Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Power Grid Corporation Of India Ltd vs Raju Skariya
2024 Latest Caselaw 15990 Ker

Citation : 2024 Latest Caselaw 15990 Ker
Judgement Date : 7 June, 2024

Kerala High Court

Power Grid Corporation Of India Ltd vs Raju Skariya on 7 June, 2024

Author: V.G.Arun

Bench: V.G.Arun

           IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                  PRESENT
               THE HONOURABLE MR.JUSTICE V.G.ARUN
     FRIDAY, THE 7TH DAY OF JUNE 2024 / 17TH JYAISHTA, 1946
                          CRP NO. 755 OF 2018
AGAINST THE ORDER/JUDGMENT DATED 28.04.2018 IN OP NO.213
        OF 2010 OF ADDITIONAL DISTRICT COURT, KOZHIKODE


REVISION PETITIONER/S:

             POWER GRID CORPORATION OF INDIA LTD.
             REP. BY ITS ADDITIONAL GENERAL MANAGER,
             UGRAPURAM, AREACODE, MALAPPURAM DISTRICT.
             BY ADV E.M.MURUGAN


RESPONDENT/S:

             RAJU SKARIYA
             S/O SKARIYA, VARIKKAMAKKAL HOUSE, KUPPAYAKODE
             P.O., KOZHIKODE DISTRICT.
             BY ADVS.
             SMT.BIMALA BABY
             SHRI. JEFRIN JOSE


        THIS CIVIL REVISION PETITION HAVING COME UP FOR ADMISSION
ON    07.06.2024,   THE   COURT    ON   THE   SAME   DAY   DELIVERED   THE
FOLLOWING:
 CRP No.755 of 2018


                                 -2-



                               ORDER

Dated this the 07th day of June, 2024

The revision petitioner, Power Grid

Corporation of India Ltd ('the Corporation' for

short), is aggrieved by the enhanced compensation

ordered to be paid to the respondent towards

diminution in land value, consequent upon the

drawing of 400 KV electric lines across his

property by the Corporation. The essential facts

are as under;

The respondent is in ownership and possession

of landed property having an extent of 75 cents

comprised in Re-Sy.No.57/1 of Eangappuzha

Village. The land was cultivated with various

yielding and non-yielding trees. In order to

facilitate drawing of 400 KV electric lines for

the smooth transmission of power in the Mysore-

Kozhikode sector, large number of trees were cut

from the respondent's property. According to the

respondent, the drawing of high tension lines had

rendered the land underneath and adjacent

useless, resulting in diminution of the land

value. In spite of the huge loss suffered by the

respondent, only small amount was granted as

compensation. Hence, the original petition was

filed, seeking enhanced compensation towards the

value of trees cut and diminution in land value.

Being dissatisfied with the enhanced compensation

ordered by the court, the respondent preferred

civil revision petition and the same was allowed

by this Court and the case remanded back with a

direction to determine yield from each tree and

to consider all components of diminution in land

value including prevailing market price of the

land and any new factor which may be brought to

the notice of the court by the respondent.

2. After remand, the respondent filed a

statement before the court below clarifying that

he is not claiming additional compensation for

loss in value of improvements. Accordingly, the

court below considered the claim for enhanced

compensation towards diminution in land value

alone and passed the impugned order.

3. Heard learned Counsel appearing on

either side.

4. Learned Counsel for the revision

petitioner Corporation contended that the land

value fixed is not based on legal evidence.

Further, the additional compensation awarded is

unreasonable and the diminution in land value,

far in excess of the percentage fixed by the

Government. Per contra, learned Counsel for the

respondent argued that the enhancement is

reasonable and has been granted after considering

all relevant factors.

5. A perusal of the impugned order shows

that, although respondent had relied on Exts.A18

and A19 documents for the purpose of fixing land

value, considering the lie of the lands and

nature of transactions, the court below found

that the properties involved in Exts.A18 and A19

and the petition schedule property are not

similar or similarly situated. The court below

took note of the fact that an extent of 50 cents

is affected due to the drawing of electric lines

and going by the manner in which the lines were

drawn, more than half of the petition schedule

property was affected. Relying on the commission

report and plan, the court below found that the

petition schedule property is situated at a

distance of 2 Km from Kaithappoyil Town and abuts

Eangappuzha-Kodencherry PWD road. The Advocate

Commissioner had also reported that the civic

amenities are available within a radius of 1 Km

to 2 Km. Based on the said findings and a

comparison of the petition schedule property with

the property included in Ext.A20 common order,

the court below fixed the land value and also the

affected area and directed to pay 25% of the land

value as compensation. A table containing the

compensation thus awarded is appended below;

          Case No.        Affected     Land     Percent Compensati Compensa   Balance
                          area (in    value     age of on payable    tion   Compensatio
                           cents)    per cent   diminut              paid      n due
                                                  ion
      OP 213/2010           50       55,000     25%         6,87,500   1,00,000     5,87,500


     6.      On       careful              scrutiny          of        the        impugned

order, it is seen that the compensation payable

towards diminution in land value was fixed based

on factors like situs of the land, the extent to

which the land is adversely affected and

consequent diminution in the value of the land,

as laid down by the Apex Court in KSEB v. Livisha

[(2007) 6 SCC 792].

7. The contention of the Corporation that

the Government having fixed the fair value of the

land and also issued guidelines for the fixation

of the percentage of diminution, the court below

ought to have fixed the land value and percentage

of diminution in accordance with the same is

liable to be rejected since the court is not

bound by the guidelines/orders issued by the

Government while fixing the compensation. The

contention that the court below committed an

illegality by awarding 12% interest cannot also

be sustained in the light of the decision of this

Court in P.Raghavan v. KSEB [CRP No.3256 of

2001]. In view of the decision of this Court in

KSEB v Maranchi Matha [2008 (1) KLT 1038], the

argument that the court below has transgressed

its jurisdiction, by granting interest from the

date of cutting of trees, is also liable to be

rejected. As such, I find no reason to interfere

with the well considered order of the court

below, rendered after taking all relevant factors

into consideration.

For the aforementioned reasons, the civil

revision petition is dismissed.

Sd/-

V.G.ARUN JUDGE Scl/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter