Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Union Of India vs M/S.Vcc Enterprises
2025 Latest Caselaw 8650 Mad

Citation : 2025 Latest Caselaw 8650 Mad
Judgement Date : 17 November, 2025

Madras High Court

Union Of India vs M/S.Vcc Enterprises on 17 November, 2025

Author: N.Anand Venkatesh
Bench: N.Anand Venkatesh
                                                                                                       OP.No.957 of 2019

                                   IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                                       DATED : 17.11.2025

                                                               CORAM

                                  THE HONOURABLE Mr.JUSTICE N.ANAND VENKATESH

                                                        OP.No.957 of 2019

                     Union of India
                     Rep. By Chief Engineer (AF)
                     Bengaluru – 560 022.                                                  .... Petitioner
                                                                    Vs

                     M/s.VCC Enterprises
                     Chalam Nivas, No.19, 1st Main Road
                     Krishnapuram, Thirunindravur
                     Chennai – 602 024.                                               .... Respondent

                     Prayer : Original Petition (Commercial Division) filed under Section 34 of
                     Arbitration and Conciliation Act, 1996, praying (a) to set aside the award
                     made and published on 27.02.2018 (received on 06.03.2018) and Amended
                     award dated 14.03.2018 (received on 28.03.2018) passed by the Sole
                     Arbitrator in Arbitration proceedings Ref.C.A.No.CE(AF)BANG/18 of
                     2007-08 PROVISION OF CERTAIN SINGLE ACCOMMODATION FOR
                     279 WIRMEN AT TAMBARAM, CHENNAI; (b) cost of the present
                     petition and pass orders.


                                      For Petitioner          : Mr.G.Ilangovan
                                                                Senior Panel Counsel

                                      For Respondent          : Mr.T.V.Lakshmanan


                     1/15



https://www.mhc.tn.gov.in/judis                  ( Uploaded on: 19/11/2025 06:44:16 pm )
                                                                                            OP.No.957 of 2019



                                                                 ORDER

This petition has been filed under Section 34 of the Arbitration and

Conciliation Act, 1996 [for brevity referred to as 'Act'] challenging the

award passed by the sole Arbitrator dated 27.02.2018.

2. The respondent/claimant is a Contractor who participated in the

tender called for by the petitioner for undertaking a work of “Provision of

Certain Single Accommodation for 279 Airmen at Tambaram, Chennai”.

The contract was for a total sum of Rs.5,87,34,962.37. The tender

submitted by the respondent was accepted on 14.01.2008 and the work

order was issued on 23.01.2008. The date of commencement of work was

fixed on 28.01.2008 and it was supposed to be completed by 27.09.2009.

However, due to various reasons, the commencement of work was getting

prolonged and the period was extended from time to time. Ultimately, the

contract was cancelled on 05.10.2013.

3. As a result of the above dispute, as agreed in the terms and

conditions of the tender, the dispute was referred to a sole Arbitrator.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )

4. The respondent/claimant made the following claims :

Claim No (1) - Loss due to delay in decision on hard rock Rs.1,66,10,000.00 Claim No (2) - Reimbursement of Addl cost Rs.81,65,000.00 Claim No (3) - Under pricing of DOs Rs.6,62,000.00 Claim No (4) - Loss of profit & establishment Rs.4,63,00,000.00 Claim No (5) - Loss due to interests paid to other Rs.37,00,000.00 establishment Claim No (6) - Loss due to confiscated T&P Rs.28,88,750.00 Claim No (7) - Balance payment in Final bill Rs.47,47,700.00 Claim No (8) - Risk & cost of UOI Rs.Nil Claim No (9) - Loss due to illegal cancellation Rs.65,76,824.00 Claim No (10) - Damage due to mental agony Rs.1,00,00,000.00 Claim No (11) - Interest past, Pendente lite and future To be calculated Claim No (12) - Cost of Arbitration Reference = To be decided during hearing TOTAL Rs.9,97,49,274.00 Say Rs.9,97,49,000

