Citation : 2023 Latest Caselaw 620 j&K/2
Judgement Date : 19 May, 2023
HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT SRINAGAR
WP(C) No. 940/2021
CM No. 3012/2021
Reserved on : 07.04.2023
Pronounced on: 19.05.2023
Abdul Salam Ganaie .... Petitioner/Appellant(s)
Through:- Mr. Rizwan Ul Zaman, Advocate.
V/s
U.T of J&K and others .....Respondent(s)
Through:- Mr. Faheem Nisar Shah, G.A vice
Mr. Ilyas Nazir Laway, G.A.
CORAM: HON'BLE MRS. JUSTICE SINDHU SHARMA, JUDGE
JUDGMENT
01. The petitioner is a registered A-Class Contractor, he after
participating in the tendering process of works for restoration of
damages caused by the flash floods of September 2014 to the road from
Asnoor to Raiwattan (Package No. JK01-81) vide order No.
EE/PMGSY/KUL/2288 dated 30.10.2014 and restoration of damages
caused by the said flash floods to the road from H.M. Guri to C.S. Rather
(Package No. JK01-196) vide order No. EE/PMGSY/KUL/2234-35
dated 25.10.2014. Both these allotment of works were for an amount of
Rs. 14,90,000/-. The respondent No. 3, after the physical verification of
the works executed by the petitioner, prepared a work done estimate for
an amount of Rs. 14,90,000/-.
02. These works were executed by the petitioner as per the terms and
conditions of the allotment order within the prescribed time period. The
petitioner after completion of entire process of verification submitted his
bills for payment of Rs. 14,90,000/-. The execution of works and the
amount of Rs. 14,90,000/- due to the petitioner is not disputed. The
contention of the petitioner is that, despite the respondents admitting
their liability, the same has not been paid to the petitioner till date
despite repeated representations.
03. The grievance of the petitioner is that after successful execution of
all the works allotted to him to the satisfaction of the respondents but the
respondents, despite admitting the same have not released the payment
due to him till date. The petitioner, thus, seeks a direction to the
respondents to release the admitted amount of Rs. 14,90,000/- due, along
with interest from the date of completion of execution of the works.
04. In their objections, the respondents have admitted that the works of
restoration of the road from Asnoor to Raiwattan and the road from H.M.
Guri to C.S. Rather were allotted to the petitioner vide order Nos.
EE/PMGSY/KUL/2288 dated 30.10.2014 and EE/PMGSY/KUL/2234-35
dated 25.10.2014. The physical verification of the works was also
undertaken by a committee constituted for the same, and the copy of the
same has also been placed on record.
05. It is further submitted by the respondents that they had demanded
funds from the District Development Commissioner, Kulgam, vide letter
Nos. E/PMGSY/DB/8750/52 dated 14.11.2018 and
PW(R&B)/Plan/FDR-517/2014 dated 01.08.2018, to enable them to
settle the pending claims of the petitioner. However, no funds have been
released till date under the proper head, i.e., SDRF. They, however,
submit that as and when the funds are available, the same will be
released in favour of the petitioner.
06. Admittedly, the petitioner executed the works allotted to him and
physical verification of the same was also undertaken by the Committee,
but despite admitting their liability, the payment has not been released in
favour of the petitioner only on the ground, that funds are not available
with them. This cannot be a ground to withhold the payment to the
petitioner for the works executed by him.
07. The petitioner, having successfully completed the works and also
also not been guilty of breach of contract, he cannot be denied payment
only on the ground that the funds are not available. The respondents,
having tendered and allotted works subsequently, cannot deny the
payment only on the ground of the non-availability of funds, therefore,
resiling from their obligation.
08. In "M/s Surya Construction Vs. State of U.P. in Civil Appeal
No. 2610/2010 dated 02.05.2010" it was held that it is well settled, even
in the realm of contract, this Court can interfere under Article 226 of the
Constitution of India as held in "ABL International Ltd. and Another
vs. Export Credit Guarantee Corporation of India Ltd. and Others
(2004 (3) SCC 553)". The State while entering into contract or
agreement with private individuals has to act in just, fair and reasonable
manner. The contractual obligations of the State coexist with the
constitutional obligations. The works being completed long back and
there being no dispute on amount and payment being admitted by the
respondents, same cannot be denied when the work stands executed.
09. In this case, the liability is admitted by the respondents, as such,
they are under obligation to pay the amount due to the petitioner for
execution of the works. The respondents, after allotment and execution
of work, cannot shirk away from payment of admitted liability on the
ground that no funds are available with them.
10. The contractor participates in tendering process and executes work
with Government on the assurance that after completion of the same, he
would be paid the amount due to him without any delay and cannot be
denied payment on the ground that funds are not available. The
petitioner is, thus, held entitled to payment of amount due to him for
execution of works.
11. In view of the aforesaid reasons, this petition is allowed. The
respondents are directed to release a payment of Rs. 14,90,000/- in
favour of the petitioner on account of works executed by him within a
period of six weeks from the date, a copy of this order is made available
and if the payment is not made within the aforesaid period, the petitioner
will also be held entitled to an interest @ 6% from the date the payment
was due till it is realized.
12. Disposed of accordingly.
(Sindhu Sharma) Judge
Srinagar:
19.05.2023
Michal Sharma
Whether the judgment is speaking : Yes/No
Whether the judgment is reportable : Yes/No
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!