Tuesday, 19, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Power Grid Corporation Of India Ltd vs Nissy Cherian
2024 Latest Caselaw 15758 Ker

Citation : 2024 Latest Caselaw 15758 Ker
Judgement Date : 6 June, 2024

Kerala High Court

Power Grid Corporation Of India Ltd vs Nissy Cherian on 6 June, 2024

Author: V.G.Arun

Bench: V.G.Arun

                   IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                    PRESENT
                   THE HONOURABLE MR.JUSTICE V.G.ARUN
 THURSDAY, THE 6TH DAY OF JUNE 2024 / 16TH JYAISHTA, 1946
                              CRP NO. 888 OF 2019
   AGAINST THE ORDER/JUDGMENT DATED 05.04.2018 IN OPELE
       NO.252 OF 2013 OF ADDITIONAL DISTRICT COURT, NORTH
                                    PARAVUR
REVISION PETITIONER/S:

               POWER GRID CORPORATION OF INDIA LTD.,
               REPRESENTED BY ITS CHAIRMAN AND MANAGING
               DIRECTOR, B-9 QUTAB INSTITUTIONAL AREA,
               KATWARIA, SARAI, NEW DELHI 110 016.
               BY ADV ANJANA KANNATH


RESPONDENT/S:

       1       NISSY CHERIAN,
               W/O. CHERIAN, THEKKEKKARA HOUSE, MOOLAPPARA,
               CHULLI (P.O.), AYYAMPUZHA VILLAGE, ALUVA TALUK
               683 581.
       2       SPECIAL THAHZILDAR (LA),
               THE POWER GRID CORPORATION OF INDIA LTD.
               CHEVARAMBALAM, KOZHIKODE 673 017.
               BY ADVS.
               P.T.JOSE
               K.P.JOHNSON


THIS       CIVIL   REVISION    PETITION   HAVING   BEEN   FINALL   HEARD   ON
21.05.2024, THE COURT ON          06.06.2024 DELIVERED THE FOLLOWING:
 CRP No.888 of 2019

                                 -2-



                            ORDER

Dated this the 06th day of June, 2024

The revision petitioner, Power Grid

Corporation of India Ltd ('the Corporation' for

short), is aggrieved by the enhanced compensation

ordered to be paid to the first respondent ('the

claimant' for short), consequent upon the drawing

of 400 KV electric lines across her property by

the Corporation. The essential facts are as

under;

The claimant is in ownership and possession

of landed property having an extent of 10.12 Ares

comprised in Sy.Nos.140/1-2 and 140/1-3 of

Perumbavoor Village. The land was cultivated with

various yielding and non-yielding trees. In order

to facilitate drawing of lines for the smooth

transmission of power, large number of trees were

cut from the claimant's property. The drawing of

high tension lines rendered the land underneath

and adjacent to the lines useless, resulting in

diminution of the value of the property. In spite

of the huge loss suffered, only meagre amount was

paid to the claimant as compensation for the loss

sustained. Hence, the original petition was

filed, seeking enhanced compensation towards the

value of trees cut and diminution of land value.

2. Heard Adv.Millu Dandapani for the

Corporation and Adv.P.T.Jose for the claimant.

3. A perusal of the impugned order shows

that the court below has assessed the loss

sustained due to cutting of yielding coconut

palms by assessing the average number of nuts per

year and multiplying it with the value of one

coconut after deducting the immature falling and

expenses. Likewise, the loss sustained due to

cutting of yielding areca palm was assessed by

reckoning the total yield from each palm, the

weight of nuts after drying and the price of

dried nuts. Based on such assessment, the net

income was fixed after deducting the immature

falling and expenses. For reckoning the

compensation amount payable, 8 was taken as the

multiplier. Further, the court below enhanced

the compensation for cutting of timber trees to

Rs.2,000/-, as against Rs.1,000/- assessed by the

Commissioner. Being so, this Court finds the

procedure adopted by the court below to be just

and proper.

4. A perusal of the impugned order shows

that, for the purpose of fixing the compensation

towards diminution in land value, the court below

relied on Exts.C1 and C1(a) commission report and

plan. The Advocate Commissioner had reported that

the petition schedule property has road frontage.

On consideration of the evidence on record, the

land value was fixed at Rs.60,000/- per cent and

awarded 50% of the land value thus fixed as

compensation for the affected area admeasuring

1.98 Ares (4.89 cents). Accordingly, the claimant

was found entitled to compensation of

Rs.2,75,000/- with interest at the rate of 8% per

annum.

5. On careful scrutiny of the impugned

order, it is seen that the compensation due

towards diminution in land value was fixed based

on factors like situs of the land, the extent to

which the land is adversely affected and

consequent diminution in the value of the land,

as laid down by the Apex Court in KSEB v. Livisha

[(2007) 6 SCC 792]. Similarly, the discretion

vested with the court was properly exercised by

awarding 50% of the land value as compensation

for the land affected due to the drawing of

electric lines.

6. The contention of the Corporation that

while adequate compensation was paid to the

claimant in compliance of the orders/directions

of the Government, the court below could not have

altered the compensation is liable to be rejected

since the court is not bound by the

directions/orders issued by the Government while

fixing the compensation. As such, I find no

reason to interfere with the well considered

order of the court below, rendered after taking

all relevant factors into consideration.

For the aforementioned reasons, the civil

revision petition is dismissed.

Sd/-

V.G.ARUN JUDGE Scl/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter