                                                                     W.P.No.21546 of 2023
                      IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                           DATED : 23.11.2023

                                                CORAM :

                      THE HON'BLE MR.SANJAY V.GANGAPURWALA ,
                                   CHIEF JUSTICE
                                       AND
                 THE HON'BLE MR.JUSTICE D.BHARATHA CHAKRAVARTHY

                                           W.P.No.21546 of 2023

              1. Star Trace Engineering Division
                Rep. by its Propretrix P.Ponnal

              2. Ponnal P.                                        .. Petitioners

                                                   Versus

              1. The Registrar,
                Debts Recovery Tribunal - II,
                Shastri Bhawan Annexe Building VI Floor,
                Haddows Road, Chennai - 600 006.

              2. The Authorized Officer,
                State Bank of India,
                Stressed Assets Management Branch,
                Red Cross Building, Montieth Road,
                Egmore, Chennai - 600 008.

                    3. M.M.M.Thiagarajan
                    4. M.Sivakumar
https://www.mhc.tn.gov.in/judis                                   .. Respondents
              1/27
                                                                                     W.P.No.21546 of 2023


                    Prayer : Writ Petition filed under Article 226 of the Constitution of India

                    seeking a Writ of Certiorarified Mandamus, to call for the records in order,

                    dated 31.05.2023 made in T.S.A.No.35 of 2023 (Old S.A.No.145 of 2022)

                    on the file of the Debts Recovery Tribunal-II, Chennai, the first respondent

                    herein and quash the same and direct the 2nd respondent to return the title

                    deeds by closing the loan account.


                                    For Petitioner      : Mr.S.R.Rajagopal,
                                                          for Mr.M.A.Aruneshe

                                    For Respondents : R1 - Tribunal

                                                        : Mr.Om Prakash, Senior Counsel,
                                                          for Mr.B.Raghavulu Naidu,
                                                          for R2

                                                        : Mr.T.Mohan, Senior Counsel,
                                                          for Mr.S.P.Sudalaiyandi,
                                                          for RR-3 and 4

                                                        ORDER

(Order made by the Hon'ble Mr.Justice D.Bharatha Chakravarthy)

The brief facts leading to the filing of this Writ Petition are that the

writ petitioners are engaged in the business of manufacturing, exporting and

supplying massive assemblage of Industrial Separators and Magnetic https://www.mhc.tn.gov.in/judis

Equipment. For their business purpose, they had availed Cash Credit facility

to a tune of Rs.1,82,24,183/-, Common COVID - 19 Emergency Credit Line

facility to a tune of Rs.10,25,369/- and Guaranteed Emergency Credit Line

to a tune of Rs.36,96,715/-, in all totaling to Rs.2,30,45,715/-. In view of

default in repayment, the account was classified as Non-Performing Asset

(NPA) with effect from 30.09.2021.

2. A notice under Section 13(2) of the Securitisation and

Reconstruction of Financial Assets and Enforcement of Security Interest Act,

2002 (hereinafter referred to as 'SARFAESI Act'), was issued on 08.10.2021

and the notice under Section 13(4) of the SARFAESI Act was issued on

11.01.2022. Thereafter, a sale notice was issued under Rule 8(6) of the

Security Interest (Enforcement) Rules, 2002 on 18.02.2022 fixing auction on

28.03.2022. The auction was to bring for sale the mortgaged property by

fixing a reserve price of Rs.2.58 crores. The respondent Nos.3 and 4, in the

Writ Petition, jointly participated in the bid and were the successful bidders

for a sum of Rs.3,03,00,000/-. Their highest bid was accepted and they were https://www.mhc.tn.gov.in/judis

directed to pay 25% amount on or before 29.03.2022. They were also

advised to pay the balance amount of Rs.2,27,25,000/- within a period of 15

days i.e., on or before 12.04.2022. As per the directive of the second

respondent bank, the respondent Nos.3 and 4 paid the 25% of the amount on

29.03.2022.

3. It is at this stage, the writ petitioners filed S.A.No.145 of 2022 on

the file of the Debts Recovery Tribunal - I, Chennai and on 31.03.2022, the

following interim order was passed :-

" Hence the respondent bank is directed to maintain status quo on condition that the applicant remitting a sum of Rs.1.00 Crore today and on further condition that the applicant remitting a further sum of Rs.85.00 Lakhs on or before 04.04.2022. It is made clear that if any of these conditions are not complied with by the applicant, the respondent is free to proceed further in accordance with law. Applicant to implead auction purchaser as a party to the proceedings. Ld. Counsel for the bank undertakes to file a memo furnishing details of the auction purchaser within a week's time after serving a copy to the applicant."

https://www.mhc.tn.gov.in/judis

4. However, the amounts were not paid exactly as per the conditional

order. The writ petitioners were directed to remit a sum of Rs.1,00,00,000/-

on the same day of the order i.e., on 31.03.2022 and were directed to pay

another sum of Rs.85,00,000/- on or before 04.04.2022. The writ petitioners

paid a sum of Rs.89,00,000/- on the same day of the order i.e., on

31.03.2022 and thus, there was a deficit of Rs.11,00,000/-. On 01.04.2022,

they paid a sum of Rs.15,73,000/-. On 02.04.2022, they paid a sum of

Rs.20,77,500/-. On 05.04.2022, the petitioners made another deposit of

Rs.70,08,000/-. Thus, even though there was one day delay, the petitioners

had even paid the sums over and above the conditional order of the Tribunal

and as a matter of fact, the entire outstanding stood paid as on 05.04.2022. It

is in this background, when the appeal filed by the writ petitioners before the

Tribunal came up for further hearing, the Tribunal recorded the said fact and

passed the following order :-

" ….

                                          The Ld. Counsel for the applicant submits
https://www.mhc.tn.gov.in/judis    that the transactions are not clear to the bank


                                   though the entire amount is paid.         In the

circumstance the bank, to verify and confirm the transactions as regards the submissions made today by 14.07.2022. Let the same be verified and confirmed by the bank by 14.07.2022. Thus IA/821/2022 stands disposed of by cancelling the earlier date 15.09.2022 assigned."

5. Thereafter, the matter was further taken up for hearing on

14.07.2022, 05.09.2022 and 10.02.2023. In all these dates, inspite of memo

filed by the second respondent bank that the condition was not complied in

time, the Debt Recovery Tribunal extended the interim order specifically.

The relevant portion of the order, dated 14.07.2022 reads as follows :-

"…. Put up this matter for counter by the auction purchaser and the Bank which be filed within six weeks. Put up for further proceedings by 05.09.2022. Interim order extended."

6. The relevant portion of the order, dated 05.09.2022 reads as

follows:-

"…. The auction purchaser and the applicants may explore the possibility of settlement and report the same by 07.11.2022. Interim order is https://www.mhc.tn.gov.in/judis extended."

7. The entire order, dated 10.02.2023 reads as follows :-

" Counsel for both sides present. Applicant to carry out amendments in the course of the day and file amended SA. Post this matter on 22.02.2023 for further proceedings. Interim order extended till posting date."

8. But, however, when the matter was further taken up on 22.02.2023

and was adjourned for filing counter, the interim order was not extended.

The said order is extracted hereunder :-

" Counsel for both sides present. Respondent undertakes to file counter by next posting date.

Post this matter on 21.3.2023 for counter of the respondent."

9. Thereafter also, the interim order was not extended in any of the

further orders, dated 21.04.2023 and 18.05.2023. Finally, on 31.05.2023, the

appeal itself was dismissed by the Tribunal. The Tribunal found that the writ

petitioners were not able to point out any infirmity in the sale notice. Even

though the Tribunal pointed out that the bank was conducting the https://www.mhc.tn.gov.in/judis

proceedings in a reckless manner, however, dismissed the Securitisation

Appeal. Nothing was stated about the amount paid by the petitioners and

about the fact that they have paid the entire loan amount and nothing was

outstanding to the bank. It is at this stage, without filing an appeal before

the Appellate Tribunal, the writ petitioners approached this Court by way of

the present Writ Petition on 17.07.2023.

10. After dismissal of the Securitisation Appeal, the respondents

received the certified copy of the final order of the Tribunal on 06.06.2023.

As per the joint affidavit of the auction purchasers furnished to the second

respondent bank, the bank directed them to pay the balance of 75% by its

communication dated 07.06.2023. Upon their request for extension of time,

by letter dated 01.07.2023, time was extended upto 18.07.2023. In the

meanwhile, the fourth respondent withdrew from the consortium and both

the respondent Nos.3 and 4 jointly requested that sale certificate be issued

only in the same of the third respondent. The third respondent paid the

entire sale consideration on 17.07.2023 and the sale certificate was issued to https://www.mhc.tn.gov.in/judis

him and on 18.07.2023, the same was also registered. It is under these

circumstances, counter-affidavits are filed by the second respondent bank as

well as the respondent Nos.3 and 4 / auction purchasers and the matter is

taken up for hearing.

11. Mr.S.R.Rajagopal, learned Senior Counsel appearing on behalf of

the writ petitioners would submit that the contentions raised by the writ

petitioners relating to the impugned order of the Debt Recovery Tribunal are

that (i) the Tribunal did not even advert to the grounds raised by them in the

appeal; (ii) even after finding that the bank has not even produced the

documents relating to the various steps to justify its action, the Debt

Recovery Tribunal still proceeded to dismiss the Securitisation Appeal; and

(iii) inspite of the entire amount being already paid, the Tribunal did not

even advert to the same and on the other hand, held the payment itself as a

ground to reject the contentions on merits. Dehors the above contentions,

the fact remains that the subsequent sale which is proceeded by the second

respondent bank in favour of the respondent Nos.3 and 4, per se, is a nullity. https://www.mhc.tn.gov.in/judis

According to the learned Senior Counsel, Rule 9 of the Security Interest

(Enforcement) Rules, 2002 was amended vide G.S.R.1046 (E), dated

03.11.2016 with effect from 04.11.2016 and as per the amended Rule 9(4) of

the Security Interest (Enforcement) Rules, 2002, the balance of 75% has to

be paid within such extended period as may be agreed upon in writing

between the purchaser and secured creditor, but, in any case, it cannot

exceed three months. In this matter, the interim order of status quo was not

extended beyond 22.02.2023. From the date of that order, the three months

period expired on 21.05.2023. In this case, the auction purchasers have paid

amount only on 17.07.2023 i.e., beyond the period of 90 days. Therefore, as

per Rule 9(5) of the Security Interest (Enforcement) Rules, 2002, the second

respondent bank ought to have forfeited the initial deposit amount and the

property has to be resold. The property has to be resold by issuing a fresh

sale notice and any time before the issue of fresh sale notice, the writ

petitioners have right of redemption and therefore, the writ petitioners,

having been exercised their right of redemption by paying their entire

amount, this Court should set aside the sale certificate, dated 18.07.2023 https://www.mhc.tn.gov.in/judis

issued in favour of the respondent Nos.3 and 4 and direct the second

respondent bank to issue full satisfaction receipt and No Objection

Certificate for cancelling the mortgage.

12. Per contra, Mr.Om Prakash, learned Senior Counsel appearing on

behalf of the second respondent bank would submit that right from the

beginning, the writ petitioners were offering to make payment, but, however,

did not keep up their promise. Even after issue of possession notice under

Section 13(4) of the SARFAESI Act, they did not take any steps. Therefore,

when the sale notice dated 18.02.2022 was issued, as per the amended

Section 13(8) of the SARFAESI Act, the right of redemption was lost and

therefore, the auction which took place on 28.03.2022 was valid. The

respondent Nos.3 and 4 were the highest bidders and have deposited the

initial 25% on 29.03.2022 as directed by the second respondent bank.

Before they could pay the balance amount within a period of 15 days as

directed originally, the writ petitioners approached the Debt Recovery

Tribunal and obtained the order of status quo on 31.03.2022. Even though https://www.mhc.tn.gov.in/judis

the second respondent bank filed a memo of non-compliance, the interim

order was extended by the orders, dated 14.07.2022, 05.09.2022 and

10.02.2023. Even thereafter, in the order, dated 22.02.2023, there was no

express observation that the order of status quo stood vacated or not

extended. In the absence of the same, the bank as well as the respondent

Nos.3 and 4 had to await the final orders to be passed by the Debt Recovery

Tribunal and once the final orders are passed on 31.05.2023, the respondent

Nos.3 and 4 paid the balance amount within a period of three months from

the said date of order on 17.07.2023 and accordingly, the sale certificate is

also issued and is registered on 18.07.2023.

13. In this context, he would rely upon the judgment of the Hon'ble

Supreme Court of India in Varimadugu Obi Reddy Vs. B.Sreenivasulu and

Ors.1, specifically, by relying upon paragraph Nos.41, 42 and 43 of the said

judgment to contend that in the context of the present case, where the

amount was received after the final order in S.A was passed, the same cannot

https://www.mhc.tn.gov.in/judis

(2023) 2 SCC 168

be held to be fatal. By placing strong reliance on the judgment of the

Hon'ble Supreme Court of India in Celir LLP Vs. Bafna Motors (Mumbai)

Pvt. Ltd. and Ors.2, the learned Senior Counsel would submit that once the

borrowers have lost their right of redemption and the sanctity of public

auction being specifically stressed upon by the Hon'ble Supreme Court of

India in paragraph Nos.83 and 88 of the said judgment, the Writ Petition is

bound to fail.

14. Mr.T.Mohan, learned Senior Counsel appearing on behalf of the

respondent Nos.3 and 4 / auction purchasers, would submit that firstly, in

this case, they were ready and willing to deposit their amount whenever the

bank insisted. As a matter of fact, the bank has brought to the notice of the

Debt Recovery Tribunal by filing a memo and thereafter, they were

impleaded in the proceedings before the Debt Recovery Tribunal. The order

of status quo was never refused to be extended expressly. In that view of the

matter, placing reliance on the judgment of a learned Single Judge of this

https://www.mhc.tn.gov.in/judis

2023 SCC OnLine SC 1209

Court in K.Jayaraman Vs. Union of India and Ors. , more specifically on

paragraph No.32, he would submit that when the Court does not take up the

matter on the question of vacating the order and when the said prayer is

closed only on the final day, it cannot be said that there was vacation of

interim order and therefore, the payment made by them is within the

mandatory period of three months and there is no illegality in the sale.

15. He would further contend that in any event, as per the dictum of

the Hon'ble Supreme Court of India in Celir LLP's case (cited supra), in

view of the amended Section 13(8) of the SARFAESI Act, once the sale

notice is issued, the right of redemption is permanently lost. It cannot once

again eclipse or enure to the borrowers. Therefore, in any event, have lost

their right of redemption cannot now plead about the payment of entire loan

outstanding. In any event, the sale has taken place and the sale certificate

has been issued. The petitioners have got every right to challenge the said

measures by way of filing a fresh application under Section 17 of the

https://www.mhc.tn.gov.in/judis

2023 (4) CTC 30

SARFAESI Act before the Debt Recovery Tribunal. In the absence of the

same, in the present proceedings arising out of the challenge to the sale

notice, the same cannot be set aside. He would also rely upon the order

passed by this Court in W.P.No.14301 of 2023 in M/s.Thilak International,

rep. by its Partner D.Joseph Raja Vs. UCO Bank and Ors.

16. We have considered the rival submissions made on either side and

perused the material records of the case. The first point that would arise for

consideration is as to whether there was any interim order by the Debt

Recovery Tribunal after 22.02.2023 ? All the relevant orders are extracted

supra. It can be seen from the order, dated 10.02.2023, the interim order

was specifically extended till the posting date only. When the interim order

is extended specifically till the next date and on the next date i.e., on

22.02.2023, when the matter is taken up and the interim order is not further

extended, then, the same cannot be construed to be extended beyond the

particular date. Therefore, the period of time of 90 days specifically started

running from 22.02.2023. Obviously, the deposit of balance of 75% was not https://www.mhc.tn.gov.in/judis

made within a period of three months. As a matter of fact, this point was

specifically considered by this Court in Sri International, Represented by

its Partner, N. Ramalingam and Another Vs. Central Bank of India and

Ors.4, wherein, it was specifically held that once there was no impediment

by way of a prohibitory order passed by the Court, the time for payment

would start running from thereon. The relevant portion of the said judgment

is extracted as hereunder :-

" 28....The parties cannot be permitted to read or interpret the orders of this Court in their own way, that too in a way so as to render any particular direction in order otiose and redundant. As a matter of fact, if the entire order is read in total, this Court had even taken into account the entire sale consideration to be paid by the auction purchasers while calculating the waiver amount and the condition to be imposed."

17. As a matter of fact, the decision relied upon by the Mr.T.Mohan,

the learned Senior Counsel in K.Jayaraman (Supra) arise in the context of

Writ Petition where limited interim order which was granted upto a date

where the court does not take up the matter for hearing. On the contrary, the https://www.mhc.tn.gov.in/judis

2023 SCC OnLine Mad 2210

hearing procedure is followed by the tribunal and on the next adjourned date,

the matter was taken up for hearing and orders were passed posting the

matter to a further date for the purposes mentioned therein, however, without

extending the interim order.

18. The contention of Mr.Om Prakash, the learned Senior Counsel that

in the instant case, since the matter was pending Court, the ninety days

period need not be strictly adhered to cannot be countenanced. The

language used in Rule 9(4) of the Security Interest (Enforcement) Rules,

2002 is “...in any case not exceeding three months”. When a statute uses a

negative language and commands loud and clear, it cannot be interpreted

that in the context of any factual situation, it can be extended. Useful

reference in this regard, can be made to the Judgment of the Supreme Court

of India in Lachmi Narain Vs. Union of India5 and the relevant portion of

paragraph 68 reads thus :

“68. ….If the provision is couched in prohibitive or negative language, it can rarely be directory, https://www.mhc.tn.gov.in/judis

(1976) 2 SCC 953

the sue of preemptory language in a negative form is per se indivative of the intent that the provision is to be mandatory...”

19. The second contention of Mr.T.Mohan, learned Senior Counsel

appearing on behalf of the respondents 3 and 4 / the auction purchasers, is

that once the sale notice under Section 13(8) of the SARFAESI Act, is issued

and the right of redemption is lost, thereafter, it will never accrue to the

mortgagors. The said contention is absolutely fallacious. Firstly, the title in

respect of the property vests with the mortgagor. It gets divested only upon

a sale. Secondly, the Hon'ble Supreme Court of India in Celir LLP's case

(cited supra) has categorically held that the statutory regime has to be

strictly followed only to avoid the sale being set at naught. It is relevant to

quote paragraph No.82 which reads as follows :-

" 82. Thus, it is necessary to interpret the amended Section 13(8) of the SARFAESI Act in such a manner where a legal sanctity is attached to an auction process and a bright line is drawn where a mischievous borrower is told ‘no more and no further’ and precluded from hastily exercising its right of redemption from nowhere at https://www.mhc.tn.gov.in/judis the very end of the process and thereby set the

entire auction process at naught. If permitted to do so then all auctions under the SARFAESI Act would be meaningless and simply rendered otiose and the very object of Section 13 and the overall scheme of the SARFAESI Act of enabling the banks from recovering its dues in a timely manner without intervention of the courts would be simply defeated."

(emphasis supplied)

20. Therefore, in a case where there is no sale at all, it goes without

saying that once again the matter remains at large at the pre-sale notice stage

and the borrower can very well pay the amount and redeem the property.

Similarly, if auction purchaser does not pay the amount in time, then, Rule

9(5) of the Security Interest (Enforcement) Rules, 2002 comes into play. The

entire Rule 9(4) and 9(5) of the Security Interest (Enforcement) Rules, 2002,

are extracted hereunder for ready reference :-

" 9. Time of sale, Issue of sale certificate and delivery of possession, etc.-

.

.

.

(4) The balance amount of purchase price payable shall be paid by the purchaser to the https://www.mhc.tn.gov.in/judis

authorised officer on or before the fifteenth day of confirmation of sale of the immovable property or such extended period as may be agreed upon in writing between the purchaser and the secured creditor, in any case not exceeding three months. (5) In default of payment within the period mentioned in sub-rule (4), the deposit shall be forfeited to the secured creditor and the property shall be resold and the defaulting purchaser shall forfeit all claim to the property or to any part of the sum for which it may be subsequently sold."

21. Thus, it can be seen that the purchaser has to pay the balance

amount within such period as may be agreed between the purchaser and the

secured creditor and in any event, such period cannot be beyond three

months. Thus, as per Rule 9(5) of the Security Interest (Enforcement) Rules,

2002, in case if there is a default in payment, the sum already deposited shall

be forfeited and the property shall be resold and the defaulting purchaser

shall forfeit all claim to the property or to any part of the sum for which it

may be subsequently sold.

https://www.mhc.tn.gov.in/judis

22. What is contemplated under Rule 9(5) of the Security Interest

(Enforcement) Rules, 2002 is not postponement of sale, but, a resale. A

careful consideration of Section 13(8) of the SARFAESI Act and Rules 8 and

9 of the Security Interest (Enforcement) Rules, 2002, it would be clear that

once again a sale notice has to be issued, in which case, it goes without

saying that from the moment the sale did not fructify and the time ripens for

resale of the property, from that moment till again fresh sale notice is issued,

the mortgagor has the right to redeem the property. At all times when there

is no sale proceedings which are pending, the right can be exercised and it

cannot be used in any manner to frustrate the sale proceedings or to stultify

the sanctity of auction sale. Therefore, we specifically reject the contention

raised on behalf of the auction purchaser that the right of redemption of the

writ petitioners would be permanently lost.

23. Therefore, once the sale does not take place or if the sale is set

aside by the Tribunal or a Court of law on material irregularities, the right of

redeem automatically revives.

https://www.mhc.tn.gov.in/judis Thus, if the writ petitioners succeed in

impugning the present sale, then, by virtue of the payment of the entire

amount, the petitioners can exercise their right of redemption.

24. The question therefore, is whether the sale in favour of the

respondents 3 and 4 has to set aside. In this regard, even though it is

contended by Mr.S.R.Rajagopal, the learned Senior Counsel appearing on

behalf of the writ petitioners that even in the absence of the challenge to the

sale certificate, this Court should exercise its jurisdiction as the case is

crystal clear, we are of the opinion that the present proceedings are filed

impugning the measure of issue of sale notice. The writ petition is filed

challenging the Order of the Debt Recovery Tribunal arising out of a

Securitisation Appeal under Section 17 of the SARFAESI Act challenging the

sale notice. This Court would exercise the jurisdiction under Article 226 of

the Constitution of India in matters arising out of SARFAESI Act only if the

sale has been challenged before the Debt Recovery Tribunal and the party

has exhausted the appeal remedy before the Debt Recovery Appellate

Tribunal. Even in the judgment in Celir LLP's case (cited supra), the https://www.mhc.tn.gov.in/judis

Hon'ble Supreme Court of India had made observations about the exercise of

the extraordinary jurisdiction of the High Court under Article 226 of the

Constitution of India in SARFAESI Act matters, more specifically, in

paragraph Nos.89 to 96. In view thereof, we are of the view that the writ

petitioners have to be relegated to the Debt Recovery Tribunal. However, it

must be seen that the Writ Petition was filed on 17.07.2023, on which date,

the sale certificate was issued and only on 18.07.2023, the same was

registered. Since it is brought to the knowledge of the writ petitioners about

the issue of the sale certificate only by the counter affidavits and since that

technically happened pending the Writ Petition and the Writ Petition being

entertained by this Court and the matter is kept pending till date, the period

from 17.07.2023, till date has to be excluded for the purpose of computation

of limitation for challenging the sale certificate before the Tribunal.

25. In view of our findings as above, we dispose of this Writ Petition

on the following terms :-

https://www.mhc.tn.gov.in/judis

(i) Since the second respondent bank has proceeded to complete the

sale and issue sale certificate, dated 18.07.2023 being registered as

Document No.11119 / 2023, at the office of the Sub-Registrar, Red Hills,

Chennai, the writ petitioners may specifically challenge the same by way of

an appropriate proceedings under Section 17 of the SARFAESI Act before the

Tribunal;

(ii) The period spent in the present Writ Petition from 17.07.2023 till

date shall be excluded for the purpose of computation of limitation for filing

an application under Section 17 of the SARFAESI Act;

(iii) As and when the application is filed the same shall be considered

on merits in the light of the findings above;

(iv) There shall be no order as to costs;

(v) Consequently, W.M.P.Nos.20917 and 20918 of 2023 are closed.

                                                                   (S.V.G., CJ.)             (D.B.C., J.)
https://www.mhc.tn.gov.in/judis                                                    23.11.2023


                    Index        : yes
                    Speaking order
                    Neutral Citation : yes
                    grs

                    To

                    1. The Registrar,
                      Debts Recovery Tribunal - II,
                      Shastri Bhawan Annexe Building VI Floor,
                      Haddows Road, Chennai - 600 006.

                    2. The Authorized Officer,
                      State Bank of India,
                      Stressed Assets Management Branch,
                      Red Cross Building, Montieth Road,
                      Egmore, Chennai - 600 008.




https://www.mhc.tn.gov.in/judis




                                     THE HON'BLE CHIEF JUSTICE
                                                          AND
                                  D.BHARATHA CHAKRAVARTHY, J.

                                                                   grs









https://www.mhc.tn.gov.in/judis






                                        23.11.2023




https://www.mhc.tn.gov.in/judis



 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter