Tuesday, 19, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Pooja Devi Wd/O Sh. Sandeep Kumar vs State Of J&K Through Principal Chief
2024 Latest Caselaw 2164 j&K

Citation : 2024 Latest Caselaw 2164 j&K
Judgement Date : 21 October, 2024

Jammu & Kashmir High Court

Pooja Devi Wd/O Sh. Sandeep Kumar vs State Of J&K Through Principal Chief on 21 October, 2024

Author: Moksha Khajuria Kazmi

Bench: Moksha Khajuria Kazmi

  -1-        OWP No.439/2018 C/w OWP No.53/2018




        HIGH COURT OF JAMMU & KASHMIR AND LADAKH
                        AT JAMMU

                                                    Reserved on: 10.10.2024
                                                    Pronounced on: 21.10.2024
Case: OWP No. 439/2018 &
      OWP No. 53/2018

      1. Pooja Devi Wd/o Sh. Sandeep Kumar
      2. Miss Divya Devi D/o Late Sh. Sandeep
         Kumar.
      3. Master Divam (Minor) S/o Late Sh.
         Sandeep Kumar.                                               .....Petitioner(s)

Through :-                        Mr. R K Gupta, Sr. Advocate with
                                  Ms. Ishna Vaid, Advocate.

                               v/s

      1. State of J&K through Principal Chief                        .....Respondent(s)
         Conservator of Forests, Van Bhawan,
         Gulab Singh Marg, Jammu.
      2. Conservator of Forest, Chenab Circle,
         Doda.
      3. Divisional Forest Officer, Batote Forest
         Division, Batote.
      4. Chief Conservator of Forest, Project
         Cordinator, CAMPA, Van Bhawan,
         Gulab Singh Marg, Jammu.

Through :-                        Mr. Amit Gupta AAG

CORAM: HON'BLE MS. JUSTICE MOKSHA KHAJURIA KAZMI, JUDGE

                                        ORDER

01. These petitions were initially filed by the then sole Proprietor of the

firm M/s Sandeep Kumar- Government Contractor, who died on 15-09-

2021. In terms of order dated 09.11.2021 passed by this Court in an

application (CM No. 8330/2021), his legal heirs were impleaded as

petitioners in these petitions.

-2- OWP No.439/2018 C/w OWP No.53/2018

02. Petitioners by way of OWP No. 53/2018 have challenged order No.

3826-33/BFD dated 31.12.2017, issued by respondent No. 3, whereby the

said respondent, i.e., Divisional Forest Officer, Batote Forest Division,

Batote, has recommended cancellation of contract of 'Construction of

Chain Link Fencing at compartment 9/Btt; 10a/Btt and 10b/Btt., Patnitop

area Batote Range, Forest Division Batote' in pursuance to e-NIT no. 01 of

2017 dated 29.05.2017. Petitioner has also challenged by way of OWP No.

439/2018 order bearing no. CAMPA order no. 284/Forest dated 09.02.2018

issued by respondent no. 4 i.e. Chief Conservator of Forest, Project

Coordinator, CAMPA, whereby the tender allotted to the petitioner in terms

of e-NIT No. 01 of 2017 dated 29.05.2017, for Construction of Chain Link

Fencing at compartment 9/Btt; 10a/Btt and 10b/Btt., Patnitop area Batote

Range, Forest Division Batote has been cancelled.

02. Since the issues in both the petitions are same, the parties are also the

same, as such, these petitions are taken up for hearing analogously and are

being disposed of by this common judgment.

Factual Matrix

03. The Government o f Jammu and Kashmir through the Divisional

Forest Officer, Forest Division Batote issued e-NIT No: 01 of 2017 dated

29.05.2017, for construction of Chain Link Fence at Compartment, C O -

9t, 10A, 10B/ Patnitop area, Batote Range Forest Division Batote. The

bid was opened on 12.06.2017. The time for completion of the project

was fixed as four months. In response to the NIT, the petitioner offered

-3- OWP No.439/2018 C/w OWP No.53/2018

to execute the Contract on the terms and conditions referred in the NIT

through its bid. The bid of the petitioner which were complete in all

respects along with CDR of ₹ 3.25 lacs as earnest money was also

deposited.

04. It is stated that the petitioner firm was informed vide letter dated

15.07.2017 that the rates offered by the petitioner-firm are below 25.57 of

the estimated /advertised cost, therefore, he was required to furnish 5%

additional amount as security. Accordingly, the petitioner firm deposited

CDR amounting to ₹ 8,13,000/- pledged in favour of DFO Batote. After

submission of Additional CDR, the petitioner was waiting for the approval

and allotment of the contract by the higher authorities, the petitioner firm

received a notice No. 2744-49/BFD dated 03.10.2017, issued by respondent

no.3 where by petitioner firm was informed that the allotment of the work

order in respect of the contract work in question has been issued by the

Office of the Principal Chief, Conservator of Forest vide order passed on

06.09.2017.

05. It is stated that the petitioner had no knowledge about the approval

granted to the petitioner firm vide letter dated 06.09.2017 and for the first

time it was communicated by the respondent no.3 vide letter dated

03.10.2017. The DFO, Batote desired the petitioner firm to start the work

immediately as the area of contract work was falling in the snow zone

which has very limited working period. The petitioner firm as such

responded to the notice and made clear that no such formal allotment order

has been issued by any higher authorities and Departmental approval cannot

-4- OWP No.439/2018 C/w OWP No.53/2018

substitute as a formal allotment order. Moreover, it was stated that the

working season in the snow bound area is between Apr-May to September-

Oct and the contract can be executed only when the next working period

resumes.

06. Finally, the allotment order was awarded in favour of the petitioner

firm by the respondent no.2 i.e. Conservator of Forest, Chenab Circle, Doda

vide Order F.O.24/CAMPA/CFC/2017-18 dated 08.11.2017. It is stated that

as per the directions contained in the allotment order dated 08.11.2017, the

petitioner firm attended the office of DFO, Batote along with requisite

documents for drawing up an agreement but the petitioner firm was

informed that the format of the agreement was not available and as such was

asked to commence the work immediately without the formal execution of

the agreement. Since the winter season had already commenced and the

working season had ended, as such it was impossible to execute the work in

the extreme cold climatic conditions.

07. It has been further stated that respondent no.3 issued several notices

in the month of November and December, 2017, thereby directing the

petitioner firm to execute the work, knowing well that the same was not

possible in the snow bound areas where the site of work is situated. The

respondent no. 3 issued notice dated 16.12.2017, whereby the petitioner

firm was directed to execute the agreement and in the event of failure, he

would recommend to the higher authorities for cancellation of contract and

forfeiture of earnest money deposit and additional security deposited with

the Department.

-5- OWP No.439/2018 C/w OWP No.53/2018

08. The aforesaid notice was appropriately replied by the petitioner firm

vide its letter dated 22.12.2017 but the same was not considered.

Respondent no.3 issued impugned communication No. 3826-33 / BFD dated

31.12.2017, thereby recommending cancellation of the contract work and

re-tendering of the contract work in question. Respondent no. 3 forfeited the

earnest money (EMD) deposited by the petitioner firm and also the

additional security amount deposited to the department in the shape of CDR

pledged in favour of Divisional Forest Officer.

09. Being aggrieved of the action of the respondent No.3 in terms of

communication No. 3826-33/ BFD dated 31.12.2017, the petitioner

challenged the same by way of filing the writ petition being OWP No. 53 of

2018, before this Court, This Court, in terms of order dated 19.01.2018, had

directed the respondents not to encash the earnest money and additional

security furnished by the petitioner from the concerned bank in response to

e-NIT No. 01 of 2017.

10. Respondent no.4 vide impugned order being CAMPA Order No.

284/Forest dated 09.02.2018 cancelled the tender which had been allotted to

the petitioner in terms of e-NIT No. 01 of 2017. Thereafter, respondent no.3

issued a short term tender notice being e-NIT No. 10 of 2017-18 dated

02.03.2018, for inviting fresh tenders for the execution of the same contract

work which had been allotted to the petitioner in terms of e-NIT No. 01 of

2017.

-6- OWP No.439/2018 C/w OWP No.53/2018

11. Petitioner-firm herein has challenged action of the respondents for

recommending and consequently cancelling the contract which was allotted

to him in terms of e-NIT No. 01 of 2017. He has also challenged forfeiture

of earnest money deposit and additional security deposited with the

Department on the ground that respondent no.3 Divisional Forest Officer,

Batote directed petitioner firm to commence the work even before the

issuance of formal allotment order by the competent authority and drawing

up of the agreement, which is absolutely unlawful and no party can force the

other contracting party to execute the work before a contract is duly allotted

and a formal contract agreement is entered into between the parties.

Moreover the petitioner was not communicated regarding the approval

accorded by the higher authorities and it came to his knowledge only after

receipt of notice dated 03.10.2017, whereas the approval was granted by

respondent No.1 on 06.09.2017.

12. The allotment Order came to be issued in terms of order No.F.O.

24/CAMPA/CFC/2017 -18 dated 08.11.2017, as such department took four

months to issue formal allotment order in favour of petitioner firm and by

that time the working season had already ended in the snow bound area, as

such, petitioner-firm could not commence the work in the non-working

season.

13. It is also stated that it is evident from order dated 06.09.2017 that it

was forwarded to the petitioner vide dispatch No. 2531/BFD dated

19.09.2017, and respondent no.3 had received the said order in his office on

22.09.2017 vide receipt No. 3375. It is an admitted case between the parties

-7- OWP No.439/2018 C/w OWP No.53/2018

that the period of four months had to commence from the date of the

allotment order/ drawing up of an agreement and by the time the order of

allotment came to be issued on 08.11.2017, severe winter season had

already commenced in which no work could be executed. He has also stated

that fresh tender was issued in the month of March, 2018, by that time even

the petitioner firm could have executed the work allotted to him in the

month of April onwards.

14. Per contra, reply stands filed on behalf of the respondent no. 3, it is

stated that the petitioner did not take any step for execution of the allotted

work after receiving the letter of allotment and reminder notices issued to

start the execution of contract work within stipulated period.

15. The fencing work of both Patnitop Sanasar road falling in Comptt.

10c/Btt, 11/Btt. 17/Btt. and village Korthri to Padora falling in Comptt.

9/Btt, 10a/Btt and 10b/Btt, was e-tendered and allotted to Sh. Abdul Latief

Natnoo and Sh. Sandeep Kumar Contractor (Husband of the petitioner) vide

CAMPA order No: 166/Forests dated 06.09.2017 and CAMPA order no.

67/Forests dated 06.09.2017. The work in Comptt. 10c/Btt, 11/Btt and

17/Btt was taken up by Sh. Ab. Latief Natnoo, who completed the same

within stipulated time, whereas Sh. Sandeep Kumar contractor (husband of

the petitioner No.1) did not start the work and preferred to file the instant

petition stating that the climatic conditions do not suit for execution of the

work.

-8- OWP No.439/2018 C/w OWP No.53/2018

16. It is stated that the petitioner firm was not willful to execute the work

allotted to him. He did not even pay any heed to attend the office of

respondent no.3 in execution of the agreement. There is complete breach of

agreement on the part of the petitioner. Accordingly, the case of the

petitioner -firm was considered and he was found as defaulter. The action

under Clause 11 of the tender documents of e-NIT of 2017 dated 29.05.2017

stands taken vide order No. 3826-33/BFD dated 31.12.2017 wherein the

contract allotted in favour of the petitioner-firm was recommended for

cancellation and re-tendering of the approved work and the amount of

earnest money along with additional security amount deposited in shape of

CDRs pledged to DFO Batote, stood forfeited in the best interest of the

Government to penalize the contractor who failed to comply with the terms

and conditions, to execute the work and complete the contract.

Consequently, the allotment of work order issued in favour of the contractor

was cancelled vide CAMPA order No: 284/Forests dated. 09.02.2018 and

work was executed through lowest bidder (Ll) in response to re tendering of

the approved work vide E NIT No. 10/2017 dated 02.03.2018.

17. It is submitted that the petitioner did not participate in the retendering

process and the bid of the lowest bidder was considered and work has

already been executed by him. It is also submitted that formal agreement

was never executed with the petitioner as he never bothered to appear before

the respondent no.3. He has falsely tried to implicate respondent no.3

thereby stating that the agreement was not drawn between the parties

because of the delay on the part of respondents.

-9- OWP No.439/2018 C/w OWP No.53/2018

Submissions made by learned counsel for the petitioner

18. Mr. R K Gupta, learned Senior counsel for the petitioner, has stated

that during the pendency of the instant petitions, husband of the petitioner

no.1, Mr. Sandeep Kumar has died and the petitioners herein have no source

of income. In terms of impugned order dated 31.12.2017, respondent no.3-

Divisional Forest Officer had recommended to respondent no.2-

Conservator of Forest for cancellation of the allotment made in favour of the

petitioner and also sought re-tendering of the approved work but he has

forfeited the earnest money (EMD) and 5% of additional amount deposited

by the contractor in the shape of CDR pledged in the name of respondent

no.3, without seeking any approval by the competent authority. Mr. Gupta

has relied upon the judgment passed by the Supreme Court reported as

Joshi Technologies International Inc. v. Union of India and others,

(2015) 7 SCC 728. He has stated that, though, the petitioner had not prayed

for the release of the earnest money (EMD) and 5% of additional amount

deposited by the contractor in the shape of CDR but this Court has power to

cull out the prayer from prayer no. (e) which is residual in nature.

Observations of the Supreme Court in para 51 of Joshi Technologies (supra)

are reproduced hereunder:-

"51. Mr. Ganesh, however, submitted that such a prayer should be culled out from prayer no. (iii) which is residual in nature. Ordinarily, it would be difficult to read into this prayer clause a relief of substantive nature of issuing the writ of mandamus. However, we find that there are specific averments to this effect in the body of the writ petition as well as in the grounds. More pertinently this

-10- OWP No.439/2018 C/w OWP No.53/2018

relief was specifically pressed and argued in the High Court which was even entertained by the High Court without any objections from the respondent to the contrary. Therefore, we are inclined to examine the plea on merits, though reluctantly."

Submissions made by learned counsel for the respondents

19. Mr. Amit Gupta, learned counsel for the respondent, has stated that

respondent no.3 in terms of Government order No. 233-F of 2012 dated

12.10.2012 is the competent authority to forfeit the said amount. It is

further stated that the fresh tenders were retendered in the month of March,

2018 after cancellation of the tender allotted to the petitioner on 09.02.2018.

The same stands executed, as such, no cause of the petitioners survives in

terms of the prayer made in the instant petitions.

20. Heard learned counsel appearing for the parties, considered their

submissions and perused the material available on record.

21. In order to appreciate the challenge which is being raised by the

petitioners, it would be pertinent to extract the relevant Clause of the e-

bidding process which was set out in the short term tender Notice E-NIT

No.10 of 2017 dated 02.03.2018.

"11. Default: In the event of failure on the part of contractor to achieve the required periodical progress or complete the contract in time, the Department shall without prejudice to the remedies available to the Government under any law for the time being in force, be competent to adopt all or any of the following courses.

 Rescind the contract for which rescission notice of 10 days in writing to the contractor shall be conclusive evidence and in which case the

-11- OWP No.439/2018 C/w OWP No.53/2018

security deposit and CDR of the contractor shall be forfeited and be at the disposal of the Department and OR  Employ labour and supply materials to carry out works or any part of the work debiting the contractor with cost of the labour and the price of the material. Certificate of the Incharge Engineer/Range Officer in respect of the coast (cost) of the material and wages of labour shall be final and conclusive against the contractor.

 Measure up the work executed by the contractor and to take such part thereof as shall be unexecuted out of his hand and get the same executed/completed through alternate means/agency/contractor, at the risk and cost of the original contractor.

 Impose and recover such penalty as may be determined by the Incharge Engineer/Range Officer in addition to the forfeiture of security deposit.  In the event of any of the above courses being adopted by the Department, the contractor shall have no claim to compensation for any loss sustained by him for reasons of his having purchased or procured any material/equipment, or entered into agreement or paid any advance on account of or with a view to the execution of the work. In case the contract is rescinded under aforesaid provisions the contractor shall not be entitled to be paid any sum for any work actually performed by him under this contract.

In any case, in which the powers conferred upon the Conservator of Forests, Chenab Circle, Doda/ In charge Engineer, by any clause under this notice shall have become exercisable, the on exercise thereof shall not constitute waiver of any of the conditions.

In the event of the Department putting in force any of the powers vested in it under the preceding clauses, it may, if so desired, take possession or order to take possession of any materials, tools, plants, stores, etc lying in or upon the works or the site thereof, belonging to the contractor or procured by him and intended to be used for the execution of the work or any part thereof. The Department may choose to remove them at the contractor's expenses or sell them by auction or private sale and debit the amount towards contractor penalty. The certificate of the Incharge Engineer/ Range Officer in respect expenses incurred or the amount debit-able to the contractor on account of any such sale shall be final, conclusive and binding on the contractor."

-12- OWP No.439/2018 C/w OWP No.53/2018

22. From Clause 11 (supra) it becomes clear that for invoking the

provisions of Clause 11, there has to be failure on the part of the contractor

to complete the contract within the time prescribed in terms of the contract

made between the parties. It is admitted by the parties that no formal

agreement was even signed by the parties till passing of the impugned order

dated 09.02.2018.

23. This court on 18-10-2022 passed an order as under, which reads as under:-

"1. Learned senior counsel appearing for the petitioner submits that the contractor- husband of the petitioner had died and the said contractor had deposited two FDRs with the department. However, no agreement was executed between the parties yet there was an allotment with regard to the execution of the work, which was later on again allotted to some other contractor.

2. Learned counsel for the petitioner submits that deceased contractor has left behind his widow and two children, who have no source of income. He further submits that department may sympathetically consider the request for settlement by releasing the amount of FDRs, which is only source of survival of the petitioner.

3. Learned counsel for the respondents submits that he has already taken the matter with the department for the settlement of this issue. He also submits that he will seek instructions in the matter and report on the next date of hearing. He further submits that he will take necessary steps for the settlement of the matter within two weeks."

24. Respondent no.3, in terms of order dated 18-10-22, supra, after

considering the claim of the petitioner firm, vide order no. 416 5-68/BRO,

22-11-2022, rejected the claim for the release of the security amount/EMD

to the tune of ₹3.25 lakhs and additional security in the shape of CDR to the

tune of ₹8, 13, 000/- lying with the respondents, without taking any

sympathetic view.

-13- OWP No.439/2018 C/w OWP No.53/2018

25. The respondent no.3 has rejected the claim of the petitioner firm on

the same grounds as have been taken in the reply filed by the respondent

no.3 in both writ petitions. Nowhere he has been able to substantiate as to

what authority he had to impose penalty on the petitioner for forfeiture of

the security amount and the EMD deposited by the petitioner firm without

seeking prior approval from respondent no.2 conservator of forest, Chenab

circle Doda, who as per clause 11 is the sole authority to take any action in

case of default on the part of the contractor.

26. The allotment order was issued in favour of the petitioner firm by

respondent No.2 i.e. Conservator of Forest Chenab Circle, Doda on

08.11.2017, whereas acceptance letter of the bid was issued on 15.07.2017.

The department took four months to issue formal allotment order.

Respondent No.3 issued first notice on 16.12.2017, which was appropriately

replied by the petitioner (deceased) on 22.12.2017. Thereafter, respondent

No.3 issued impugned communication dated 31.12.2017, thereby

recommending to respondent No.2 for cancellation of contract and re-

tendering of the contract work. The respondent No.3 sought approval from

respondent No.2 for rescinding the contract duly approved and allotted in

favour of petitioner firm but without asking for any approval from

respondent No.2, forfeited the earnest money deposited (EMD) and the

additional security amount deposited by the petitioner firm in the shape of

CDR pledged in favour of respondent No.3.

27. If Respondent no.3 had no authority to approve the rescission of

contract in terms of clause 11 of e - NIT 01 of 2017, then respondent no.3

-14- OWP No.439/2018 C/w OWP No.53/2018

also had no authority for forfeiture of EMD and additional security

deposited by the petitioner firm, on his own, without seeking prior approval

from the competent authority i.e. Respondent no.2. As such penalty of

forfeiture of EMD and additional security deposited by the petitioner firm

imposed by an incompetent authority i.e. respondent No.3 is nullity the eyes

of law.

28. Viewed on the aforesaid pedestal this Court finds itself unable to

uphold the action of respondent no.3. Not only he has failed to seek prior

approval of the competent authority i.e. Conservator of Forest-respondent

no.2, which would constitute a breach, he has also fundamentally failed to

justify its action as being warranted under law. Respondent no.3, had no

authority to unjustly enrich itself based on the preconceived or assumed

power to forfeit security deposit and earnest money deposited by the

petitioner firm. The facts obtaining here constrain this Court to hold that the

action of forfeiture was clearly unjustified. This court thus has no hesitation

in recording that the action taken by respondent no.3, without any

competency is also manifestly arbitrary, thus, cannot be sustained.

29. Since the work which was allotted to the petitioner firm, has already

been executed by some other contractor, after being retendered by the

respondents as such learned counsel for the petitioners has made a very

limited prayer only for release of the security deposit/EMD amounting to

Rs. 3.25 lakhs and ₹8, 13, 000/-as additional security deposit, it comes out

to the total amount of ₹11,38, 000/-, on the ground that the husband of the

petitioner No.1, who was the contractor, had died in the year 2021, during

-15- OWP No.439/2018 C/w OWP No.53/2018

the pendency of these petitions and is survived by his widow and children

who need this money for survival. Though, this prayer has not been made in

the writ petition but the relief can be culled out from the prayer No.(e)

which is residual in nature.

30. Accordingly, and for all the aforesaid reasons, these petitions are

allowed. Impugned order dated 31-12-2017, is quashed to the extent of

forfeiture of Earnest Money (EMD) and 5% Additional amount deposited

by the contractor in the shape of CDRs/FDRs pledged to Divisional Forest

Officer, Batote, issued by respondent no.3. Respondents are directed to

release the Earnest Money Deposit to the tune of ₹3.25 lakhs and additional

security deposit to the tune of ₹8, 13, 000/-, total amount of ₹11, 38, 000/-,

lying with the respondents, in favour of the petitioners within a period of

two months from the date of passing of this order.

31. Disposed of.

(MOKSHA KHAJURIA KAZMI) JUDGE Jammu 21.10.2024 Sunita/PS Whether order is reportable: Yes

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter