Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Thahira vs Kerala State Electricity Board - Kseb
2025 Latest Caselaw 12387 Ker

Citation : 2025 Latest Caselaw 12387 Ker
Judgement Date : 17 December, 2025

[Cites 7, Cited by 0]

Kerala High Court

Thahira vs Kerala State Electricity Board - Kseb on 17 December, 2025

                                                                    2025:KER:97221
W.P(C) No.22214 of 2022                  1


                  IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                   PRESENT

                THE HONOURABLE MR.JUSTICE MOHAMMED NIAS C.P.

    WEDNESDAY, THE 17TH DAY OF DECEMBER 2025 / 26TH AGRAHAYANA, 1947

                          WP(C) NO. 22214 OF 2022


PETITIONER/S:

             THAHIRA,
             AGED 63 YEARS,EVOOR (SOUTH), KEERIKKADU.P.O, KAYAMKULAM,
             ALAPPUZHA DISTRICT, PIN-690508


             BY ADV SHRI.K.P.RAJEEVAN


RESPONDENT/S:

      1      KERALA STATE ELECTRICITY BOARD LTD.
             REPRESENTED BY ITS SECRETARY, VYDYUTHI BHAVANAM, PATTOM,
             THIRUVANANTHAPURAM, PIN-695 004

      2      ASSISTANT EXECUTIVE ENGINEER,
             ELECTRICAL SUB DIVISION, KERALA STATE ELECTRICITY BOARD
             LTD, KAYAMKULAM, ALAPPUZHA DISTRICT, PIN-690502.

      3      ASSISTANT ENGINEER,
             ELECTRICAL SECTION, KERALA STATE ELECTRICITY BOARD LTD,
             CHEPPAD, ALAPPUZHA DISTRICT, PIN-690507

      4      THE STATE ELECTRICITY OMBUDSMAN,
             CHARANGATTU BHAVAN, BUILDING NO.34/895, MAMANGALAM
             ANCHUMANA ROAD, EDAPPALLY, KOCHI, PIN-683025

      5      CONSUMER GRIEVANCE REDRESSAL FORUM (CENTRAL),
             220 KV SUBSTATION COMPOUND, HMT COLONY.P.O, KALAMASSERY,
             ERNAKULAM, PIN-683503.

             SRI. RIJI RAJENDRAN, SC


      THIS   WRIT   PETITION   (CIVIL)       HAVING   COME   UP   FOR   ADMISSION   ON
08.12.2025, THE COURT ON 17.12.2025 DELIVERED THE FOLLOWING:
                                                                                           2025:KER:97221
W.P(C) No.22214 of 2022                               2




                                  MOHAMMED NIAS C.P., J.
                      ......................................................
                                   W.P(C) No.22214 of 2022
                          .............................................................

                     Dated this the 17th day of December, 2025


                                               JUDGMENT

The petitioner, a consumer engaged in ice manufacturing under

Consumer No. 1155304022245 with LT-IV A demand-based tariff at

Electrical Section, Cheppad, challenges the orders of the Consumer

Grievance Redressal Forum (hereinafter 'CGRF') dated 03.03.2022 and the

State Electricity Ombudsman dated 20.06.2022, and the consequential

demand cum disconnection notice dated 25.06.2022, issued by the 3 rd

respondent, Assistant Engineer, Cheppad.

2. The petitioner asserts that the energy meter had been

functioning properly and was regularly inspected and billed without

arrears. On 14.09.2021, APTS, Alappuzha, conducted an inspection and

alleged that the R-phase was recording 29.70% below the actual

consumption. Based on this, a short assessment bill of Rs.96,147/- was

issued pursuant to the demand notice dated 01.11.2021 under Section 45 2025:KER:97221

of the Electricity Act, read with Regulation 134 of the Kerala Electricity

Supply Code (hereinafter 'the Supply Code').

3. The petitioner approached the CGRF challenging the said

demand, and the Forum ordered that the short assessment be reassessed

by revising the bills of 07.2021 and 08.2021 based on the average

consumption computed from the three billing cycles after the

replacement of the phase wire, i.e., from 10.2021. This was further

challenged before the Ombudsman, and by order dated 20.06.2022, the

Ombudsman affirmed the decision of the CGRF by following the very same

reasoning. Consequent to the order of the ombudsman, the 3rd

respondent issued a Demand cum disconnection notice dated 25.06.2022

with a revised bill for payment of Rs. 99,293/-.

4. The petitioner contends that Ext.P1 mahazar merely records

sludge formation at the R-phase terminal and voltage of 30.4 V in R-phase

against 234 V and 230 V in the other phases, and that the Sub Engineer

had no authority to unilaterally determine 29.70% under-recording since

Regulation 18(2) of the Central Electricity Authority (Installation and

Operation of Meters) Regulations, 2016 permits meter accuracy testing 2025:KER:97221

only through NABL-accredited laboratories or mobile testing units. It is

urged that Ext.P1 contains no reference to the downloading of data by

APTS, yet the assessment is admittedly based on such extraneous

material. Exts.P2 to P5 show the meter status as "working" in July,

August, and September 2021; hence, any defect could only have arisen

between 01.09.2021 and 14.09.2021, and the defect was rectified on the

very day of inspection. The petitioner submits that the anomaly noted in

Ext.P1 is a "meter defect" within the meaning of Regulation 2(57) of the

Supply Code, and therefore, assessment could only be undertaken under

Regulation 125, which mandates billing based on the average of the three

preceding billing cycles and limits assessment to two cycles.

5. The petitioner further contends that Ext.P10 bill dated

01.11.2021, issued after Ext.P9 objection to the demand notice, violates

the mandatory procedure prescribed under Ext.P11 KSEB Circular dated

25.02.2016 for handling meter-defect cases, and that the failure to record

tamper-data in the mahazar demonstrates procedural irregularity. It is

argued that Ext.P13 order of the CGRF, directing that the short

assessment be revised by reassessing the bills for July and August 2021

based on the average consumption for the three billing cycles after 2025:KER:97221

rectification, i.e., from 10/2021, adopts a methodology not contemplated

under Regulation 125 or Rule 7(3) of the Electricity Rules, 2005, and is

therefore unsustainable. The Ombudsman, by Ext.P15 order dated

20.06.2022, is stated to have repeated the same error by mechanically

affirming the Forum's reasoning without considering the prior billing-

cycle data in Exts. P17 to P22.

6. In the counter affidavit filed by respondents 1 to 3, it is stated

that during the APTS inspection on 14.09.2021, the petitioner's premises

were found equipped with a CT-operated energy meter (PGR Powertek,

MF 20), and examination of the voltage connections revealed weathering

and patina formation at the R-phase voltage tapping point. The voltage

recorded in the meter was only 30.4 V in the R-phase, while the Y and B

phases recorded 234 V and 230 V, respectively; however, the actual R-

phase voltage measured with a multimeter was 232V. To quantify the

under-recording, a Zera MT-310 standard meter (Sl. No. 50043258), duly

calibrated by the Electrical Inspectorate, was used, and it showed a

29.70% negative error. The respondents contend that such an

abnormality could not have been detected during routine monthly meter

reading and required specialised technical analysis. Since the shortfall for 2025:KER:97221

the period from 03.07.2021 to 14.09.2021 was identified only upon

inspection, Regulation 134 of the Kerala Electricity Supply Code, 2014,

authorises the licensee to assess and recover the undercharged amount.

They further submit that testing in an NABL-accredited laboratory was

not required because the meter itself was functioning properly and had

not been replaced; therefore, Regulation 125 of the Supply Code does not

apply as the anomaly arose from an external connection defect rather

than a "meter fault".

7. The respondents rely on Southern India Marine Products Co. v.

Kerala State Electricity Board and Others (MANU/KE/0404/1995), and

Indus Towers Limited v. Kerala State Electricity Board and Another, (W.P.

(C) No. 29244 of 2015) (Kerala High Court), to contend that where the

meter is intact, sealed, and in proper working condition, external issues

such as wrong connections, phase disconnection, or wiring defects do not

render it "faulty" and do not attract Regulation 125. They also note that

after the petitioner sought rectification, the R-phase tapping point was

cleaned and re-fixed, following which the meter began recording

accurately, confirming that the anomaly was external. The respondents

assert that the consumer cannot retain the benefit of reduced billing 2025:KER:97221

arising from such a connection defect and that the licensee is statutorily

entitled to recover the actual charges when under-recording is

established. Recovery of legitimately undercharged amounts is stated to

be consistent with Section 45 of the Electricity Act, the Supply Code

framework, and the public interest, and therefore, the assessment, as well

as the orders of the CGRF and the Ombudsman, are fully legal, valid, and

binding.

8. Heard Sri. K.P. Rajeevan, learned counsel for the petitioner,

and Sri. Riji Rajendran, learned Standing Counsel for the Board.

9. The CGRF, in its order dated 03.03.2022, found on verification

of the downloaded meter data produced by the APTS Wing that the R-

phase voltage had been abnormally low from 03.07.2021 onwards. At the

time of the APTS inspection, the R-phase voltage recorded was 30.4V. The

downloaded data showed wide fluctuations in R-phase voltage between

2.4V and 218V, with the voltage remaining below 100V for most of the

relevant period. The Forum concluded that applying the 29.7% error

detected by the Zera reference meter for the entire period was

inappropriate. It also noted that the anomaly was rectified on 14.09.2021 2025:KER:97221

by replacing the phase wires, after which the metering system functioned

properly. The Forum found the short assessment issued for the entire

month of September 2021 unsustainable. Examining the consumption

pattern between April 2021 and February 2022, it was found that higher

consumption was recorded post-rectification, clearly indicating that the

meter had under-recorded due to deteriorated phase wiring. The Forum

therefore directed that the short assessment be recomputed by applying

the average of the three billing cycles after replacement, i.e., from

October 2021, and revising the bills for July and August 2021 accordingly.

The Ombudsman concluded that the licensee was entitled to recover

undercharged amounts under Regulation 134 and upheld the

reassessment ordered by the CGRF.

10. In view of the above dispute, this Court on 18.11.2025

directed the Board to produce the petitioner's bills for the three months

preceding 14.09.2021, the date of inspection, and for the three months

thereafter. In compliance, the Standing Counsel produced Ext. R1(a)

series of bills. A comparison of the bills for the three months preceding

the inspection with those issued after the inspection and rectification

reveals a clear increase in consumption. This establishes that the meter 2025:KER:97221

had been under-recording prior to the inspection and rectification, and

therefore, the finding of the CGRF stands duly justified. There is no case

for the petitioner that the meter was faulty during this period.

11. In this case, the inspection revealed that patina (oxidation)

had developed at the connecting point of the phase wire-tapping voltage

from the R-phase to the meter, which was due to weathering and

atmospheric conditions. The anomaly was not with the energy meter

itself but with the external wiring connection that supplied voltage to the

meter, and it was rectified by replacing the affected phase wire, and after

cleaning and re-fixing the terminal, the meter began recording

accurately. Hence, this is not a case of a defective meter or faulty meter

within the meaning of Regulation 125 of the Supply Code. It is also to be

noted that Regulation 2(57) defines meter, and the connecting wire that

taps voltage from the R phase to the meter does not form part of the

meter as per the definition. Therefore, it is important to note that neither

the meter nor the CTs were defective.

12. The grievance forums relied upon contemporaneous

technical evidence, including downloaded meter data and an on-site 2025:KER:97221

accuracy test conducted with a calibrated Zera reference meter, which

confirmed under-recording. Their findings that the case does not fall

under Regulation 125 and that the reassessment should proceed under

Section 45 of the Electricity Act, 2003, read with Regulations 134, 136, and

152 of the Supply Code cannot be said to be wrong or illegal.

13. The method of reassessment adopted is rational, technically

supported, and consistent with the statutory framework governing

recovery of undercharged amounts. The petitioner's grievances regarding

non-detection by meter readers or the absence of NABL testing do not

absolve liability to pay for energy actually consumed when under-

recording is established on reliable technical evidence. For all the above

reasons, this Court finds no reason for interference in Exts.P13 and P15

orders of CGRF and Ombudsman respectively, and Ext.P16 demand.

The writ petition fails and is accordingly dismissed.

Sd/-

MOHAMMED NIAS C.P. JUDGE

okb/ 2025:KER:97221

APPENDIX OF WP(C) NO. 22214 OF 2022

PETITIONER EXHIBITS

Exhibit P1 A TRUE COPY OF THE MAHASAR DATED 14.9.2021. Exhibit P1a A TRUE COPY OF ENGLISH TRANSLATION OF EXHIBIT P1.

Exhibit P2 A TRUE COPY OF THE BILL NO.5530210600115 DATED 1.6.2021.

Exhibit P3 A TRUE COPY OF THE BILL NO.5530210700644 DATED 1.7.2021.

Exhibit P4 A TRUE COPY OF THE BILL NO.5530210800583 DATED 2.8.2021.

Exhibit P5 A TRUE COPY OF THE BILL NO.5530210900385 DATED 1.9.2021.

Exhibit P6 A TRUE COPY OF NOTICE DATED NIL ISSUED BY THE 3RD RESPONDENT TO THE PETITIONER.

Exhibit P7 A TRUE COPY OF THE NOTICE AND BILL DATED 1.10.2021.

Exhibit P7 a A TRUE COPY OF ENGLISH TRANSLATION OF EXHIBIT P7.

Exhibit P8 A TRUE COPY OF CALCULATION STATEMENT NO.INSP/202122/APTS DATED 14.9.2021.

Exhibit P9                A   TRUE   COPY   OF    FORWARDING   LETTER   I
                          NO/.DB/APTS DATED 1.11.2021.
Exhibit P10               A TRUE COPY OF BILL DATED 1.11.2021 ISSUED
                          TO THE PETITIONER.
Exhibit P10 a             A TRUE COPY OF ENGLISH TRANSLATION OF
                          EXHIBIT P10.
Exhibit P11               A TRUE COPY OF CIRCULAR NO.D(D&S)/D2/GENL-
                          08/2015 DATED 25.2.2016.
Exhibit P12               A TRUE COPY OF THE APPLICATION FOR FILING
                          COMPLAINT    WITH   THE    CONSUMER   GRIEVANCE
                          REDRESSAL FORUM (CENTRAL) DATED 22.9.2021.
Exhibit P13               A   TRUE    COPY   OF    ORDER    NO.CGRF-CR/OP
                          NO.53/2021-22 - 403 DATED 3.3.2022.
Exhibit P14               A TRUE COPY OF APPEAL NO.P/021/22 FILED BY
                          THE PETITIONER DATED 21.3.2022 BEFORE THE
                          STATE ELECTRICITY OMBUDSMAN
Exhibit P15               A TRUE COPY OF ORDER DATED 20.6.2022 IN
                          APPEAL PETITION NO.P/021/2022 OF THE STATE
                          ELECTRICITY OMBUDSMAN
Exhibit P16               A TRUE COPY OF LETTER NO. DEMAND CUM
                                                        2025:KER:97221



DISCONNECTION NOTICE/CON NO.22245/CHD/2022- 23/50 DATED 25.6.2022 ISSUED BY THE 3RD RESPONDENT.

Exhibit P17 A TRUE COPY OF BILL NO.5530210400112 DATED 1.4.2021 ISSUED TO THE PETITIONER Exhibit P18 A TRUE COPY OF BILL NO.5530210500113 DATED 1.5.2021 ISSUED TO THE PETITIONER Exhibit P19 A TRUE COPY OF BILL NO.5530210600115 DATED 1.6.2021 ISSUED TO THE PETITIONER Exhibit P20 A TRUE COPY OF BILL NO.5530210700644 DATED 1.7.2021 ISSUED TO THE PETITIONER Exhibit P21 A TRUE COPY OF BILL NO.5530210800583 DATED 2.8.2021 ISSUED TO THE PETITIONER Exhibit P22 A TRUE COPY OF BILL NO.5530210900385 DATED 1.9.2021 ISSUED TO THE PETITIONER RESPONDENT EXHIBITS

Exhibit R1 (a) A TRUE COPY OF THE OF BILLS PERTAINING TO Series THE PETITIONER FOR THE PERIOD RANGING FROM

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter