Tuesday, 19, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Saravana Global Energy Limited vs Tamil Nadu Transmission Corporation ...
2024 Latest Caselaw 18638 Mad

Citation : 2024 Latest Caselaw 18638 Mad
Judgement Date : 23 September, 2024

Madras High Court

M/S. Saravana Global Energy Limited vs Tamil Nadu Transmission Corporation ... on 23 September, 2024

                                  IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                           RESERVED ON       : 22.12.2023

                                         PRONOUNCED ON :        23.09.2024

                                                     CORAM:

                                    THE HON`BLE MR.JUSTICE A.A.NAKKIRAN

                                               C.S. No. 810 of 2012



                     M/s. Saravana Global Energy Limited
                     Rep. by vice president and company secretary,
                     No.15, New Giri Road, T.Nagar,
                     Chennai-600 017.                                               ....Plaintiff

                                                        Vs

                     Tamil Nadu Transmission Corporation Limited,
                      (TANTRANSCO)
                     Chief Engineer/Transmission,
                     having office at 5th Floor, TANTRANSCO HQ,
                     144, Anna Salai, Chennai-600 002.                            ....Defendant

                     (As per amendment order dated 12.09.2023 in A.No.4720 of 2023)



                     Prayer: Civil Suit filed under Order IV Rule 1 of Original Side Rules read

                     with Order VII Rule 1 CPC praying to pass a Judgment and decree:




                     1/31


https://www.mhc.tn.gov.in/judis
                                  (i) For directing the defendant to pay sum of Rs.1,38,35,732/- along

                     with the interest at 12% per annum from 12.09.2012 till the date of

                     realization.

                                  (ii) For the cost of the suit and,

                                  (iii) To pass such further or other orders.


                                  For Plaintiff                        : Mr. S.R. Raghunathan

                                  For Defendant                        : Ms. M. Sneha
                                                              *****

                                                       JUDGMENT

This Civil Suit is filed for the relief as stated in the prayer.

2. The case of the Plaintiff, as set out, in the plaint is as

follows:-

(a) The plaintiff is a manufacturer of electrical insulators and a

small scale industry providing gainful employment to scores of families.

The defendant had invited tenders and the plaintiff had participated in the

tender and was declared as the successful bidder. The price agreed was as

under:

https://www.mhc.tn.gov.in/judis i. 110 KV Solid core Insulators: Rs.6049.95 per unit [PO NO. 1651].

Though as per the tender the quantity was indicated as 2176 the Purchase

order No. 1651 dated 05/03/2007 was placed for 2720 numbers/ units for a

total value of Rs. 1,64,55,864/- (Rupees One Crore Sixty Foupppr Lakhs

Fifty Five Thousand Eight Hundred Sixty Four Only). The price was

inclusive of all taxes, cess and freight.

ii. 230 KV Solid core Insulators: Rs.15572.68 per unit[PO NO. 1724].

Under Purchase order No.1724, dated 30/08/2007, 4104 units were required

to be supplied for a total value of Rs.6,39,10,278.72 (Rupees Six Crore

Thirty Nine Lakhs Ten Thousand Two Hundred Seventy Eight and Paise

Seventy Two Only]. The price was inclusive of all taxes, cess and freight.

iii. 110 KV Solid core Insulators: Rs. 7270.21 Per unit. [PO NO.

1725].

Under Purchase order No.1725 dated 29/08/2007, 5721 units were required

to be supplied for a total value of Rs.4,15,92,871.41 [Rupees Four Crore

Fifteen Lakhs Ninety Two Thousand Eight Hundred Seventy One and Paise

Forty One Only). The price was inclusive of all taxes, cess and freight.

https://www.mhc.tn.gov.in/judis

b). The terms and conditions were enumerated in the Annexure to the

Purchase order, and hence not a contract arising out of any commercial

bargain. The goods were required to be supplied to the various stores of

TNEB running through the State of Tamilnadu. The goods were mostly

required as a stock.

c. The Plaintiff has sold and delivered the goods to various stores of

TNEB and the defendant have without any quarrel or repudiation received

the goods. The petitioner has raised periodical invoice for the supplies.

d. As per the terms and conditions, the defendant had agreed to make

payment of 90% of the "all inclusive price" within a reasonable time after

receipt of material, which time as per the prevalent practice of TNEB being

30 days. In breach of this condition/practice, payments have been made with

delay. The petitioner is entitled to interest for such delayed payment as

under:

                     i. P.O. No. 1651           - Rs. 3,51,802.00
                     ii. P.O.NO. 1724           -Rs.37,70,004.00
                     iii. P.O.No. 1725          -Rs.23,68,098.00
                                                ------------------------
                              Total             -Rs.64,89,905.00
                                                ------------------------







https://www.mhc.tn.gov.in/judis

e. After completion of supply of the goods, the plaintiff had

approached the defendant for balance payment due under the invoice raised

by our client. To the shock and surprise of plaintiff, the defendant had sent

letters dated 26/05/2009, 25/06/2009 and 06/06/2009 informing the plaintiff

that a sum of Rs.2,19,673.65, Rs. 43,18,226.06 and Rs. 19,67,790.95 in

respect of P.O.Nos 1651, 1724 and 1725 respectively were recovered

towards Liquidated damages for delayed supply. Further the defendant had

also informed that a sum of Rs.3635/- and Rs.8523.80 was being recovered

towards Liquidated damages towards non supply of 5 & 3 nos, of insulators

under P.O.No. 1725 and 1724 respectively. Though the defendant had

agreed to release the balance payment to the plaintiff, however, they failed

to even make payment of this. The balance payment including the amount

withheld as Liquidated Damages was Rs.73,45,827/- (Rupees Seventy Three

Lakhs Forty Five Thousand Eight Hundred Twenty Seven Only.)

f. Since the plaintiff's activities were affected due to severe flood,

heavy rain, labour problem and frequent power cuts by Tamil Nadu

Electricity Board, some deliveries were delayed. The reasons were force

majeure events and not attributable to the plaintiff. No proof whatsoever, has

https://www.mhc.tn.gov.in/judis been produced by the defendant establishing any loss suffered by the

defendant. The liquidated damage clause even if applicable to the transaction

in question is subject to the limitation stipulated under Section 73 and 74 of

the Contract Act. The defendant, as a matter of right, is not entitled to deduct

the entire amount stipulated as liquidated damages. Notwithstanding the

above, the said clause is only in the nature of penalty.

g).The defendant vide its letter dated 04/03/2010, in complete

disregard to the provisions of Contract Act and the circumstances refused to

refund the amount withheld. The said letter dated 04/03/2010 is in violation

of the Contract Act. Hence, the plaintiff caused a lawyer's notice to be issued

on the defendant on 17/12/2011 and the said notice was returned by the

defendant. Subsequently the defendant has made certain part payments and

the last of the payment was made on 5th January 2011. The defendant is still

liable to pay a sum of Rs. 1,38,35,732/-[Rupees One Crore Thirty Eight

Lakhs Thirty Five Thousand Seven Hundred and Thirty Two only). Hence,

this suit is filed seeking to direct the defendant to pay the aforesaid amount

along with the interest at 12% per annum from 12.09.2012 till the date of

realization.

https://www.mhc.tn.gov.in/judis

2. The case of the Defendant, in a nutshell, as set out in the

written statement, is as follows:-

a. The purchase order issued to the firm are containing all the

commercial and technical terms, GTP Annexure to purchase order etc,

including payment and delivery clause which is a contract and mutually

agreed by the Purchaser TNEB and the supplier M/s.Saravana insulators,

and same are bound in all respect of the Purchase order (PO) issued.

b.The insulators ordered against the above purchase orders are to

be supplied to various stores of TNEB as per delivery schedule and dispatch

instructions given then and there. These insulators are very essential and

required to execute the substation erection works and commissioning of the

same to maintain more and reliable power supply to consumers. It is not

correct to state that, as the terms & conditions were enumerated in the

annexure to the purchase order and hence they are not contract arising out of

a commercial bargain. In fact, the purchase order annexure is also part of the

contract and binding on both parties.

c. The plaintiff firm have delivered the quantum of insulators as per

the dispatch instructions issued to them but beyond the due date of delivery

https://www.mhc.tn.gov.in/judis fixed under clause 10 (a) of respective purchase orders. However the same

has been accepted subject to the condition that, 90% payment only will be

released initially without prejudice to levy of Liquidated Damages (LD) as

per PO clause 8.03 (i) (b) which reads as below:

For the equipments/materials delivered beyond the contractual delivery period

i) 90% of the all inclusive price (Including Central Sales

Tax/TNVAT) of the materials of each consignment will be paid within a

reasonable time after receipt of materials in good condition at Stores and

submission of bills with required documents.

ii) Balance 10% payment will be paid within a reasonable time after

completion of the execution of the contract and after closure of the Purchase

Order finalizing the amount of LD to be levied.

In case of delay in supply, the materials will be accepted subject to the

following conditions.

a. There should be no declining trend in prices.

b. Payment will be released as per the recent purchase order rates or lowest

rates obtained during the recent tenders opened subject to levy of liquidated

damage for belated supplies.

https://www.mhc.tn.gov.in/judis c. Board reserves the right to accept or reject the delayed supplies without

assigning any reason therefore and take action as per the other terms and

conditions of this specification.

From the above payment clause, it may seen that, no where the specific date

/ period for making payment has been mentioned. Also the above PO

contract payment clause including periodical delivery schedule has been

accepted by Mr. Vimal sharma, DGM-Marketing on behalf of the plaintiff

firm during perusal of the said draft purchase orders, based on which

detailed PO's placed on them. Also it is submitted that, the Board had not

included payment of interest against delayed payments in the contract. The

supplier is not eligible to entitle interest on delayed payment and claiming

the interest is breach of the contract agreed into by the plaintiff firm. It is not

correct to state that, a prevalent practice of TNEB is to pay the purchase

price within 30 days as stated in the plaintiff. It has been stated in the

purchase order and accepted by the plaintiff that, within a reasonable time

payments for the purchased materials would be disbursed. The calculations

made by the plaintiff for payment of interest in the plaint are not payable to

the plaintiff as the purchase orders do not envisage payment of interest.

https://www.mhc.tn.gov.in/judis d. The plaintiff firm have, admittedly completed their supply against

the purchase order placed on them with delay in delivery. The respective

purchase orders were closed and the firm has been informed about

Liquidated Damages to be recovered as per PO clause 13.01 from the

retention 10% amount available with the Board. The LD and other

recoveries are made as per agreed and accepted terms of the PO by plaintiff

firm. Further it is submitted that, the firm has submitted 10% bill towards

balance of payment based on PO closer order issued by TANTRANSO,

hence the same has been paid to them after making recoveries as per PO

closure order. No bill is pending to be paid against the above PO's. It is not

correct to state that, the defendant has not made payment of the balance to

the plaintiff. It is also not correct to state that, the balance payment including

the LD comes to Rs.73,45, 827/-.

e. Even though, no actual proof or loss may not have been given to the

plaintiff, however, the projects were delayed due to the lack of supply of

materials in this stipulated period. The provisions of the Contract Act quoted

by the plaintiff namely Section 73&74 of the Contract Act squarely applies

to the plaint's failure to supply materials in time and the defendant slapping

https://www.mhc.tn.gov.in/judis of LD on the plaintiff's delayed supply is quite legal. The delivery schedule

of the said PO's are as below:

POTR No. 1651/ dated 5.03.2007.

The delivery schedule of the 110 KV solid core insulators ordered in this

Purchase Order shall be commenced before the end of 2nd month and

completed within 5 months from the date of receipt of order. The materials

were delivered from 28.04.07 to 16.10.07 with an overall delay of one to 6

weeks.

POTR No. 1724/ dated 29.08.2007: The delivery schedule of the 230KV

solid core insulators ordered in this Purchase Order shall be commenced and

completed from the date of receipt of order. The firm had supplied 4101Nos.

insulators out of 4104Nos. from 30.10.07 to 11.7.08 with over all delay of 1

to 23 weeks.

POTR No. 1725/dated.29.08.2007

The delivery schedule of the 110 KV solid core insulators ordered in this

Purchase Order shall be commenced and completed from the date of receipt

of order. The firm had supplied 5717Nos. insulators out of 5721Nos. from

12.11.07 to 16.4.08 with over all delay of 3 to 16 weeks. In respect of POTR

https://www.mhc.tn.gov.in/judis No. 1651/ dated 5.03.2007 it may be noted that, the firm have completed the

entire supply with last date of supply received on 16.10.2007. During the

above period, the plaintiff have claimed that their activities were affected

due to severe flood, heavy rain, labour problem, and frequent power cut due

to cyclone. Where as the evidence given by the firm corresponds to

November 2007 which clearly shows that the firm had furnished false

statement to this Honb'le Court and produced evidences to get waiver of LD

which is not valid one. Hence their request for waiver of LD was not

accepted. The insulator quantities delivered by the plaintiff firm are almost

equal and constant in all the time and no where reduced drastically in the

period in question i.e. November 2007. Hence, it was concluded that the

firm's activities were not affected their factory premises due to flood, heavy

rain and power cuts though it has affected in Cuddalore District and the

firm's statement cannot be relied upon and therefore their request for waiver

of LD imposed on them under Force Majeure is not acceptable.

f.PO clause 13.07 reads as below. "The purchaser reserves the right to

cancel the order if the supply is not made as per the delivery schedule

specified in the Purchase Order, notwithstanding its right to claim LD for the

https://www.mhc.tn.gov.in/judis belated supplies and quantities outstanding to be supplied on the date of

cancellation".

But the Board has not cancelled the said PO's as per the above clause due to

delay in delivery schedule, the insulators were accepted subject to levy of

LD. During the financial year 2007-08 the following named 13 Nos. 230 KV

Substation and 46 Nos. 110 KV substation erection and commissioning

works under new Substation category has been programmed with Rs

54,699.99 lakhs fund allocation. The insulators ordered in the purchase

orders were very essentially required to fix bus bars and AB switches which

are all critical materials of the Substations. Due to delay in delivery of those

insulators by the plaintiff firm 3 Nos. 230 KV Substations and 12 Nos. 110

KV substations (marked) commissioning works were suffered and executed

with delay by 3 to 5 months which affects power distribution to consumers.

g. The plaintiff has stated that, there were flash floods and water

logging in plaintiff factory during the last quarter of 2007 and 2008, and that

there had been strike very frequently by the transporters and as a result of

said position plaintiff have stated that Force Majeure conditions has

happened which affected the supply schedule. The Plaintiff having accepted

https://www.mhc.tn.gov.in/judis the purchase orders cannot turn its eyes blind on the purchase order

conditions particularly clause 14.0 of the said POs which deal with Force

majeure, which provides that, on the happening of any event mentioned in

the said clause, notice of the happening of any such eventuality is to be

given by the supplier to the Board within 15 days from the date of

occurrence thereof. However, for the reasons best known to plaintiff, he has

not sent any such notice to the Board within stipulated time specified in the

said clause. Therefore, the TNEB is not in a position to admit the

happenings alleged to have been occurred under Force Majeure clause for

the reason that no notice has been received by the Board within the time

specified in the said clause as per contract conditions. Therefore the reasons

stated by plaintiff for the delay in supply of the materials is not acceptable as

per contract conditions. Plaintiff's further contention that the Accepting this

plaintiff claimed bill for the balance payment of Rs.52,94,165.00 and the

same was paid vide cheque No. 813762 & 813798 dt 30.12.2010. Without

any request for waiver of LD and also the defendant Board have no due to be

paid to the plaintiff firm as on date. It is not correct to state that, the

defendant is liable to still to pay a sum of Rs 1,38,35,732/-.

https://www.mhc.tn.gov.in/judis h. In respect of POTR 1651/ 5.3.07, the firm delivered entire quantity

with overall delay of 1to 6 weeks from 28.4.07 to 16.10.07, from which it is

to be noted that, the supply had been completed before the alleged flood and

rain in the region happened in November 2007, so Force Majeure will not

apply. In any case, the plaintiff is not entitled seek relief under Force

Majeure in view of the position. If the manufacturing activities were affected

as stated by the firm, then there must be drastic reduction in production

during November 2007, where as it is to be noted that, the pattern of

delivery of materials were uniform throughout the delivery period in respect

of all PO's. As per PO clause 13.07, the Board has not cancelled the said

PO's because of delay in delivery schedule and the insulators were accepted

subject to levy of LD and the same was accepted by the firm as the LD was

levied as per PO terms & conditions only. As there is a delay, 90% payment

only will be released initially without prejudice to levy of LD as per clause

13.0 of the purchase order and also the acceptance of material does not

absolve the firm from fulfilling their contractual obligations of the PO.

i. With regard to plaintiff further contention that, plaintiff had made a

https://www.mhc.tn.gov.in/judis written request for extension of delivery period up to 31.3.08 without

imposition of LD were received by TNEB without prejudice, it was

informed that the materials were accepted with delay, but subject to the

condition that the 90% payment only will be released initially without

prejudice to levy of liquidated damages as per PO clause 13.0 of the PO's

and the same had been communicated to plaintiff in the subsequent dispatch

instructions issued from this office in respect of the subject PO's. Despite

the plaintiff have requested the Board to sympathetically consider its case

for waiver of LD, by letter dated 14.12.09, it is not feasible of compliance

as per the respective PO conditions.

j. As per the Force Majeure clause, notice of the happenings such as

flash flood, devastations, flooding of factory premises, non reporting of

workers for work, frequent power failures etc, is to be given by the supplier

to the Board within 15 days from the date of occurrence thereof. In absence

of the above, their request for waiver of LD under this clause beyond the

period is not acceptable and from the supply pattern it appears there is no

substantial reduction in quantity supplied during November 2007 and

subsequently in all the above 3 PO's. Hence Plaintiff claim for waiver of LD

https://www.mhc.tn.gov.in/judis was not acceptable. Further, the suit is hopelessly barred by limitation in as

much as the order of recovery relating to the respective purchase orders were

passed as early as on 26.06.2009, 06.06.2009, and 25.06.2009 and were

allowed to become final. As such, the suit is liable to be dismissed as time

barred. Hence, the defendant prays that this Hon'ble Court may please be

pleased to dismiss the suit with cost and thus render justice.

4.On the pleadings of the parties, the following issues were framed in

both suits:-

1.Whether the Plaintiff is entitled to suit claim of Rs. 1,38,35,732 along with interest 12%.

2.Whether the defendant is entitled to the liquidated damages, if so, to what extent?

3.Whether the stipulated liquidated damages in the purchase order is in the nature of penalty?

4.Whether liquidated damages is payable during Force Majeure condition?

5.Whether the suit is barred by limitation?

6.Whether the Defendant is correct in accepting the extension of delivery period letter subject to the condition of 90% payment and without prejudice to levy liquidated damages?

7. To what other relief the plaintiff is entitled for?

5. To substantiate the respective contentions, P.W.1 was examined

https://www.mhc.tn.gov.in/judis and Ex.P1 to Ex.P37 were marked on the side of the plaintiffs. D.W.1 was

examined and Ex.D1 to Ex.D12 were marked on the side of the defendants.

6.Heard both sides and perused the material available on records.

7. The learned counsel for the plaintiff submits that the plaintiff

completed supply of the insulators to the various stores of the defendant and

the defendant had also without any quarrel received the goods. The plaintiff

raised periodical bills but the defendant did not make payment on time as

per the practise and it was delayed beyond 30 days. The plaintiff is entitled

for interest for the delayed payment. After supplying the material, the

plaintiff approached the defendant for the balance payment, but the

defendant had sent letters dated 26.05.2009, 25.06.2009 and 06.06.2009

informing the plaintiff that a sum of Rs.2,19,673.65/-, Rs.43,18,226.06 and

Rs.19,67,790.95/- in respect of the three purchase orders were recovered

towards Liquidated Damages for delayed supply. A sum of Rs.3635/- and

Rs.8523.80/- recovered towards non-supply of 5 & 3 nos of insulators under

PO 1725 & 1724 respectively. Hence, a sum of Rs.73,45,827/- which

https://www.mhc.tn.gov.in/judis includes the balance payment and the Liquidated damages is to be paid to

the plaintiff.

8. The learned counsel for the plaintiff further submits that the

reasons for the delayed supply is due to unforeseen floods, labour problem

and frequent power cuts by TNEB. The reasons were force majeure events

and not attributable to the plaintiff. Hence, the plaintiff filed WP 26709 of

2009 and the same was disposed on 22.12.2009 by directing the defendant to

consider the plaintiff's representation. Subsequent to the order of this Court,

the defendant by letter dated 04.03.2010 refused to refund the withheld

amount. Hence, the plaintiff issued a legal notice dated 17.12.2011 and the

defendant thereafter made part payment. However, the defendant is still

liable to pay a sum of Rs.1,38,35,732/-.

9. The learned counsel for the plaintiff further submits that the

plaintiff was awarded three purchase orders in the year 2007 where supply

has to be completed within a period of 2 years. As per the terms of the

purchase order in clause 8.03(ii), the payment of 90% of the "all inclusive

https://www.mhc.tn.gov.in/judis price" shall be made within a reasonable time after the receipt of material

which is relevantly 30 days as per the prevalent practice of the Defendant.

The Purchase orders were closed (Ex.P.15 to 17) and the balance amount

outstanding stands to the tune of Rs. 73,45,827/- as evident from Ex.P.36 to

be received from the defendant. Relying upon the Judgments of the cases of

in “Union of India V. Raman Iron Foundry” reported in (1974) 2 SCC 231

and “Hardware (India) Co. V. Firm shamlal and Bros.” reported in AIR

1954 Bom 423, he has submitted that the alleged liquidated damages

adjusted by the Defendant cannot be sustained as the said claim is not a debt

and the appropriate procedure to recover the alleged damage is by way of

suing the plaintiff for damages. While so, the levying of liquidated damages

by the Defendant is arbitrary and illegal and void.

10. It has been further submitted by the learned counsel for the

plaintiff that the Defendant had been paying the Plaintiff for the supplies

made belatedly and it is evident from the Ex.P.17 that the last such payment

received from the Defendant was on 05.01.2011. As per the Limitation Act,

3 years is the limitation stipulated. In the present case the last payment was

https://www.mhc.tn.gov.in/judis received on 05.02.2011 and the suit has been filed on 20.11.2012. Even

assuming the date stated by the DW1 in her cross examination in Q16 i.e.,

30.12.2010 is taken for the purpose of calculation of the limitation, the same

being well within the 3 years stipulated under the Act, the present suit is not

barred by limitation. Hence, he seeks the relief as prayed for.

11. The learned counsel for the defendant submits that even the

plaintiff had agreed to all the terms and conditions of the contract, the

plaintiff had supplied the insulators as per the dispatch schedule but beyond

the date of delivery which is fixed in clause 10(a) of each of the contract.

Though the supply was delayed, the same was accepted by the defendant

subject to the condition that only 90% payment will be released initially and

without prejudice to the levy of liquidated damages as per P.O clause

8.03(i)(b). The said levy of LD was accepted by the firm and supplied

insulators even beyond the stipulated date. The time for payment for each

bill had not been stated in the PO and there is no clause for payment of

interest on delayed payment, since there is no time stipulated for the

payment of the invoice.

12. It has been further submitted by the learned counsel for the

https://www.mhc.tn.gov.in/judis defendant that the force majeure clause was never invoked by the plaintiff

during the period of occurrence. It is only an after thought. The pattern of

supply of insulators with respect to the three purchase orders all long the

entire period will show that the sudden floods as alleged by the plaintiff

during November 2007 had not even had the slightest effect on the plaintiff.

The supply of materials all along had been the same and there had not been a

sudden dip on the supply of materials. The notices necessary for invoking

the force majeure clause were never sent within a 15 days to the defendant

and the said plea is taken only after the defendant had closed the purchase

order and invoked liquidated damages. 90% of the payment has been made

and the balance is adjusted towards liquidated damages towards delayed

supply and for non supply.

13. The learned counsel for the defendant submits that it is an

admitted fact by the plaintiff in para c (g) of the plaint that, the defendant

had sent letters dated 26.05.2009, 25.06.2009 and 6.6.2009 informing the

plaintiff that a sum of Rs.2,19,673.65/-, Rs.43,18,226.06/- and Rs.

19,67,790.95 in respect of P.O. Nos: 1651, 1724 & 1725 were recovered

https://www.mhc.tn.gov.in/judis towards Liquidated damages and for delayed supply. The denial of

liquidated damages was on the year 2009, the present suit claiming

liquidated damages is filed in the year 2012. When the said suit is filed for

released of withheld amount towards liquidated damages, the denial is of the

year 2009. The cause of action arose on the date of denial and therefore the

present suit ought to have been filed within three years from the date of

denial and the suit being filed beyond the three years period is barred by

limitation. Hence, he seeks to dismiss the suit.

14. Having considered the facts and circumstances of the case

and submissions made by the learned counsel for both parties, it is admitted

fact is that there is a delay in supply of insulators with respect to all purchase

orders. The reason for the same alleged by the Plaintiff is force majeure, due

to heavy floods in the month of November 2007. However, no such notice

was issued by the plaintiff within a period of 15 days from the date of

occurrence and the defence of force majeure clause was first taken only on

11.08.2009 after three months of closure of purchase order. The so called

alleged floods in November 2007 had no role to play in their delayed supply.

Further, the first purchase order ought to have been completed even prior to

https://www.mhc.tn.gov.in/judis the floods, with respect to the other two purchase orders, even before the

floods there was a delayed supply and the said pattern continued during the

alleged floods and even after the floods.

15. In so far as the claim of the plaintiff on the interest for the delayed

payment, Article 19 of the limitation Act, speaks as follows:

19.Effect of payment on account of debt or of interest on legacy: Where payment on account of a debt or of interest on legacy is made before the expiration of the prescribed period by the person liable to pay the debt or legacy or by his agent duly authorised in this behalf, a fresh period of limitation shall be computed from the time when the payment was made.

Provided that, save in the case of payment of interest made before the 1st day of January, 19*28, an acknowledgment of the payment appears in the handwriting of, or in a writing signed by, the person making the payment.

Explanation. - For the purpose of this Section,-

a). Where mortgaged land is in the possession of the mortgagee, the receipt of the rent or produce of such land shall be deemed to be a payment;

b)”debt” does not include money payable under a decree or order of a Court.

Hence, to attract the operations of this section, two conditions

are essential: first, payment must be made within the prescribed period of

limitation and secondly, by some form of writing either in the handwriting

https://www.mhc.tn.gov.in/judis of payer himself it must be acknowledged or signed by him. It is the

payment which really extends the period of limitation: but the payment has

got to be proved in a particular way and a written or signed acknowledgment

is the only proof of payment and oral testimony is excluded unless there is

acknowledgment in the required form as per the Judgment in the case of

“Sant Lal Mahton v. Kamla Prasad” reported in A.I.R. 1951 S.C. 477. In

view of the above, the plaintiff is not entitled to interest on the delayed

payment.

16. As per the Section 14 of the Limitation Act enumerates, for

the price of goods sold and delivered, where no fixed period of credit is

agreed upon, the suit has to be filed within a period of 3 years from the date

of delivery of the goods. Against the placement of the three purchase orders,

the delivery has been completed in the month of June, 2009 and the

defendant has sent Ex.P18 dated 26.05.2009, Ex.P19 dated 06.06.2009, and

Ex.P20 dated 25.06.2009 for closing the three purchase order and levying of

Liquidated damages. If the plaintiff has aggrieved by levying the liquidation

damages, he has to come forward to file the suit within a period of three

https://www.mhc.tn.gov.in/judis years. However, the suit has been filed as against the liquidation damages in

the month of November 2012 which is beyond the prescribed limitation

period, according to the Limitation Act. Hence, the suit filed by the plaintiff

is barred by limitation and accordingly, the suit is liable to be dismissed.

Thus, the Issue No.5 is answered against the plaintiff and in favour of the

defendant. Further, other issues involved in this case does not arise since the

issue No.5 is against the plaintiff.

17. In the result, the suit is dismissed. No costs.

23.09.2024

Index:Yes/No Web:Yes/No Speaking/Non Speaking Lbm

Witnesses examined on the side of the plaintiff and defendant:

Marketing Manager - MR. T.R. Ramachandran (PW-1)

https://www.mhc.tn.gov.in/judis Assistant Executive Engineer (A.E.E) – Mrs. K.Ammu (DW-1)

Exhibits produced on the side of the plaintiff:

                         S.No           Exhibits                  Description of documents
                            1.           Ex P1     Authorization Letter
                            2.           Ex P2     Tender - Specification No. 1366 dated 20.09.2006
                            3.           Ex P3     Tender - Specification No. 1407 dated 04.04.2007
                            4.           Ex P4     Tender - Specification No. 1408 dated 05.04.2007
                            5.           Ex P5     Purchase Order No. 1651 dated 05.03.2007
                            6.           Ex P6     Purchase Order No. 1725 dated 29.08.2007
                            7.           Ex P7     Purchase Order No. 1724 dated 30.08.2007
                            8.           Ex P8     English Version of Letter from President, Pethanayakkam
                                                   Kuppam Panchayat dated 25.11.2007
                            9.           Ex P9     Paper Publication - The Hindu dated 24.12.2007
                           10            Ex P10    Lingan's Weblog on flood affected area in Cuddalore
                                                   District - Tamilnadu dated 27.12.2007
                           11.           Ex P11    English Version of Letter from Village Administrative
                                                   Officer, Pethanayakkam Kuppam Panchayat dated
                                                   05.01.2008
                           12.           Ex P12    Letter Requesting for extension of delivery period without

imposition of Liquidated Damages dated 25.02.2008

13. Ex P13 Online Publication in the Indian news portal on Cyclone hits Tamilnadu dated 27.11.2008

14. Ex P14 Publication Flash Floods Relief Efforts (Nov 2008 & Dec 2007)

15. Ex P15 Statement of Account - POTR 1651

16. Ex P16 Statement of Account - POTR 1724

17. Ex P17 Statement of Account - POTR 1725

18. Ex P18 Letter Closure of Purchase Order and levy of liquidated Damages for specification No. 1366 dated 26.05.2009

19. Ex P19 Letter Closure of Purchase Order and levy of liquidated

https://www.mhc.tn.gov.in/judis

17. Ex P17 Statement of Account - POTR 1725 Damages for specification No. 1407 dated 06.06.2009

20. Ex P20 Letter Closure of Purchase Order and levy of liquidated Damages for specification No. 1408 dated 25.06.2009

21. Ex P21 Reply Letter- Request for waiver of liquidated Damage to TNEB with enclosures dated 11.08.2009

22. Ex P22 Request to waiver of liquidated damage to TNEB with Ref. to letter dated 11.08.2009 with enclosure dated 03.09.2009

23. Ex P23 TNEB's reply to letters dated 11.08.2009 and 03.09.2009 dated 12.09.2009

24. Ex P24 Letters to TNEB with Ref. to letters dated 11.08.2009 and 03.09.2009 dated16.09.2009

25. Ex P25 Letters to TNEB with Ref. to letters dated 11.08.2009, 03.09.2009 and 16.09.2009 dated 20.10.2009

26. Ex P26 Letter to The Chairman and the Chief Engineer, TNEB, w.r.t Waiver of LD in POTR No. 1651 dated 14.12.2009

27. Ex P27 Letter to The Chairman and the Chief Engineer, TNEB, w.r.t Waiver of LD in POTR No. 1724 dated 14.12.2009

28. Ex P28 Letter to The Chairman and the Chief Engineer, TNEB, w.r.t Waiver of LD in POTR No. 1725 dated 14.12.2009

29. Ex P29 High Court Order in W.P. No. 26709 of 2009 dated 22.12.2009

30. Ex P30 Reply letter by TNEB to rep. dt. 16.09.2009, 20.10.2009 and 14.12.2009 dated 04.03.2010

31. Ex P31 Reply to TNEB w.r.t letter dt. 12.09.2009 and 04.03.2009

- POTR No.1651 dated 17.03.2010

32. Ex P32 Reply to TNEB w.r.t letter dt. 12.09.2009 and 04.03.2009

- POTR No.1724 dated 17.03.2010

33. Ex P33 Reply to TNEB w.r.t letter dt. 12.09.2009 and 04.03.2009

- POTR No. 1725 dated 17.03.2010

34. Ex P34 Reply from TNEB to M/s. Saravana Global w.r.t. rep. dt.

16.09.2009, 20.10.2009 and 14.12.2009 dated 29.03.2010

35. Ex P35 Legal Notice to TNEB dated 02.08.2010

36. Ex P36 Amount Outstanding from TNEB dated 11.09.2012

https://www.mhc.tn.gov.in/judis

35. Ex P35 Legal Notice to TNEB dated 02.08.2010

37. Ex P37 Interest for delayed payments dated 11.09.2012

Exhibits produced on the side of the defendant:

                         S.No     Exhibits                    Description of documents
                            1.     Ex D1      The true copy of the perusal and acceptance of Draft
                                              purchase order-1651/5.3.07 dated 05.03.2007.
                            2.     Ex D2      The true copy of the perusal and acceptance of Draft

purchase order 1724/25.08.2007 dated 25.08.2007.

3. Ex D3 The copy of the perusal and acceptance of Draft purchase order 1725/25.08.07 dated 29.08.2007.

4. Ex D4 The copy of the 90% payment conditional dispatch instruction POTR 1724 dated 01.03.2008.

5. Ex D5 The copy of the 90% payment conditional dispatch instruction POTR 1724 dated 07.07.2008.

6. Ex D6 The copy of the 90% payment conditional dispatch instruction POTR 1725 dated 31.01.2008.

7. Ex D7 The original of the request letter from plaintiff on priority payment dated 19.01.2008.

8. Ex D8 The true copy of the request letter from plaintiff for closure of PO dated 29.10.2007.

9. Ex D9 The true copy of the request letter from plaintiff for closure of PO and delivery extension dated 03.01.2008. 10 Ex D10 The true copy of the request letter from plaintiff for closure of PO dated 10.12.2008.

11. Ex D11 The original of the Transmission T&D programme 2007- 08 dated 23.08.2007.

12. Ex D12 The true copy of the Bill register of PO.No.1651, 1724 & 1725.

https://www.mhc.tn.gov.in/judis 23.09.2024

A.A. NAKKIRAN, J,

Lbm

https://www.mhc.tn.gov.in/judis

23.09.2024

https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter