Government had recovered a sum of Rs.17,00,000/- from the retention
amount of Rs.30,47,700/-, since there was no separate security deposit
available. According to the petitioner, due to non-completion of the work,
the Government had sustained huge loss and towards the same, the recovery
was made. Condition No.50 of GCC authorises the Government to levy
compensation. Therefore, the sole Arbitrator, without appreciating the fact
that the Government had the power of cancellation and levying
compensation, ought not have awarded the claim in favour of the
respondent.
19. The sole Arbitrator had already given sufficient reasons as to why
time is not the essence of the contract and has also taken into consideration
the scope of Section 55 of the Indian Contract Act, in this regard. The sole
Arbitrator also took into consideration the fact that the permission was
granted only upto 30.04.2012, but, the contract was cancelled on
https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )
05.10.2013, almost 1 ½ years after the permission was granted to complete
the work without levy of compensation. On the date when the cancellation
was made, the contract was not in subsistence.
20. Apart from the above, the sole Arbitrator made an independent
assessment / detailed assessment under various heads at Paragraph No.98 of
the award, while arriving at the net total compensation of Rs.27,14,234.53
under this claim. The sole Arbitrator also came to the conclusion that the
petitioner has not proved any loss suffered by them on account of the delay
in completion of work. On this very ground, the counter claim made by the
petitioner was also rejected.
21. The sole Arbitrator has properly appreciated the evidence and
given a factual finding, apart from making a detailed calculation under this
claim. Certainly, the findings of the sole Arbitrator under Claim No.7 does
not suffer from any perverse or patent illegality, warranting interference of
this Court.
22. Finally, this Court deals with Claim No.9 which relates to 'Loss
https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )
due to illegal cancellation'. Under this claim, the sole Arbitrator has
awarded a sum to the tune of Rs.10,16,155/- in favour of the claimant.
23. The main ground that was urged by the learned Senior Panel
Counsel appearing for the petitioner is that the issue concerns TDS deposit
and issuance of Form-16A, or credit in Section 26A or 26S of the Income
Tax Act. The claim was made on the ground that the dues for the year
2008-2009 upto 2011-2012 was uploaded only on 31.07.2013, and due to
this delay, the financial position of the claimant was adversely affected and
he was not in a position to complete the work. The claimant had claimed a
sum of Rs.65,76,824/- under this head and what was awarded by the sole
Arbitrator is Rs.10,16,155/-.
24. In the considered view of this Court, such matters which fall
within the realm of TDS deduction, cannot fall within the scope of
arbitration proceedings before the Tribunal. Useful reference can be made
to the judgment of a Division Bench of this Court in Sree Kamatchi
Amman Constructions Vs The Divisional Railway Manager Works,
Palghat Division reported in 2007 5 CTC 17.
https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )
25. Even otherwise, there is absolutely no discussion or reference to
any evidence to justify as to how the sole Arbitrator came to a conclusion
that a sum of Rs.10,16,155/- can be awarded in favour of the claimant.
Thus, the sum awarded is not supported by any evidence and has been
awarded on a mere surmise and it certainly suffers from patent illegality
under Section 34(2A) of the Act and it warrants interference of this Court.
26.The upshot of the above discussion, this Court upholds the
compensation given under Claim Nos.3, 6 and 7, and sets aside
compensation awarded under Claim No.9.
27. The next question to be dealt with is as to whether the award of
the sole Arbitrator can be modified by interfering only with one of the
claims awarded in favour of the claimant. In the light of the judgment of the
Apex Court in Gayatri Balasamy Vs ISG Nova Soft Technologies Limited
reported in (2025) 7 SCC 1, such modification is permissible, if the invalid
portion can be severed from the valid portion of the award. Certainly, the
compensation awarded for Claim No.9 can be severed from the other claims
https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )
awarded in favour of the claimant which has been upheld. Consequently,
relying upon the judgment of the Apex Court in Gayatri Balasamy referred
supra, the award can be modified.
28. Insofar as the award of interest and costs is concerned, this Court
finds that the sole Arbitrator has only awarded simple interest at the rate of
12% per annum and with regard to costs, the sole Arbitrator has only fixed
the reasonable cost of Rs.45,000/- incurred by the claimants towards making
reference, administrative costs etc.,
29. In the result, this petition is partly allowed in the above terms with
costs of Rs.1,00,000/- payable by the petitioner to the respondent.
17.11.2025
Index : Yes / No Speaking order / Non-speaking order Neutral Citation: Yes / No ds
https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )
N.ANAND VENKATESH,J.
ds
17.11.2025
https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!