Citation : 2022 Latest Caselaw 844 j&K
Judgement Date : 25 May, 2022
Sr. No. 2
HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT JAMMU
(Through Virtual Mode Srinagar)
WP(C) No. 1372/2021
CM No. 5556/2021
in
WP(C) No. 2005/2021
CM Nos. 7439/2021 & 7440/2021
Ghulam Mustafa Batt .....Appellant(s)/Petitioner(s)
Through: Mr. K. S. Johal, Sr. Advocate with
Mr. Supreet Singh Johal, Advocate &
Mr. Karman Singh Johal, Advocate
in WP(C) No. 1372/2021
Mr. M. A. Goni, Sr. Advocate with
Mr. S. Tanzeel Illahi, Advocate
in WP(C) No. 2005/2021
Vs
Union Territory of J&K and others ..... Respondent(s)
Through: Mr. D. C. Raina, Advocate General with
Mr. K. D. S. Kotwal, Dy. AG for R-1 to 6.
Mr. Sunil Sethi, Sr. Advocate with
Mr. Navyug Sethi, Advocate for R-7.
Coram: HON'BLE MR. JUSTICE PUNEET GUPTA, JUDGE
JUDGMENT
01. The petitioner is aggrieved of the participation and acceptance of the
technical bid of the private respondent No.7 and subsequently also of acceptance
of the final bid of the private respondent in pursuance to e-NIT No.3 of 2021-
22/East dated 09.06.2021 and therefore preferred two Writ Petitions- one after
acceptance of technical bid of the respondents and the other after the final bid of
the petitioner was accepted by the respondents. The challenge in the two
petitions by the petitioner is more or less on the similar grounds and that is why
both the petitions are taken up for consideration together by this Court.
02. The basic claim put forth by the petitioner for all practical parties in
both the petitions is that the private respondent was not eligible to bid in the
tender as he did not fulfill the terms and conditions of the e-NIT and the relevant
Clauses of the Regulations. The respondent was not eligible to participate in the
tender notice because of his being not eligible as Class A Contractor. The grant
of Class A Contractor certificate and the other certificates issued in favour of the
respondents is illegal as the same were issued in order to make him eligible for
participation in the tender.
03. The objections stand filed in both the writ petitions by the official
respondents as well as the private respondent No.7. Indeed, the respondents have
denied the allegations made in both the petitions of arbitrariness and alleged
illegality committed by the official respondents. The private respondent was
eligible to participate in the tender and the respondent No.7 being the lowest
tenderer his bid was accepted is the crux of the stand taken by the respondents.
The certificate issued in favour of the respondent No.7 is as per Rules and no
arbitrariness is to be found in the manner certificates/documents are issued to the
respondents is the stand taken in the objection.
04. It may be suffice to mention herein that the both sides have placed on
record the documents which are more or less not in dispute. In fact the petitioner
has mainly relied upon the documents placed on file by the private respondent
and has raised the arguments on the strength of the documents placed by the
respondents.
05. The learned counsels appearing for both the sides have raised
extensive arguments in support of their respective pleas taken in the pleadings.
The same shall be referred as per the discussion which is to be made by the
court. The written arguments have been filed by the petitioner wherein the
petitioner has reiterated pleas taken in the writ petition.
06. The key argument raised by the petitioner against the respondents is
that in order to be eligible for participation in the tender, the tenderer has to be
Class A Contractor and that in order to be Class A Contractor certain conditions
are required to be fulfilled. The reference is made to Clause 4 of J&K State
Forest Corporation Registration of Contractors and their Conduct Regulations,
2014 (hereinafter accord the Regulations). The respondent did not fulfill the
criteria as laid down in Clause 4 of the Regulations and therefore was not
eligible to participate in the tender.
07. M/S K. S. Johal and M. A. Goni, learned senior counsels appearing on
behalf of the petitioner have tried to convince the court that the very basic
acceptance of the technical bid of the respondent No.7 by the respondents was
flawed one as the certificate Class A Contractor issued in favour of the private
respondent could not be issued for want of compliance of the requisite
formalities.
08. Learned Advocate General and Mr. Sunil Sethi, learned senior counsel
have argued that the petitioner has raised disputed questions of fact and the
court is debarred from determining the issued raised in the present writ petition.
The official respondents after following procedure and taking into consideration
all the facts issued the certificates to the respondent No.7 and found him entitled
for participation in the tender.
09. The respondents have submitted that the reliance is mainly placed by
the petitioner on the documents which are placed on record by the private
respondent and that the petitioner has not brought any record of his own to
substantiate his pleas. The court is not an agreement with the argument of
learned counsel for the respondents and particularly the learned senior counsel
appearing for the private respondent as the court is not barred from looking into
the documents which are placed on record by the private respondent. The
documents on the record are sufficient or not to adjudicate upon on the pleas
raised by the petitioner is a different question.
10. The learned senior counsel appearing for the petitioner has referred to
the documents in order to substantiate the argument that the documents
explicitly make out that the respondent No.7 did not fulfill the criteria for grant
of Class A Contractor certificate as on the date of issuance of e-NIT or even
when the tender was finally opened. The reference is made to the documents
issued by the Chief General Manager of the respondents department vide
No.654-59/GM/SFC/ECD dated 31.05.2017, wherein the private respondent was
allowed to work out the markings to the tune of Rs. 40 lacs. cft (RV) equal to
(=) 0.02 lacs cft (SV) in compartment No.84/Udil on Amani basis. Another
communication dated 14.07.2018 issued by the General Manager to the
Divisional Manager Ext., J&K SFC Division Kisthwar West (annexure-13) in
the Writ Petition No.1372/2021 mentions for extension of time for completion
of work of left over volume in compartment 84/Udil so that the whole volume
can be extracted and hauled down jointly upto sale depot Jammu by ending
March 2019. Similarly, the order dated 05.07.2021 (annexure-14 of the writ
petition) states of further concession granted to the private respondent so far as
the completion of the work. The payment was also withheld of the work done by
the private respondent is also stated on behalf of the petitioner. The aforesaid
position did not make the respondent eligible to get Class A Certificate
Contractor is the contention of the petitioner. The respondent failed to complete
the allotted work as required as Class B Contractor and the work which was
done by the respondent was only on Amani basis and therefore the respondent
was not even entitled to be classified as Class A Contractor. The respondents
have contended that Class A Certificate has been issued by the respondents after
scrutiny and taking into consideration all the relevant material. The class A
certificate has been issued in favour of the respondent No.7 on 26.06.2021. The
perusal of the file reveals that the respondents have also placed on record the
certificate bearing No.18/SIGDI dated 15.06.2021 issued by Range Manager and
counter signed by Divisional Manager, Forest Corporation, wherein it is
certified that Jaffer Hussain Wani has completed the allotted works in
compartment 84/Udil and compartment 67-C/Udil. In the order No.389-
91/GM/FDC/ECD dated 13.07.2021 from General Manager (Ext) East Circle,
Doda the actual overturn as against projected overturn has been regularized.
11. The emphasis is laid on behalf of the petitioner on Clause 4 of the
regulations wherein conditions have been laid down for eligibility to qualify as
Class A Contractor. The certificate of Class B certificate of the respondent has
been renewed as per certificate dated 11.06.2021 issued by General Manager.
The documents on file and which have been referred to by the petitioner may not
be sufficient themselves to accept the contentions of the petitioner. The class A
certificate has been issued in favour of the respondent No.7 and the presumption
is that the same has been issued after the respondents were satisfied with regard
to eligibility of the respondent No.7 in terms of the Regulations. It is not for the
court in the Writ Petition to determine the eligibility of the respondent No.7 as
class A contractor. The said respondent had done the work on Amani basis only
and the documents mentioned above do not certify that the respondent has
completed the work as required by the Regulations is the aspect which cannot be
finally determined by the Writ Court. The concession, if any, given by the
respondents with regard to the work done by the respondent No.7 justifies for
his being classified as Class A Contractor or that there were other sufficient
reasons to grant concession to the respondent is again the matter which is
required to be seen by the official respondents. The court cannot normally
substitute its own satisfaction for the satisfaction which is arrived at by the
concerned authority before issuing the certificate. The respondents if have taken
some decision the same cannot be questioned unless there is apparent
arbitrariness exercised by the authority. It is trite proposition of law that where
administrative action has been taken by the official and in order to determine its
validity the evidence may be required to be produced by parties and the matter is
required to be trashed after assessing the evidence the challenge to such action
of the official cannot be thrown in the writ petition. The court is not to interpret
the satisfaction of the official respondents in a particular way. The petitioner
cannot seek relief of invalidating the certificate No.78 Class A issued by the
Chief General Manager Forest Department vide dated 26.06.2021 on the
aforesaid ground. The respondent while referring to letter bearing
No.1029/GM/SFC/ECD dated 11.09.2019 issued by General Manager SFC East
Circle Doda, has argued that in fact the petitioner had himself failed to complete
certain works allotted to him and therefore cannot raise finger against the private
respondent qua his eligibility as Class A Contractor. The court is not required to
determine the impact of this communication/letter as the same is not germane to
the issue raised in the present petition.
12. As stated above Clause 4 of the Regulations refers to the conditions to
be fulfilled before the contractor can be classified as class A contractor. Five
conditions have been mentioned in the same. It may be noted herein that except
for condition (V) of Clause 4 which relates to the completion of minimum work
as Class B contractor, the petitioner has not specifically challenged the other
conditions of Clause 4 in the writ petition. However, the learned counsels for
the petitioner have referred to the documents on the file to substantiate their
claim that the respondent No.7 did not fulfill those criteria also which could
make him eligible as Class A Contractor. One of the conditions laid in the
Regulations 4 is that the contractor should have immovable property worth not
less than Rs.75 lakhs free from all encumbrances and to be certified by an
officer not below the rank of Assistant Commissioner, Revenue. The private
respondent has placed on record certificate from the Deputy Commissioner,
Kisthwar bearing No.DCK/SQ/232/2021-22 dated 18.06.21. It is mentioned in
the certificate that the respondent has property valuation of Rs.75 lakhs. The
learned counsel for the petitioner has vehemently argued that the certificate does
not fulfill the criteria and the same is evident from the certificate itself though
the other side has contested the claim of the petitioner that the respondent failed
to fulfill the criteria as required under the Regulations and submits that the
certificate does not either indicate that the property is mortgaged me. The other
condition as envisaged under Clause 4 is that the contractor should have
minimum balance of Rs. 25 laks or more during past six months, the contractor
has furnished a fixed deposit certificate of Rs.1.00 lakh from any of the
scheduled bank pledged to the Managing Director, J&K SFC. None of the
conditions is met by virtue of the documents which are placed on record is
submitted on behalf of the petitioner. The Solvency Certificate dated from the
J&K Bank, Chatroo, speaks of the bank providing secured overdraft facility of
10% to the petitioner to meet their work requirement, if any, contract is to be
allotted to the respondents. The two FDRs dated 20.01.2016 & 16.06.2021
amounting to Rs.1.00 lakh and another certificate from the J&K Bank, Chatroo
dated 19.04.2021 mentions of the balance amount of more than Rs.25 lacs. in
the Saving Account of the respondent as on 18.04.2021are also placed on
record. The argument raised on behalf of the petitioner is that aforesaid
documents do not reflect that they were in force as on date when the tender was
issued is met by the counsel for the private respondent with the argument that
the documents do not necessarily show that their validity had expired on the
crucial date. The court is of the view that in case the official respondents have
relied upon on the aforesaid documents the same must have been done by them
after satisfying that the respondents did possess the aforesaid amount before
issuing the certificate. It is not expected that the respondents who are to issue the
necessary certificate which requires fulfillment of certain conditions will issue
the same without adhering to the formalities which were required to be complied
with as per the Regulations. It is for the petitioner to bring by positive evidence
that the respondent had not that much of amount with him as reflected in the
documents as on date when the certificate was issued in favour of the
respondent.
13. Last but not the least, the petitioner has tried to highlight the issue of
non-availability of the No Objection Certificate (NOC) from the CID
Department as required in terms of Clause 5 of the Regulations and has referred
to the certificate which is issued by Senior Superintending Police, District
Kisthwar vide dated 20.06.2021 to the effect that there is nothing
adverse/incriminating against respondent-Jaffer Hussain Wani. No doubt the
certificate does not mention of the verification from CID, however, the
petitioner has not produced any documents on record that the concerned agency
did not issuance any such certificate in favour of the respondent. It is for the
petitioner to place on record with positive evidence that the respondent was not
having all the criteria which was required to be fulfilled before he could be
issued the Class A Certificate or lacked qualification in pursuance to the tender
issued by the respondent. The petitioner cannot base all his claim mainly on the
strength of the documents which are placed on file by the private respondent.
The deficiency if any occurring in the formalities required to be fulfilled can be
condoned is for the authorities to take all on the same and not for the court to
normally fathom the same. The assessment and the satisfaction of the authorities
cannot be scrutinized by the court very minutely.
14. Admittedly, disputed questions of fact have been raised in the writ
petition which may even require evidence. The court in exercise of its writ
jurisdiction cannot determine the disputed questions of fact.
15. The court cannot normally interfere into the tender and the terms and
conditions which are incorporated in the tender and required to be fulfilled
unless the same appear to be manifestly arbitrary and against public policy.
16. The learned counsels for the parties have relied upon the judgments in
support of their contentions. The petitioner has referred to '2017 0 Supreme SC
1185 titled M/S Sam Built Well Pvt. Limited Vs. Deepak Builders and others',
wherein on facts the Hon'ble Apex Court set aside the judgment of the Division
Bench of the High Court on the ground that the Division Bench had not stated
that the three experts committees had arrived at perverse conclusion and that the
matter which is required to be considered by the technical experts should be left
to those technical experts. The court also took note of the judgment of
Montecarlo Limited Vs. NTPC Limited reported in (2016) 15 SSC 272, and
Afcons Infrastructure Limited Vs. Nagpur Metro Rail Corporation Limited and
another reported in (2016) 16 SCC 818. The court had held that the bidder's
expertise, technical capability and capacity is to be assessed by the experts and
further exercised of judicial review would be invoked if the approach is
arbitrary or mala fide or procedure adopted is meant to favour one. The decision
making process should clearly show that said maladies are kept at bay.
17. In Caretel InfoTech Limited Vs. Hindustan Petroleum Corporation
Limited and others, in SLP No.48 of 2019 decided on 9 th April, 2019, the apex
court took note of the earlier decisions and held that the court should not give
interpretation to the contracts and more particularly to the tender terms at the
behest of the third party competing for the tender rather than what is propounded
by the party framing the tender.
18. In celebrated case of Tata Cellular Vs. Union of India reported in
1994 0 Supreme SC 697, the apex court held that it cannot be denied with the
principles of judicial review would apply to the exercise of contractual powers
by government bodies in order to prevent arbitrariness or favoritism. However,
it must be clearly stated that there are inherent limitations in exercise of that
power of judicial review. It was further held that the judicial review is concerned
with reviewing not the merits of the decision in support of which the application
for judicial review is made but the decision making process.
19. In SLP (Civil) No. 2013 of 2022 case titled M/S N.G. Projects Limited
Vs. M/S Vinod Kumar Jain and others decided on 21st March, 2022 it was held
by the Supreme Court that the satisfaction as to whether a bidder satisfies the
tender condition is primarily upon the authority inviting the bids and that such
authority is aware of expectations from the tenderers while evaluating the
consequences of non performance. It was further held that on same set of facts,
different conclusions can be arrived at in a bona-fide manner by the Technical
Evaluation Committee, the court should refrain itself from imposing its decision
over the decision of the employer as to whether or not accept the bid of a tender.
It was also held that the approach of court should not be to find fault with
magnifying glass in its hands, rather the court should examine as to whether the
decision making process is after complying with the procedure contemplated by
the tender conditions. Further, it was held if the court finds that there is total
arbitrariness or the tender has been granted in a mala fide manner still the court
should refrain from interfering in the grant of tender but relegate the parties to
seek damages for the wrongful claim rather than to inject the execution of the
contract. There can be no dispute with what has been held by the Apex court of
the country in aforesaid judgments. The petitioner has also submitted that nature
of work to be carried out as per tender did not require any special skill or
expertise. The court cannot act as evaluator of the terms and conditions which
are to be acted upon.
20. The learned counsel for the petitioner has vehemently argued that the
manner in which Class A Certificate has been issued by the respondents in
favour of the petitioner manifestly speaks of mala fide on the part of the official
respondents. It is submitted that the respondent No.7 applied for issuance of the
certificate on 19.06.2021 after issuance of tender and the certificate was issued
on 26.06.2021. The counsels appearing for the respondents have denied that any
favoritism was shown to the respondent in this respect. All has been done as per
the rules and regulations and the petitioner has not been able to make out any
arbitrariness or unjustified action on part of the official respondents. Merely
because the certificate has been issued within a short period to the respondent
No.7 of his being class A contractor after the tender was issued by itself does not
present the picture of arbitrariness and therefore no interference by the court on
aforesaid plea of the petitioner. The court cannot substitute the satisfaction of
the authority with its own or on the minimum period which the authority should
take to process the case of the party.
21. The basis of both the petitions is the alleged non fulfillment of the
conditions which are required to be fulfilled to gain qualification as Class A
Contractor and consequently the participation of the petitioner in the tender.
Whereas the first petition challenges the certificate issued by the respondents of
Class A certificate and the decision taken by the respondents in accepting the
technical bid, the second petition in addition to the aforesaid also seeks
quashment of work order issued for compartments 31-AB/Keshwan and 35-
D/Keshwan and the agreements executed in pursuance to the acceptance of
tender of the respondent No.7 and that the respondent be prohibited from
entering the compartments and not to carry the work allotted to the petitioner.
22. As the court has held that the disputed questions of fact have been
raised by the petitioner the same cannot be determined in the present case. The
official respondents committed flaw while granting Class A Contractor
certificate in favour of the respondent No.7 is not otherwise prima facie made
out by the petitioner on the strength of the documents on which the petitioner
has relied upon and moreso when other evidence may be required to be
produced so as to consider the claim set up by the petitioner in the petitions. It
may be pertinent to mention herein that the petitioner has not challenged the
decision of awarding of the works to the petitioner in pursuance to the tender on
the basis that the respondent No.7 was not lowest tender or the official
respondents had otherwise faulted in awarding the tender at the time of taking
final decision on the tender.
23. In view of what has been discussed above both the petitions are liable
to dismissed and are accordingly dismissed. The petitioner is however at liberty
to avail any other remedy which he may have under law. Copy of the judgment
shall be placed on both the files.
(Puneet Gupta) Judge
Jammu 25.05.2022 Shammi
Whether the order is speaking: Yes Whether the order is reportable: Yes
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!