WP(C) NO. 15209 OF 2018
PETITIONERS:
1 E.SUKUMARAN,
S/O.APPUNNU, IRULKUNNUMMEL HOUSE,
MUKKKOM PO, PIN 673 602,
KOZHIKODE DISTRICT.
2 T.SHIHABUDEEN,
S/O.MUHAMMED,THADATHIL HOUSE,
KODAVALLY PO, PIN 673 572,
KOZHIKODE DISTRICT.
BY ADVS.
SRI.P.T.MOHANKUMAR
SRI.C.M.ANDREWS
SMT.ANITYA ANNIE MATHEW
SMT.BOBY M.SEKHAR
KUM.LAYA MARY JOSEPH
SMT.NEETHU RAVIKUMAR
SMT.REVATHY P. MANOHARAN
SRI.SHYAM PADMAN
RESPONDENTS:
1 VAZHAYUR GRAMA PANCHAYAT
REPRESENTED BY ITS SECRETARY,KARAD PARAMBA PO,
PIN 673632,MALAPPURAM DISTRICT.
2 SECRETARY
VAZHAYUR GRAMA PANCHAYAT,KARAD PARAMBA PO,
PIN 673632,MALAPPURAM DISTRICT
3** THE LOCAL LEVEL MONITORING COMMITTEE,
REPRESENTED BY THE CONVENOR THE AGRICULTURAL
OFFICER, VAZHAYUR,AGRICULTURE OFFICE VAZHAYUR,
MALAPPURAM -673 639.
4 REVENUE DIVISIONAL OFFICER, TIRUR,
OFFICE OF THE RDO, TIRUR-THRIKANDIYOOR ROAD,
TIRUR,
PIN -676 101, MALAPPURAM DISTRICT
WP(C) NO.15209 OF 2018
2
[**RESPONDENTS 3 & 4 ARE IMPLEADED AS PER ORDER
DATED 06.06.2024 IN I.A. No.1 OF 2023 IN W.P.(C)
No.15209 OF 2018]
OTHER PRESENTS
SRI. BIMAL K.NATH - Sr.GOVERNMENT PLEADER
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR
ADMISSION ON 06.06.2024, THE COURT ON THE SAME DAY
DELIVERED THE FOLLOWING:
WP(C) NO.15209 OF 2018
3
M.A. ABDUL HAKHIM, J.
--------------------------------
W.P.(C) No. 15209 of 2018
--------------------------------
Dated this the 6th day of June, 2024
JUDGMENT
1. The grievance of the petitioners is that Ext.P3 building
permit was given to the petitioners and when the petitioners
started construction on the strength of Ext.P3 building permit,
Ext.P6 stop memo was issued to stop the construction on the
allegation that the land is a wetland and the petitioner is to
produce permission under the Kerala Conservation of Paddy
Land and Wetland Act, 2008. During pendency of this writ
petition, the petitioners have submitted Form-5 application to
the additional respondent No.3 on 03.01.2023.
2. In this circumstances, there will be a direction to the
additional respondent No.3 to consider and pass appropriate
orders on Ext.P8, Form-5 application within a period of two
months from the date of receipt of a copy of this Judgment.
Sd/-
M.A. ABDUL HAKHIM, JUDGE S.M.K. WP(C) NO.15209 OF 2018
APPENDIX OF WP(C) 15209/2018
PETITIONERS' EXHIBITS
Exhibit P-1 TRUE COPY OF THE SALE DEED,REGISTERED AS No.4270/2016 IN FAVOUR OF THE PETITIONERS EXHIBIT P2 TRUE COPY OF THE JUDGMENT IN WPC.NO.
17705/2014 OF THIS HON'BLE COURT, DATED 15.12.2014 EXHIBIT P3 TRUE COPY OF THE BUILDING PERMIT, ISSUED BY THE 2ND RESPONDENT DATED 03.06.2015 EXHIBIT P4 TRUE COPY OF THE APPLICATION SUBMITTED BY THE 1ST PETITIONER FOR TRANSFERRING THE BUILDING PERMIT DATED 05.03.2018 EXHIBIT P 5 TRUE COPY OF THE APPLICATION SUBMITTED BY THE VENDORS FOR TRANSFERRING THE BUILDING PERMIT DATED 17.04.2018 EXHIBIT P6 TRUE COPY OF THE STOPPAGE ORDER ISSUED BY THE 2ND RESPONDENT DATED 05.04.2018 EXHIBIT P7 TRUE COPY OF THE RELEVANT PAGE OF THE DATA BANK EXHIBIT P 8 TRUE COPY OF THE APPLICATION IN FORM NO. 5 FILED BEFORE THE RDO, TIRUR, DATED 03-01- 2023.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!