Wednesday, 20, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Harish Gupta Age 41 Years vs Union Of India Through Secretary
2025 Latest Caselaw 934 J&K

Citation : 2025 Latest Caselaw 934 J&K
Judgement Date : 13 February, 2025

Jammu & Kashmir High Court

Harish Gupta Age 41 Years vs Union Of India Through Secretary on 13 February, 2025

Author: Chief Justice
Bench: Chief Justice
          HIGH COURT OF JAMMU & KASHMIR AND LADAKH
                          AT JAMMU

                                                     Arb P No. 71/2024

                                                     Reserved on : 07.02.2025
                                                     Pronounced on : 13.02.2025


 Harish Gupta age 41 years
 Prop. M/S Harish Gupta, 149, Phase-II,
 Housing Colony, Udhampur (J&K)-182101                      ....Petitioner(s)
                   Through :- Mr. Sumit Moza, Advocate
                               Mr. Gourav Sadotra, Advocate
         V/s
 1. Union of India Through Secretary,
    Ministry of Defence, New Delhi
 2. 52 Road Constr. Coy. (GREF) C/o 56 APO
 3. Head Quarter, 760, Border Road Task Force,
    C/o 56 APO                                                   ....Respondent(s)

                    Through :-    Mr. Vishal Sharma, DSGI

 Coram: HON'BLE THE CHIEF JUSTICE

                                   JUDGMENT

1. Heard Mr. Sumit Moza, learned counsel for the petitioner and Mr. Vishal

Sharma, learned DSGI for the respondents at length and perused the record.

2. The present petition has been filed by the petitioner seeking appointment

of an independent Arbitrator under Section 11 of the Arbitration and Conciliation

Act, 1996 read with clause 23 of Special Conditions of Contract and clause 37 of

General Conditions of Contract (IAFW-1815Z) in pursuance to tender no. CDR

35 TF/04/2021-22 to settle the disputes that has arisen between the parties.

3. Brief facts, which lead to the filing of the present petition, are that the

petitioner is the Proprietor of M/S Harish Gupta firm and vide Notice Inviting

Tender (NIT) bearing CA No. CDR-35 BRTF/ /2021-22 bearing Tender No.

CDR-35 TF/04/2021-2022 dated 08.02.2022, the Commander 35 Border Roads

Task Force invited online bids on single stage two bid system for Supply and

Stacking of Stone Aggregate 13.20 MM, 11.20 MM, 6.70 MM and COARSE

Sand at HMP Site KM 24.800 on Ramban-Gul Road for re-surfacing works on

Ramban-Gul Road and Nashri Bye-Pass Road in 52 RCC Sector under 35 BRTF

project Beacon and the cost of estimated works was fixed at Rs. 84.14 lacs; that as

per Clause 7 of NIT it was provided that the work was required to be completed

within 180 days from the date of handing over the site.

4. It is averred that the petitioner's bid was lowest and as a result was

declared as L1 and the letter of acceptance regarding the said work was issued by

Commander 35 BRTF in favour of the petitioner vide letter dated 09.04.2022. It is

further averred that in terms of the communication dated 17.05.2022, the

petitioner was directed to supply and stack the stone aggregate 13.20 MM, 11.20

MM, 6.70 MM and Coarse Sand at HMP Site as provided in the contract and the

petitioner made available the same, however, despite repeated requests the site

was not handed over to the petitioner for almost three months; that the

respondents verbally directed the petitioner to make the supplies vehicle-wise in

piece-meals as the respondents did not have a proper dumping yard and as per the

consumption of the material in the plant, the petitioner could not dump material in

a single go and the material was dumped every alternate day as per the

requirement; that the respondents have issued the impugned cancellation letter

dated 02.02.2023 for cancellation of contract and the ground taken in the said

letter was that the material was not supplied by the petitioner since 24.12.2022,

due to which the progress of the project had been stalled.

5. It is further contended that aggrieved of the cancellation letter dated

02.02.2023 issued by the respondent No. 3, the petitioner invoked the jurisdiction

of this Court under Section 9 of the Arbitration and Conciliation Act for seeking

interim relief by way of filing Arb P No. 05/2023 and this Court vide order dated

27.02.2023 passed the interim direction, whereby the respondents have been

restrained from invoking the risk and cost retendering option with respect to the

contract work against the petitioner. It is further contended that vide letter dated

12.07.2023, the petitioner requested the respondents to refer all the claims to the

Arbitrator at an earliest, however, the respondents are acting as mute spectator and

have not referred the claims before the Arbitrator till date

6. In the above backdrop, the petitioner approached this Court by preferring

the present petition seeking appointment of an independent arbitrator under

Section 11 of Arbitration and Conciliation Act, 1996 read with clause 23 of

Special Conditions of Contract and clause 37 of General Conditions of Contract

(IAFW-1815Z) in pursuance to tender no. CDR 35 TF/04/2021-22 to settle the

disputes arising between the parties.

7. Mr. Vishal Sharma, learned DSGI has resisted this petition by way of

filing detailed objections and perusal of the same would show that a dispute exists

between the parties.

8. The fact that the petitioner has raised certain claims which, according to

the petitioner, have not been addressed by the respondents, this Court is of the

view that a dispute exists between the parties, which would require resolution in

accordance with the aforementioned Clause 23 of Special Conditions of Contract

and Clause 37 of General Conditions of Contract and this court is of the view that

the dispute has to be ultimately decided by an Arbitrator.

9. Accordingly, the present petition is disposed of by appointing Maj.

General K. Gajria (Retd.), 11-K/51, Lajpat Nagar-2, New Delhi-110 024 to act

as the sole Arbitrator, who shall proceed in the matter to decide the dispute

between the parties and make an award in accordance with law after hearing the

parties and charging the prescribed fee along with incidental expenses, as per

applicable guidelines and rules, to be shared by the parties.

10. Parties may raise their claims and counter claims before the Arbitrator.

11. Registry to inform the learned Arbitrator accordingly.

12. With the above observation and direction, the petition stands disposed of.

                                                                      )            (Tashi Rabstan)
                                                                                    Chief Justice
           Jammu:
           13.02.2025
           Pawan Angotra
                                       Whether the order is speaking? : Yes/No
                                       Whether the order is reportable? : Yes/No

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter