Citation : 2022 Latest Caselaw 862 j&K
Judgement Date : 27 May, 2022
HIGH COURT OF JAMMU AND KASHMIR AND LADAKH
AT JAMMU
Reserved on : 21.05.2022
Pronounced on 27.05.2022
WP(C) No. 35/2022(O&M)
Amanat Ali .....Appellant(s)/Petitioner(s)
Through: Mr. Rohan Nanda, Advocate
vs
UT of J&K and Ors. ..... Respondent(s)
Through: Mr. KDS Kotwal, Dy.AG
Coram: HON'BLE MR. JUSTICE RAJNESH OSWAL, JUDGE
JUDGMENT
1. The petitioner has filed the instant petition for quashing the
communication No. FD-BDGT0D-3/17/2021-03-FINANCE
DEPARTMENT dated 22.12.2021 issued by the office of respondent
Nos. 1 to 4 and also for issuance of a direction to the respondents to
release the payment of the work executed by the petitioner.
2. The petitioner claims to have executed the following works:
(a) Construction of road along with drain, culvert and nallah from
link road Kote Purkhoo road to Mahhalla Ramdssain at village
Kalakam (by way of earth work premixing) Part-I
(b) Construction of road along with drain, culvert and nallah from
link road Kote Purkhoo road to Mahhalla Ramdssain at village
Kalakam (by way of earth work premixing) part-II.
3. It is stated that the respondent No. 2 vide communication dated
08.07.2019 conveyed the approval of execution of aforesaid works. It
was also stated that the funds for the purpose shall be provided at the
time of revised estimate 2019-2020 after completion of all codal
formalities. The respondent No. 4 vide communication dated
31.07.2019 authorised the respondent No. 5 to execute the work. The
respondent No. 5 vide communication dated 14.08.2019 authorised the
respondent No. 6 to execute the work. The respondent No. 6 further
authorised the Secretary Panchayat, Kot Upper vide two
communications each dated 05.09.2019 to take up the execution of
works through facilitators to be selected by Gram Sabha concerned,
who shall arrange the labourers at the work site. The work was
completed by the petitioner and the physical verification of the said
works was conducted on 14.03.2020 by the Additional Development
Commissioner, Jammu. After the verification was conducted, the
Additional Development Commissioner, Jammu forwarded a
communication dated 16.03.2020 to the respondent No. 4 to release the
payment as per quantity executed and authenticated by executing
agency. The respondent No. 4 requested the respondent No. 1 to
release the funds vide communication dated 16.03.2020. The
respondent No. 1 vide communication dated 08.03.2021 conveyed the
respondent No. 4 the authorization for release of funds for the work
done by the petitioner. The respondent No. 4 vide order dated
18.03.2021 accorded the sanction to the "accord of administrative
approval" and release of funds in favour of the respondent No. 5 for its
release/utilization for the works done by the petitioner. The respondent
No. 5 vide order dated 19.03.2021 accorded the sanction to the "accord
of administrative approval" and release of funds and placed the funds at
the disposal of respondent No. 6. The respondent No. 6 sought
clarification from the respondent No. 5 regarding release of funds for
the work done by the petitioner vide communication dated 22.03.2021.
4. The respondent No. 5 vide communication dated 22.03.2021 stated that
the tendering process in the Rural Development Department started
vide Government order dated 04.10.2019, whereas the work has been
executed by the petitioner before the tender process was adopted. The
respondent No. 5 vide communication dated 22.03.2021 also sought
clarification from respondent No. 4 in the matter and also intimated the
respondent No. 4 that these works were authorised much before the
tendering process adopted by Rural Development Department and has
requested for exemption of e-tendering, so that the past liabilities of the
executed works are cleared during the current financial year. The
respondent No. 4 vide communication dated 24.03.2021 to respondent
No. 1 stated that the office of respondent No. 1 vide communication
dated 08.03.2021 has authorised for clearing the work done liability
with the conditions among others that the work should have been
initiated with due e-tendering process and AAA/TS be in placed and it
was also intimated that the works were authorised prior to issuance of
order dated 04.10.2019.
5. The respondent No. 1 vide communication dated 22.12.2021 asked the
respondent No. 4 to furnish details whether the works done by the
petitioner were undertaken after following due tendering process. The
petitioner has impugned the said order on the ground that works were
executed by the petitioner much before implementation of the tendering
system in the Rural Development Department and the respondent No. 1
has issued the impugned communication despite the fact that the
respondent No. 4 vide its communication dated 24.03.2021 has
categorically requested the respondent No. 1 to grant one time
exemption for the condition of e-tendering because when the petitioner
started the executing works, the e-tendering system was not
implemented in the Rural Development Department.
6. Response stands filed by the respondents, in which it is stated that the
Finance Department vide No. DP-7/Jammu 2018-19/PS-901 dated
08.07.2021 and DP-7/Jammu 2018/PS-2011 dated 02.08.2019
authorised the four works to the District Development Commissioner,
Jammu for its execution. The funds for the said works were released to
the District Development Commissioner, Jammu with the condition to
follow e-tendering procedure. In response, the Block Development
Officer approached the Assistant Commissioner Development, Jammu
and apprised that at the time these works were executed, there was no
tendering system in the department. It was also intimated that
tendering system was introduced vide G. O. No. 267 RD&PR of 2019
dated 04.10.2019. The District Development Commissioner, Jammu
approached the Finance Department and apprised the same facts to the
Finance Department. At last, the Finance Department had asked District
Development Commissioner, Jammu to furnish details whether the
works were taken after following due tendering process, to which the
District Development Commissioner, Jammu replied that the works in
question were taken up as per GFR and due codal formalities, such as
AAA and TS were fulfilled except tendering for execution of works.
These works were authorised for execution in the month of July and
August, 2019 as per the authorization conveyed by the Finance
Department vide orders dated 08.07.2021 and 02.08.2019, whereas the
tendering process was adopted by the Development Department from
the month of October, 2019 pursuant to order dated 01.10.2019. It has
also been stated that the physical verification of these work was also
conducted and verification report was also submitted to the Finance
Department.
7. Mr. Rohan Nanda, learned counsel for the petitioner vehemently argued
that at the time when the works were authorised for execution, the e-
tendering process was not in operation and it was in the month of
October 2019 when a direction was issued for tendering of the works.
8. On the other hand, Mr. K. D.S. Kotwal, learned Dy. AG argued that the
present petition is not maintainable, as such, the same deserves to be
dismissed.
9. Heard learned counsel for the parties and perused the record.
10. From the record, it is evident that the petitioner was allotted the above
mentioned works. He has successfully completed the same. The
respondents have admitted in their response that the physical
verification of these works has already been undertaken. The only plea,
on the basis of which the payment is being denied, is that the tenders
were not floated for the said works. It is evident that the works were
authorised prior to the order dated 04.10.2019 when the Rural
Development Department and Panchayati Raj ordered that all the
development works with an estimated cost of Rs. 3.00 lacs shall be put
to tenders before execution. So far as instant case is concerned, it is
evident from the communication dated 24.03.2021 addressed by the
District Development Commissioner i.e. respondent No. 4 to the
respondent No. 1 that the works were authorised for execution much
before the tendering process was adopted by the Rural Development
Department.
11. In view of the stand taken by the respondent No. 4, the respondent No.
1 should not have issued the impugned communication dated
22.12.2021. The impugned communication dated 22.12.2021 has been
issued oblivious to the communication dated 24.03.2021 issued by the
respondent No. 4 i.e. District Development Commissioner, Jammu, as
such, the same is not sustainable in the eyes of law being arbitrary in
nature.
12. Viewed thus, the petition succeeds and the communication No. FD-
BDGT0D-3/17/2021-03-FINANCE DEPARTMENT dated 22.12.2021
issued by Accounts Officer (Bgt.) Finance Department, is hereby
quashed. The respondents shall make the admitted payment to the
petitioner within a period of three months from the date a copy of this
order is made available to the respondents, failing which the
respondents shall pay interest @ 6% per annum from the date of filing
of this petition.
(Rajnesh Oswal) Judge JAMMU 27.05.2022 Karam Chand Whether the order is speaking: Yes/No Whether the order is reportable: Yes/No
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!