5. The petitioner submitted a statement of defence and denied all the

claims made by the respondent. The petitioner also made a counter claim

for a sum of Rs.38,85,210.21 under the head of “Minus Amount of Final Bill

on Account of Execution of Work at the risk and cost of the Contractor,

Levy of Compensation, Security Deposit for ATT, Roof Treatment etc.,” and

a further sum of Rs.4,00,000.00 under the head of “Miscellaneous

Expenditure Consequent on Cancellation, Arbitration and Legal

Procedures”.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )

6. The sole Arbitrator on considering the pleadings and also the claim

and counter claim made by the respective parties, and also considering the

evidence let in by both sides, allowed Claim Nos.3, 6, 7 and 9 in favour of

the respondent/claimant, and also Claim Nos.11 & 12 which pertain to

interest and costs. The other claims were rejected and the counter claim

made by the petitioner was also rejected. Aggrieved by the award passed

by the sole Arbitrator, the Union of India has approached this Court by

filing a petition under Section 34 of the Act.

7. Heard Mr.G.Ilangovan, learned Senior Panel Counsel appearing for

the petitioner and Mr.T.V.Lakshmanan, learned counsel appearing for the

respondent.

8. Mr.G.Ilangovan, learned Senior Panel Counsel appearing on behalf

of the petitioner confines his arguments to the claims that were awarded in

favour of the respondent viz., Claim 3, 6, 7 and 9, and consequently also

questioned the interest that were awarded as against these claims and the

costs that was imposed by the sole Arbitrator.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )

9. Claim No.3 pertains to 'Under pricing of the Deviation Orders

[DOs] and certain DOs due for payment but not initiated / paid'. This

claim was made by the respondent on the ground that such a deviation order

was necessitated either due to design fault or improper soil investigation

carried out, than what was specified in the contract. In view of the same,

the pricing had to be fixed based on the costs actually incurred by the

claimant. This costs was fixed by the Board of Officers [BOO] at

Rs.4,940.91 per cubic metre and whereas, what was allowed / permitted was

only Rs.3,304.26 per cubic metre.

10. The main ground on which the learned Senior Panel Counsel

appearing for the petitioner questioned the award passed by the sole

Arbitrator under Claim No.3 is that the claimant had accepted the finalised

rate of Rs.3,304.26 per cubic metre on 19.03.2012 and it was signed in the

presence of the witnesses. Therefore, whatever that was accepted by the

claimant alone must be awarded and the original amount that was fixed,

cannot be taken into account for calculating the compensation under this

head.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )

11. In order to appreciate the findings of the learned sole Arbitrator, it

will be relevant to take note of the background facts of this case. As per the

work order, the date of commencement of work was fixed on 28.01.2008

and the date of completion was fixed on 27.09.2009. The sole Arbitrator on

considering the evidence, found that there were various obstructions right

from the commencement of the work. Even the layout of the building was

shifted 5 mtrs. away from the edge of the existing road as against 10 mtrs.,

as per the original site plan. Apart from that, the CI water supply lines that

was running across the entire stretch of the building, required removal and

re-routing. One of the major obstructions encountered by the claimant was

that the excavation of hard rock required chiselling. The BOO has assessed

the rates for excavation of hard rock and recommended Rs.4940.91 per

cubic metre. However, the petitioner/UOI allowed only Rs.3,304.20 per

cubic metre.

12. The petitioner relied upon Amendment No.2 dated 19.03.2012,

where the Chief Engineer had reduced the rate to Rs.3,304.20 per cubic

metre. There is no doubt that the petitioner has also signed this document.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )

13. The sole Arbitrator while dealing with this issue, took into

consideration the fact that, originally under Amendment No.1 dated

02.08.2010, the rate was provisionally fixed at Rs.3,304.20 per cubic meter

and this was subsequently refixed by BOO at Rs.4,940.91 per cubic metre.

The sole Arbitrator who is the Additional Director General (Contracts), is

well-versed in such contracts, came to a conclusion that the BOO had

recommended the rate at Rs.4,940.91 per cubic metre and that the same

cannot be reduced by the Union of India. Apart from that, the respondent

through its letter dated 04.03.2012 had agreed for the provisional rates fixed

by BOO and not the final rates, as the subsequent rate was fixed by BOO, by

its letter dated 14/18 May 2010. Hence, the sole Arbitrator held that the

rates fixed by BOO cannot be unilaterally reduced by the petitioner, without

assigning any reasons. Therefore, the sole Arbitrator has awarded the

compensation by fixing it at the rate of Rs.4,940.91 per cubic metre.

14. The above reasoning given by the sole Arbitrator does not suffer

from any perversity or patent illegality. The sole Arbitrator who has

experience in such contracts, has come to the conclusion that the final rate

https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )

fixed by BOO cannot be reduced by the Chief Engineer. This finding,

arrived by the sole Arbitrator, based on the background facts of the case,

does not warrant interference of this Court.

15. The next issue pertains to Claim No.6 namely “Loss due to

confiscated T &P”. This claim was questioned by the petitioner on the

ground that whatever that was available in the site, was taken away by the

claimant and nothing remained in the site and inspite of the same, the sole

Arbitrator had assumed that, only 50% of the materials were removed from

the site and for the balance 50%, the compensation has been fixed and

awarded in favour of the respondent. It was further contended that under

Clause 54 of the General Conditions of Contract [GCC], the respondent has

the power to confiscate the materials in the event of default in completing

the contract. In the case on hand, the sole Arbitrator on considering the

repeated delays caused in completing the contract work and the extension of

time that was granted by the petitioner, came to a conclusion that time is not

the essence of this contract. However, after the expiry of last extension

which came to an end on 30.04.2012, the contract was cancelled on

05.10.2013, when the contract was not even in subsistence. In fact, the

https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )

claimant was continuing to hold the materials till 05.10.2013.

16. Exhibit-C49, pertains to the materials that were removed from the

site. It is seen that vide Ext.C49, letter dated 06.08.2013, the claimant had

requested the Security Officer, Tambaram, (through AGE B/R(P),

Tambaram) for removal of 850 nos. of Old Cementing Steel Sheets; 300

nos. of Old Spans Steel and 550 nos. of Old Props Steel. However, the

claimant was permitted to remove only 425 nos, 150 nos., and 175 nos. of

the respective materials. The same is apparent from the endorsement that

has been made in Ext.C49.

17. The sole Arbitrator, after considering the fact that there was

absolutely no explanation forthcoming from the petitioner regarding the

remaining materials, has rightly calculated the value of those materials and

awarded a sum of Rs.19,71,250/- to the claimant. This finding cannot be

held to be perverse or patently illegal. In fact, the claimant had sought for

nearly Rs.28,88,750/-. However, the sole Arbitrator took the effort of

making an independent calculation and assessed the claim of Rs.19,71,250/-

This also shows that the sole Arbitrator has assigned proper reasons and

https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )

calculated the correct compensation amount payable to the claimant.

18. The next issue pertains to Claim No.7, which is the “Balance

Payment of Final Bill”. It was contended on the side of the petitioner that

the Government had recovered a sum of Rs.17,00,000/- from the retention

amount of Rs.30,47,700/-, since there was no separate security deposit

available. According to the petitioner, due to non-completion of the work,

the Government had sustained huge loss and towards the same, the recovery

was made. Condition No.50 of GCC authorises the Government to levy

compensation. Therefore, the sole Arbitrator, without appreciating the fact

that the Government had the power of cancellation and levying

compensation, ought not have awarded the claim in favour of the

respondent.

19. The sole Arbitrator had already given sufficient reasons as to why

time is not the essence of the contract and has also taken into consideration

the scope of Section 55 of the Indian Contract Act, in this regard. The sole

Arbitrator also took into consideration the fact that the permission was

granted only upto 30.04.2012, but, the contract was cancelled on

https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )

05.10.2013, almost 1 ½ years after the permission was granted to complete

the work without levy of compensation. On the date when the cancellation

was made, the contract was not in subsistence.

20. Apart from the above, the sole Arbitrator made an independent

assessment / detailed assessment under various heads at Paragraph No.98 of

the award, while arriving at the net total compensation of Rs.27,14,234.53

under this claim. The sole Arbitrator also came to the conclusion that the

petitioner has not proved any loss suffered by them on account of the delay

in completion of work. On this very ground, the counter claim made by the

petitioner was also rejected.

21. The sole Arbitrator has properly appreciated the evidence and

given a factual finding, apart from making a detailed calculation under this

claim. Certainly, the findings of the sole Arbitrator under Claim No.7 does

not suffer from any perverse or patent illegality, warranting interference of

this Court.

22. Finally, this Court deals with Claim No.9 which relates to 'Loss

https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )

due to illegal cancellation'. Under this claim, the sole Arbitrator has

awarded a sum to the tune of Rs.10,16,155/- in favour of the claimant.

23. The main ground that was urged by the learned Senior Panel

Counsel appearing for the petitioner is that the issue concerns TDS deposit

and issuance of Form-16A, or credit in Section 26A or 26S of the Income

Tax Act. The claim was made on the ground that the dues for the year

2008-2009 upto 2011-2012 was uploaded only on 31.07.2013, and due to

this delay, the financial position of the claimant was adversely affected and

he was not in a position to complete the work. The claimant had claimed a

sum of Rs.65,76,824/- under this head and what was awarded by the sole

Arbitrator is Rs.10,16,155/-.

24. In the considered view of this Court, such matters which fall

within the realm of TDS deduction, cannot fall within the scope of

arbitration proceedings before the Tribunal. Useful reference can be made

to the judgment of a Division Bench of this Court in Sree Kamatchi

Amman Constructions Vs The Divisional Railway Manager Works,

Palghat Division reported in 2007 5 CTC 17.

https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )

25. Even otherwise, there is absolutely no discussion or reference to

any evidence to justify as to how the sole Arbitrator came to a conclusion

that a sum of Rs.10,16,155/- can be awarded in favour of the claimant.

Thus, the sum awarded is not supported by any evidence and has been

awarded on a mere surmise and it certainly suffers from patent illegality

under Section 34(2A) of the Act and it warrants interference of this Court.

26.The upshot of the above discussion, this Court upholds the

compensation given under Claim Nos.3, 6 and 7, and sets aside

compensation awarded under Claim No.9.

27. The next question to be dealt with is as to whether the award of

the sole Arbitrator can be modified by interfering only with one of the

claims awarded in favour of the claimant. In the light of the judgment of the

Apex Court in Gayatri Balasamy Vs ISG Nova Soft Technologies Limited

reported in (2025) 7 SCC 1, such modification is permissible, if the invalid

portion can be severed from the valid portion of the award. Certainly, the

compensation awarded for Claim No.9 can be severed from the other claims

https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )

awarded in favour of the claimant which has been upheld. Consequently,

relying upon the judgment of the Apex Court in Gayatri Balasamy referred

supra, the award can be modified.

28. Insofar as the award of interest and costs is concerned, this Court

finds that the sole Arbitrator has only awarded simple interest at the rate of

12% per annum and with regard to costs, the sole Arbitrator has only fixed

the reasonable cost of Rs.45,000/- incurred by the claimants towards making

reference, administrative costs etc.,

29. In the result, this petition is partly allowed in the above terms with

costs of Rs.1,00,000/- payable by the petitioner to the respondent.

17.11.2025

Index : Yes / No Speaking order / Non-speaking order Neutral Citation: Yes / No ds

https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )

N.ANAND VENKATESH,J.

ds

17.11.2025

https://www.mhc.tn.gov.in/judis ( Uploaded on: 19/11/2025 06:44:16 pm )

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter