Tuesday, 19, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Orange Bercha Wind Power Pvt. Ltd. vs The State Of Madhya Pradesh
2025 Latest Caselaw 7036 MP

Citation : 2025 Latest Caselaw 7036 MP
Judgement Date : 24 June, 2025

Madhya Pradesh High Court

M/S Orange Bercha Wind Power Pvt. Ltd. vs The State Of Madhya Pradesh on 24 June, 2025

Author: Vivek Rusia
Bench: Vivek Rusia
         NEUTRAL CITATION NO. 2025:MPHC-IND:15182




                                                              1                                 WP-8163-2021
                               IN    THE      HIGH COURT OF MADHYA PRADESH
                                                     AT INDORE
                                                          BEFORE
                                             HON'BLE SHRI JUSTICE VIVEK RUSIA
                                                             &
                                        HON'BLE SHRI JUSTICE BINOD KUMAR DWIVEDI
                                                     ON THE 24 th OF JUNE, 2025
                                                 WRIT PETITION No. 8163 of 2021
                                         M/S ORANGE BERCHA WIND POWER PVT. LTD.
                                                         Versus
                                        THE STATE OF MADHYA PRADESH AND OTHERS
                          Appearance:
                                Shri Manu Maheshwari - Advocate for the petitioner.
                                Shri Bhuwan Gautam - Government Advocate for the respondent/State.

                                                                ORDER

Per: Justice Vivek Rusia

1. The petitioner has filed this present petition challenging the order dated 12.3.2021 passed by the Additional Labour Commissioner and Cess Assessment Authority, Indore appointed under the Building and Other Construction Workers Welfare Cess Act, 1996 (hereinafter referred as "BOCW Act").

2. By the impugned order, the learned authority has calculated the cess amount of Rs.3,20,50,540/- on the basis of the project cost of Rs.3,20,50,54,081/-.

The petitioner has challenged the aforesaid order by way of writ petition inter-alia on the ground that the cost of land, erection and civil work was Rs.51,46,49,156/- and out of which only Rs.14,98,92,408/- were spent for construction work. The petitioner has deposited the 1% Cess Rs.14,64,755/- with the department.

3. The aforesaid contention has been rejected and vide impugned order dated 12.3.2021 the learned Authority has imposed the cess of Rs.3,05,85,788/-, which is 1% of the total project cost Rs.3,20,50,54,081/-.

NEUTRAL CITATION NO. 2025:MPHC-IND:15182

2 WP-8163-2021

4. Similar issue came up for consideration before the Apex Court in the case of Uttar Pradesh Power Transmission Corporation Ltd. and Another Vs. CG Power and Industrial Solutions Limited and Another [judgment dated 12.5.2021 passed in Special Leave Petition (C) No.8630 of 2020], in which the Apex Court has held that the object of enactment of BOCW Act, Cess Act and the Rules is to regulate the employment and conditions of service of building and other construction workers. The extension of the liability on a contractor is with a view to ensure that if for any reason it is not possible to collect the Cess from the owner of the building at a stage subsequent to the completion of the construction, it can be recovered from the contractor. The Apex Court has finally concluded that the cess under the Cess Act read with BOCW Act is leviable in respect of building and other construction works. The condition precedent for imposition of cess under the

Cess Act is the construction, repair, demolition or maintenance and in relation to a building or any other work of construction.

5. Therefore, Shri Maheshwari, learned counsel for the petitioner submits that in view of the aforesaid the impugned order is unsustainable and liable to be set aside.

6. Shri Bhuwan Gautam, learned Government Advocate for the respondents submits that the writ petition is not maintainable. The petitioner has a remedy of appeal before the appellate authority. The appellate authority may consider the judgment passed by the Apex Court while deciding the appeal.

7. We have perused the impugned order and it is apparent that the competent authority has passed the order mechanically calculating the cess @ 1% on the total cost of the project, whereas as per the judgment passed by the Apex Court in the case of Uttar Pradesh Power Transmission Corporation Ltd. (supra), the cess is

NEUTRAL CITATION NO. 2025:MPHC-IND:15182

3 WP-8163-2021 liable to be paid only in respect of the cost incurred in civil construction work etc.

8. Learned counsel for the petitioner submits that the petitioner has challenged the constitutional validity of the Rule 14(2)(b) & 14(2)(c) of BOCW Cess Rules, 1998.

9. In view of the aforesaid reasons, the impugned order is liable to be quashed and the matter is liable to be remanded back to the competent authority, therefore, at this stage the constitutional validity of the aforesaid rules is not being considered. The opportunity is granted to the petitioner to challenge it, if the occasion so arises in future.

10. Hence, the impugned order dated 12.3.2021 passed by the respondent No.3 is set aside and the matter is remitted back to the competent authority to examine the case again in the light of the judgment passed by the Apex Court in the case of Uttar Pradesh Power Transmission Corporation Ltd. (supra). The petitioner shall produce all the documents relating to the civil construction work and after examining the documents, the authority shall calculate the cess payable by the petitioner.

11. Writ petition is accordingly disposed of.

                                     (VIVEK RUSIA)                                 (BINOD KUMAR DWIVEDI)
                                         JUDGE                                             JUDGE
                          trilok

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter