Citation : 2021 Latest Caselaw 14027 Ker
Judgement Date : 7 July, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE THE CHIEF JUSTICE MR.S.MANIKUMAR
&
THE HONOURABLE MR. JUSTICE SHAJI P.CHALY
WEDNESDAY, THE 7TH DAY OF JULY 2021 / 16TH ASHADHA, 1943
WA NO. 824 OF 2021
AGAINST THE ORDER/JUDGMENT IN WP(C) 2017/2021 OF HIGH COURT OF KERALA, ERNAKULAM
APPELLANT/PETITIONER IN W.P.(C) 2017/2021:
GEORGE KURUVILA
AGED 61 YEARS
S/O. UMMAN, SANKARAMANGALAM HOUSE, ERAVIPEROOR P. O.
PATHANAMTHITTA DISTRICT.
BY
SRI.RANJITH THAMPAN(SR.)
ADV V.M.KRISHNAKUMAR
RESPONDENTS/RESPONDENTS IN W.P.(C)2017/2021:
1 STATE OF KERALA
REPRESENTED BY ITS SECRETARY, PUBLIC WORKS DEPARTMENT,
THIRUVANANTHAPURAM, PIN - 695 001.
2 SUPERINTENDING ENGINEER
PWD ROADS AND BRIDGES, SOUTH CIRCLE,
THIRUVANANTHAPURAM - 695 033.
3 EXECUTIVE ENGINEER
PWD ROADS DIVISION, KOTTAYAM - 686 001.
4 CHIEF ENGINEER
PUBLIC WORKS DEPARTMENT, THIRUVANANTHAPURAM - 695 001.
SRI.SURIN GEORGE IPE, SENIOR GOVERNMENT PLEADER FOR RESPONDENETS
THIS WRIT APPEAL HAVING COME UP FOR ADMISSION ON 07.07.2021,
THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WA.No.824 OF 2021 2
JUDGMENT
Dated this the 7th day of July 2021
SHAJI P.CHALY,J
Petitioner in the writ petition has filed this appeal, challenging the
judgment dated 8.4.2021, whereby the learned Single Judge directed the
respondents to permit the petitioner to complete the work, in case the
petitioner submits an undertaking before the Superintending Engineer,
Public Works Department, Roads and Bridges, South Circle,
Thiruvananthapuram - 2nd respondent, to complete the same before
31.5.2021. However, it was made clear that if petitioner does not furnish
any such undertaking, respondents would be free to proceed in accordance
with law. It is thus challenging the legality and correctness of the said
judgment, this appeal is preferred.
2. The subject issue relates to a contract awarded to the appellant by
the State Government. Brief material facts for the disposal of the writ
appeal are as follows; appellant is a Public Works Department A Class
Contractor and claims to be doing the contract work for the past more than
35 years. The Appellant participated in a tender Invited by the Public Works
Department (PWD) for improvement of the Kallungathara - Cheeppungal
Road Ch.1/70-4/250 and became the successful bidder. The work was
awarded to the appellant at 10% above the estimate rate. Agreement was
executed on 9.2.2012 and accordingly the appellant paid a sum of
Rs.8,24,000/- towards deposits and furnished bank guarantee for
Rs.8,33,050/-, evident from Exhibit P1 work order and Exhibit P2
agreement.
3. According to the appellant, as per Exhibit P3 letter dated 7.2.2018,
appellant has informed the Superintending Engineer that the work of
improvement of the road is to be undertaken through a paddy land, and
that it is marshy in nature. It was further stated that during the
construction of the first reach of the road, the road sank because of the
marshy nature of the land and therefore, requested the Superintending
Engineer to inspect the site and give proper direction to do foundation work
of the road. According to the appellant, though the appellant was issued
with the work order, the Executive Engineer, PWD Roads Division, Kottayam
- 3rd respondent, was convinced that if the road is constructed without soil
test, it will be an exercise detrimental to the department , and accordingly
issued Exhibit P4 letter to the Superintending Engineer, PWD, South Circle,
Thiruvananthapuram dated 13.6.2018 conveying that there is a possibility
of sinkage because of the marshy nature of the land and therefore to
conduct a soil test before construction of the road.
4. The case of the appellant is that because of lack of communication
from the department, the appellant could not even start the work or
complete the work within 6 months as is stipulated in the agreement. Other
contentions were also raised in the writ petition explaining the
circumstances disabling the appellant to proceed with the work.
5. Anyhow on 20.8.2018 appellant requested for extension of work and
also sought to take a decision regarding the construction of a foundation
and conduct of soil test as is suggested by the Executive Engineer in Exhibit
P4 letter. It appears without mentioning anything with respect to the soil
test or the foundation work, the Superintending Engineer, extended the
time for work up to 19.12.2018 and directed the appellant to sign the
contract. Having not been satisfied with the mere extension of work,
appellant had submitted Exhibit P7 representation, and in that he had
requested for return of the advance amount and the bank guarantee apart
from claiming damages. According to the appellant, even though he has
approached the office of the Minister concerned, there was no response.
6. From the record of proceedings, it is seen that there were no further
proceedings issued in that regard till 21.12.2020, on which date Exhibit P9
notice was issued by the Executive Engineer, PWD Roads Division,
Kottayam directing the appellant to start the construction within 10 days.
Thereupon, appellant preferred Exhibit P10 reply dated 1.1.2021 (wrongly
noted the date as 1.1.2020) wherein, it was mentioned that a revised
estimate has to be made and the construction is to be permitted on the
basis of revised estimate including the GST and if done so, appellant can
proceed with the work.
7. Therefore, the sum and substance of the contention was that unless
and until a revised estimate was prepared to carry on with the work, the
appellant was not interested in proceeding with the work. Which thus
means appellant was not prepared to complete the work on the rate agreed
as per Exhibit P1 work order dated 29.1.2018. It was thus seeking to quash
Exhibit P9 and to command the Superintending Engineer to refund the
security deposit and the bank guarantee, the writ petition was filed.
8. The learned Single Judge after taking into account the rival
submissions made and relying upon the counter affidavit filed by the
Executive Engineer that sufficient time for completing the work was given,
the writ petition was disposed of as is specified above. It was also pointed
out in the judgment that the issue with respect to the marshy land through
which the construction was to be carried out, was a matter ought to have
been taken note of by the appellant before submitting the tender. It was
also noted that the counter of the 3 rd respondent shows that the majority
of the extent of the road is not a marshy area and work could be carried out
without any difficulty.
9. The learned Single Judge had also found that the appellant never
approached the respondents to get the agreement extended and he has
never conveyed that he was willing to carry out the work even though it is
stated so in the writ petition. Therefore, taking into account the interest
expressed by the appellant to complete the work in the writ petition, the
direction was issued in the judgment to complete the work before
31.5.2021.
10. In fact a detailed counter affidavit was filed in the writ petition by
the Executive Engineer, in which it was stated that even though the work
site was handed over, appellant has not cared to complete the work within
the time period or to extend the period. It was also stated thereunder that
before submitting the bid, the appellant has visited the site and was
satisfied himself with the site condition for construction and logistics, and
smooth flow of workmen and materials including the permission to be
secured from the respective authorities for the purpose. Therefore, it was
contended by the State that the appellant cannot resile from the terms and
conditions of the contract and the reliefs sought for by the appellant cannot
be granted since the work could not be completed absolutely due to the
default on the part of the appellant.
11. The basic contention advanced by the appellant in the appeal is
that the appellant has submitted in the writ petition his willingness to
complete the work,on condition that a fresh estimate is prepared for the
work taking into account the soil and other conditions of the site in
question, but the learned Single Judge had ignored the said vital aspect
though it was recorded that the appellant has expressed his willingness to
complete the work.
12. We have heard Senior Adv.Sri.Ranjith Thampan appeared for the
appellant, assisted by Sri.V.M.Krishnakumar, Sri.Surin Geroge Ipe, learned
Senior Government Pleader, for the respondents and perused the pleadings
and materials on record.
13. It is an admitted fact that on the basis of the tender submitted by
the appellant, the work was awarded to the appellant as per Exhibit P1 work
order dated 29.1.2018. As per the terms and the conditions prescribed
under the work order, a security amount was deposited and a bank
guarantee was also extended and executed Exhibit P2 agreement. It is also
an admitted fact that the appellant did not proceed with the work assigning
the reason that the site in question is a marshy land and unless and until
the foundation work is carried out, there is every likelihood of the road
being damaged because of that. It is evident from Exhibit P3 that even
before issuance of the work order, appellant had addressed the
Superintending Engineer as per Exhibit P3 letter dated 7.2.2018 explaining
about the nature of the land and the likelihood of damage being caused to
the road unless the foundation is strengthened. In fact, the Executive
Engineer, consequent to the representation of the appellant, had addressed
the Superintending Engineer as per Exhibit P4 letter dated 13.6.2018
presumably after visiting the site and expressed his apprehension of the
damage of the road consequent to the marshy nature of the property and
suggested soil test.
14. Anyhow it is clear that the issue remained dormant after the Exhibit
P4 letter issued by the Executive Engineer till Exhibit P9 communication
dated 21.12.2020 was issued by the Executive Engineer directing the
appellant to start the work within 7 days. It is also evident from the records
that appellant had addressed the Superintending Engineer on 19.10.2018
also expressing his concern of not taking steps to consider the request
made by the appellant in regard to the soil test and proceeding with the
work or in the alternative, repayment of the security deposit and return of
the bank guarantee.
15. Therefore, assimilating the fact situation, we are of the considered
opinion that various issues were pointed out by the appellant either
immediately before or after Exhibit P1 work order was issued to the
appellant. The apprehension voiced by the appellant was very well
supported by the Executive Engineer as per Exhibit P4 communication dated
13.6.2018, which is narrated above. It is also curious to note that after
Exhibit P4 dated 13.6.2018, there was no communication till Exhibit P9
dated 21.12.2020 directing the appellant to start the work within 7 days
without addressing the issue raised by the appellant in regard to the
conditions of the work site.
16. It may be true the appellant has stated in the writ petition that he
is prepared to carry on with the work. But going by the record of
proceedings, it is clear that appellant has undertaken to continue with the
work on condition that the work was re-estimated with enhancement of
rates. Therefore, the findings rendered by the learned Single Judge that
since the appellant admitted to carry on with the work, and thus granting
time to the appellant to complete the work on or before 31.5.2021 without
addressing the issue of demand made by the appellant for re-estimate of
the work may not be a correct approach to the issue.
17. We are also of the view that the learned Single Judge, relied upon
the counter affidavit filed by the Assistant Engineer, PWD Works
Department, PWD Roads Division, Kottayam, and probably was of the
opinion that the appellant must have visited the site before the tender was
submitted. In the absence of Exhibit P4 letter addressed by the Executive
Engineer dated 13.6.2018 to the Superintending Engineer, the apprehension
of damage of the road consequent to the marshy nature of land and
proceeding without conducting soil test before starting construction of the
road, the findings of the learned Single Judge would have been correct. But
in our view the issue should have been considered and adjudicated, taking
into account the apprehension of the Executive Engineer itself and having
not done so, we feel it appropriate and proper that the judgment is set
aside and send it back for reconsideration in accordance with law, taking
into account the rival submissions made by the parties.
Accordingly, we set aside the judgment of the learned Single Judge
dated 8.4.2021 in the writ petition in question and remit the matter back for
consideration afresh after hearing the respective parties.
Sd/-
S.MANIKUMAR
CHIEF JUSTICE
Sd/-
SHAJI P.CHALY
smv JUDGE
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!