Citation : 2025 Latest Caselaw 2435 J&K
Judgement Date : 18 October, 2025
HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT JAMMU
Reserved on: 08.10.2025
Pronounced on: 18.10.2025
Uploaded on:18.10.2025
Whether the operative part or
full judgment is pronounced
Case No.:- WP(C) No 1406/2024
M/s Malik Builders & Contractors
.....Petitioner(s)
Through: Mr. Muzaffar Iqbal Khan, Advocate
Mr. Mazher Ali Khan, Advocate.
Vs
UT of J&K and anr.
..... Respondent(s)
Through: Mr. Ravinder Gupta, AAG
Mr. M.Y Akhoon, Advocate
Coram: HON'BLE MR. JUSTICE SANJAY DHAR, JUDGE
JUDGMENT
1. The petitioner, through the medium of present petition, has
challenged order No. 23-CEP (R&B) of 2024 dated 05.06.2024
issued by respondent No. 2 whereby Letter of Acceptance
issued vide No. CEP/R&B/3296-3300 dated 15.02.2024 in
favour of the petitioner in connection with the work
"construction of road from Darmala Saleri to Danti Killa
(under NABARD)" has been withdrawn. Challenge has also
been thrown to e-NIT No. 01 of 2024-25 dated 05.06.2024
issued by respondent No. 2 whereby fresh tenders have been
invited for the aforesaid work.
2. Briefly stated, the facts emanating from the pleadings of the
parties are that e-NIT No. 01 of 2023-24 dated 24.11.2023 for
allotment of civil works including the work related to
construction of road from Darmala Saleri to Danti Killa in
District Rajouri was issued by respondent No. 2. The
estimated cost of work was to the tune of Rs. 810.00 lacs. The
petitioner as well as respondent No. 3 and 05 more entities
responded to the aforesaid e-NIT. Upon opening of technical
bid on 05.02.2024, the petitioner and three more bidders
including respondent No. 3 were declared as "responsive",
whereas, three other bidders were declared as "non-
responsive". Respondent No. 3 was also declared as "non-
responsive"" by the "Technical Evaluation Committee" in terms
of technical Evaluation Summary Sheet/Report dated
14.02.2024. Thereafter, the official respondents opened the
financial bid on 14.02.2024 and declared the petitioner as
lowest bidder (L1).
3. It seems that one of the bidders M/s Green Earth
Infrastructure Pvt. Ltd called in question the Technical
Evaluation Summary Sheet/Report dated 14.02.2024 to the
extent of declaration of the petitioner firm as technically
qualified/responsive by way of writ petition bearing WP(C) No.
327/2024. Challenge was also thrown to financial bid
summary dated 14.02.2024 issued by respondent No. 2
whereby the petitioner-firm was declared as lowest bidder. The
aforesaid writ petition came to be disposed of by this Court in
terms of judgment dated 22.03.2024.
4. Respondent No. 2 vide his communication No.
CEP/R&B/3296-3300 dated 15.02.2024 issued Letter of
Acceptance in favour of the petitioner-firm whereby while,
accepting offer of the petitioner for contract price of
Rs. 6,25,89,900/- , the petitioner firm was directed to furnish
security (3%) for an amount of Rs. 18,77,697/- with additional
performance security (10%) for an amount of Rs. 62,58,990/-
valid as per Standard Bidding Document (SBD) conditions
duly pledged to Chief Accounts Officer, PW(R&B) Department,
Pir Panjal Range within a period of 21 days from the date of
issuance of Letter of Acceptance and it was further provided
that the petitioner shall submit documents in original for
signing contract agreement within 10 days.
5. According to the petitioner, in compliance to the aforesaid
Letter of Acceptance, it deposited the performance security as
well as additional performance security vide two separate bank
guarantees dated 26.03.2024, copies whereof have been
placed on record.
6. It seems that the official respondents after the aforesaid
developments, issued the impugned order dated 25.06.2024
wherein, it has been provided that it has become necessary to
rectify the bidding process by way of a withdrawing Letter of
Acceptance dated 15.02.2024 issued in favour of the petitioner
so as to avoid huge loss of Government Exchequer and to
conduct healthy competition amongst the bidders. Besides
this, the official respondents vide the said order which, it
appears has been issued on the recommendations of Technical
Evaluation Committee members found lack of merit for
allotment of contract in favour of the petitioner and it was also
decided that fresh e-NIT shall be issued for execution of the
work in question. Pursuant to the said order, the impugned e-
NIT No. 01 of 2024-25 dated 05.06.2024 has been issued by
the official respondents.
7. The petitioner has challenged the impugned action of the
respondents on the grounds that the same is mala-fide and
actuated by extraneous considerations. It has been contended
that once the Letter of Acceptance was issued by the official
respondents in favour of the petitioner, the contract between
the two stood concluded as such, it was not open to the official
respondents to revoke the said contract that too without
hearing the petitioner. It has been further contended that the
reason assigned by the official respondents in revoking the
Letter of Acceptance and in issuing the fresh tender is
completely irrational inasmuch as merely, because private
respondent No. 3 had submitted a bid lower than the bid of
the petitioner would not give a cause to the official
respondents to revoke the Letter of Acceptance and issue fresh
tenders particularly, when private respondent No. 3 had
admittedly been declared as "non-responsive" during the
technical evaluation. It has been contended that the action of
respondent No. 2 is completely arbitrary which cannot be
sustained in law.
8. The official respondents while, defending their action have
submitted that during the opening of the financial bids
inadvertently, the financial bid of private respondent No. 3
who was declared as "non-responsive" during the technical
evaluation also came to be uploaded/opened though, he was
not eligible. It has been further submitted that the rates
quoted by the said bidder were Rs. 94.63 lacs less than the
rate quoted by the petitioner. Thus, there was a huge gap
between the rate quoted by the petitioner and that quoted by
private respondent No. 3. Taking into consideration this
aspect, the matter was again referred to Technical Evaluation
Committee for re-examination and it was decided that in
exercise of power under Clause 28.1 of the SBD, Letter of
Acceptance issued in favour of the petitioner deserves to be
revoked and the work should be put to retendering so as to
avoid loss to the State Exchequer.
9. The official respondents have further contended that there was
no concluded contract between the petitioner and the official
respondents and that letter dated 15.02.2024 was only a
Letter of Intent and in terms of the said letter, the petitioner
was required to fulfil certain conditions which included the
furnishing of performance security and additional performance
security in accordance with the terms of SBD. It has been
submitted that the petitioner furnished bank guarantees only
for a period of one year though as per the terms of the SBD, it
was required to furnish bank guarantees for 05 years. Thus,
the petitioner has not fulfilled the terms and conditions
mentioned in the Letter of Acceptance as such, no concluded
contract had taken place between the parties.
10. I have heard learned counsel for the parties and perused the
record of case.
11. From the pleadings of the parties, it comes to the fore that it is
not in dispute that pursuant to the participation of the
petitioner in e-NIT dated 24.11.2023, the work relating to
construction of road from Darmala Saleri to Danti Killa was
allotted to the petitioner in terms of Letter of Acceptance dated
15.02.2024. The official respondents claim that they cancelled
its Letter of Allotment because during the re-examination of
bid documents, it came to the fore that inadvertently, financial
bid of private respondent No. 3 who was admittedly declared
as disqualified/non-responsive during the process of technical
evaluation, had been uploaded/opened. It is the case of the
official respondents that bid submitted by the said respondent
was lower by more than Rs. 94 lacs than the bid of petitioner
and in view of this huge gap, the Technical Evaluation
Committee decided to cancel the allotment letter issued in
favour of the petitioner so as to avoid loss to the State
Exchequer. It is the further case of the official respondents
that as per the terms of allotment letter dated 15.02.2024, the
petitioner was required to furnish two bank guarantees on
account of performance security and additional performance
security valid for a period of 05 years but instead of doing so,
it furnished bank guarantees valid only for one year. Thus, the
conditions of Letter of Acceptance have not been fulfilled by
the petitioner as a result whereof, no concluded contract has
come into being between the parties.
12. In the impugned cancellation order dated 05.06.2024, the only
reason given by the official respondents for cancellation of
letter of allotment is inadvertent opening of financial bid of
private respondent No. 3 which turned out to be Rs. 94.63 lacs
below the rate quoted by the petitioner who had emerged as L1
amongst the responsive bidders. The case set up in the
impugned cancellation letter dated 05.06.2024 is that in the
interests of the State Exchequer, it was decided to cancel the
letter of allotment issued in favour of the petitioner and to
retender the works. In the impugned cancellation letter, aid of
Clause 5.6.6 of Manual for Procurement of Works, 2019 issued
by Government of India, Ministry of Finance Department and
Expenditure has also been taken for issuing the said letter.
The official respondents, in their reply, have also relied upon
Clause 28.1 of Section 1 of Instructions to Bidders as
contained in SBD.
13. As already noted, there is no mention of non-furnishing of
bank guarantees valid for a period of 05 years by the petitioner
as a ground for cancellation for the letter of allotment issued
in favour of the petitioner in the impugned order. This stand
has been taken by the official respondents for the first time in
their reply affidavit. The Supreme Court has, in the case of
Mohinder Singh Gill Vs. Chief Election Commissioner;
1978 (1) SCC 405 held that where an authority makes an
order based on certain grounds its validity must be judged by
the reasons so mentioned and cannot be supplemented by
fresh reasons in the shape of affidavit or otherwise. The
Supreme Court has further observed that if an authority is
allowed to supply fresh reasons, then an order bad in the
beginning may be, by the time it comes to Court on account of
a challenge, get validated by additional grounds later brought
out.
14. In the face of aforesaid legal position, it is not open to the
official respondents to supply an additional ground for their
impugned action by urging the same in their reply affidavit. In
any case, the respondents have not placed on record any
document to even remotely suggest that they had called upon
the petitioner to extend the validity of bank guarantees
furnished by it and that despite this, the petitioner had
avoided to do so. Thus, the contention of the official
respondents in this regard cannot be accepted.
15. That takes us to the question as to whether the other reason
furnished by the official respondents for cancelling the letter of
allotment of the petitioner offers the justification for their
impugned action. The only reason given by the official
respondents for cancelling the letter of allotment in favour of
the petitioner is that while opening the financial bid of a non-
responsive bidder, it was found that bid of the said non-
responsive bidder was more than Rs. 94 lacs below the bid
submitted by the petitioner and therefore, with a view to avoid
loss to the State Exchequer, it was thought appropriate to
cancel the letter of allotment issued in favour of the petitioner.
16. In the first place, the official respondents could not have
opened the financial bid of a non-responsive bidder. If they
have done so inadvertently, which is a fault attributable to
none other than the respondents, they cannot make the
petitioner to suffer for that. Merely because the bid of the non-
responsive bidder was found to be less than the bid submitted
by the petitioner, who had emerged L1 amongst the responsive
bidders, does not offer a ground to cancel the letter of
allotment in its favour. It is a settled law that merely because a
bid is the lowest, the requirement of compliances to the rules
and conditions should be ignored. If the logic given by the
official respondents is accepted, then if they open the financial
bids of other non-responsive bidders, it is quite probable that
they may find some other non-responsive bidder having
quoted a lesser price than what has been quoted by private
respondent No. 3. If such a procedure is permitted, then
technical evaluation of bids will become an empty formality
and even an unqualified bidder who has quoted less price can
stake his claim for contract. The same is not permissible in
law. The reason and logic given by the official respondents for
cancelling the letter of allotment in favour of the petitioner is
grossly irrational and arbitrary which, no prudent employer
would take in the facts and circumstances of the case.
17. The official respondents for the purpose of defending their
impugned action have taken resort to Clause 5.6.6 of Manual
For Procurement of Works issued by the Government of India.
The said Clause reads as under:-
"5.6.6 Negotiations
i) Normally, there should be no negotiation.
Negotiations should be a rare exception rather than the rule and may be resorted to only in exceptional circumstances. If it is decided to hold negotiations for reduction of prices, they should be held only with the lowest acceptable bidder (L1), who is techno- commercially responsive for the supply of a bulk quantity and on whom the contract would have been placed but for the decision to negotiate. In no case, including where a cartel/ pool rates are suspected, should negotiations be extended to those who had either not tendered originally or whose tender was rejected because of unresponsiveness of bid, unsatisfactory credentials, inadequacy of capacity or unworkable rates. The circumstances where negotiations may be considered could be:
a) Where the procurement is done on nomination basis;
b) Procurement is from single or limited sources; c) Procurements where there is suspicion of cartel formation which should be recorded; and
d) Where the requirements are urgent and the delay in re-tendering for the entire requirement due to the unreasonableness of the quoted rates would jeopardise essential operations, maintenance and safety, negotiations with L1 bidder(s) may be done for bare minimum quantum of requirements. The balance
bulk requirement should, however, be procured through a re-tender, following the normal tendering process.
ii) The decision whether to invite fresh tenders or to negotiate and with whom, should be made by the tender accepting authority based on the recommendations of the TC. Convincing reasons must be recorded by the authority recommending negotiations. The CA should exercise due diligence while accepting a tender or ordering negotiations or calling for a re-tender and a definite timeframe should be indicated.
iii) Normally all counter offers are considered negotiations by other means and the principles of negotiations should apply to such counter offers. For example, a counter offer to L1, in order to arrive at an acceptable rate, shall amount to a negotiation.
However, any counter offer to L2, L3, and so on (at the rates accepted by L1) in case of splitting of quantities shall not be deemed to be a negotiation.
iv) After the CA or TC has decided to call a specific bidder for negotiation, the following procedure should be adopted:
a) Negotiations must be carried out by the CA or TC only;
b) It must be understood that, if the period of validity of the original offer expires before the close of negotiations, the original offer will not be available for acceptance. The period of validity of the original offer must, therefore, be extended, wherever necessary, before negotiations;
c) The tenderer to be called in for negotiations should be addressed as per the format of letter laid down in Annexure 4, so that the rates originally quoted by him
shall remain open for acceptance in the event of failure of the contemplated negotiation;
d) A negotiations meeting should be started only after obtaining a signed declaration from the negotiating contractor as per Annexure 4; and
e) Revised bids should be obtained in writing from the selected tenderers at the end of the negotiations in the format of letter laid down in Annexure 5. The revised bids so obtained should be read out to the tenderers or their representatives present, immediately after completing the negotiations. If necessary, the negotiating party may be given some time to submit its revised offer. In case, however, the selected bidder prefers to send a revised bid instead of being present at the negotiation, the offer should be taken into account. In case a bidder does not submit the revised bid, its original bid shall be considered."
18. From a perusal of the aforesaid Clause, it comes to the fore
that negotiations with the bidders after the opening of bids are
forbidden except in certain circumstances. It has been
provided that negotiations should be held in exceptional
circumstances that too only with the lowest acceptable
bidder (L1) who is techno-commercially responsive. It further
provides that in no case, the negotiations should be extended
to those who had either not tendered originally or whose
tender was rejected because of unresponsiveness of bid.
19. This Court fails to comprehend as to how the afore quoted
Clause comes to the rescue of official respondents. As per the
mandate of said Clause, the respondents could not have held
negotiations with respondent No. 3 who was admittedly non-
responsive and, therefore, could not have been treated as L1.
Amongst the responsive bidders, the petitioner was the L1 and
they could have negotiated only with the petitioner and no one
else if at all negotiations were needed. By taking resort to the
said Clause, the official respondents cannot justify their
impugned action.
20. The official respondents have also drawn support for their
impugned action from Clause 28.1 of Section 1 of Instructions
to bidders of the SBD, which reads as under:-'
"Not withstanding Clause 27 the Employer reserves the right to accept or reject any bid and to cancel the bidding process and reject all bids, at any time prior to award of Contract, without thereby incurring any liability to the affected bidder or bidders or any obligations to inform the affected bidder or bidders of the grounds for the Employer's action"
21. A perusal of the aforesaid Clause reveals that employer has
the right to accept or reject any bid or even to cancel the
bidding process as a whole but the said right has to be
exercised prior to the award of the contract. In the instant
case, the bid submitted by the petitioner which was admittedly
responsive, was accepted by the official respondents pursuant
whereto they issued Letter of Acceptance dated 15.02.2024. In
the said letter, the respondent No. 2 has, in unequivocal terms
conveyed to the petitioner that its bid in response to e-NIT No.
01/2023-24 dated 24.11.2023 with respect to work for
construction of road from Darmala Saleri to Danti Killa stands
accepted for contract price of Rs. 6,25,89,900/- meaning
thereby a concluded contract came into being between the
petitioner and official respondents with the issuance of the
said letter.
22. Section 4 of the Contract Act clearly provides that
communication of the acceptance is complete as against the
proposer when it is put in course of transmission so as to be
out of the power of the acceptor and as against the acceptor
when it comes to the knowledge of the proposer. In the present
case, e-NIT issued by the official respondents constituted an
invitation to offer in pursuance whereto, the petitioner
submitted its bid for contract price of Rs. 6,25,89,900/- which
constitutes its proposal to the official respondents. Once Letter
of Acceptance dated 15.02.2024 was put into transmission by
the official respondents accepting the proposal of the
petitioner, the said acceptance is complete as against the
official respondents when the said letter came to the
knowledge of the petitioner. Thus, the moment, Acceptance
Letter dated 15.02.2024 came to the knowledge of the
petitioner, a concluded contract came into being between the
petitioner and the official respondents. Therefore, at that
stage, it was not open to the official respondents to take resort
to the Clause quoted above with a view to revoke the
acceptance letter as well as the bidding process.
23. The acceptance letter issued by respondent No. 2 is clear and
unequivocal. The requirement of fresh performance security
and additional performance security and signing of contract
agreement is only a formality, and not a condition precedent to
the contract. Merely, because the petitioner in the first
instance, did not furnish the bank guarantees valid for period
of 05 years and instead furnished bank guarantees with
validity for a period of one year, does not amount to non-
fulfilment of the conditions of the Letter of acceptance which,
as already stated, is unequivocal and unconditional in nature.
24. It has been contended by learned counsel for the respondents
that even if there is any breach on the part of the respondents,
still then, the remedy available to the petitioners is to claim
damages by filing a civil suit against the official respondents. I
am afraid the contention raised by learned counsel for the
official respondents is not legally tenable. As already stated,
with the issuance of Acceptance Letter dated 15.02.2024, a
complete and binding contract came into being between the
parties giving rise to rights and liabilities amongst the parties
inter-se. The official respondents were, therefore, obliged to
issue a notice to the petitioner before taking any action
prejudicial to his interests under the Contract. The official
respondents being officers of the State are duty bound to act
fairly before taking an action against the allottee of the work
which, in the instant case, has not been done.
25. The Supreme Court in the case of R.D Shetty Vs. Intl. Air
Port Authority, 1979 (3) SCC 489 held that actions of the
State authorities even in matters relating to contract have to
meet the tests of fairness and reasonableness. The action of
the respondents in cancelling the Letter of Acceptance in
favour of the petitioner smacks of arbitrariness as they have
breached the principles of natural justice, thereby rendering
their action unsustainable in law. Once it is shown that the
action of the functionaries of the State smacks of arbitrariness
violating the provisions of Article 14 of the Constitution, writ
Court would be well within its jurisdiction to intervene even in
contractual matters. Thus, the present writ petition is
maintainable.
26. In view of what has been discussed hereinabove, the instant
writ petition is allowed and the cancellation order dated
05.06.2024 whereby Letter of Acceptance issued in favour of
the petitioner and the e-NIT No. 01 of 2023-24 dated
24.11.2023 have been cancelled, is quashed. Consequently,
e-NIT No. 01 of 2024-25 dated 05.06.2024 shall also stand
quashed. The respondents are directed to permit the petitioner
to execute the work in accordance with the terms and
conditions of the contract/allotment letter.
(SANJAY DHAR) JUDGE JAMMU 18.10.2025 Tarun/PS Whether order is speaking: Yes
Whether order is reportable: Yes
Mahavir Singh
2025.10.18 17:54
integrity of this document
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!