Citation : 2022 Latest Caselaw 747 j&K
Judgement Date : 9 May, 2022
HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT JAMMU
Reserved on : 26.04.2022
Pronounced on: 09.05.2022
WP(C) No. 2410/2021(O&M)
c/w
WP(C) No. 2896/2021(O&M)
WP(C) No. 267/2022(O&M)
WP(C) No. 610/2022(O&M)
WP(C) No. 713/2022(O&M)
M/s New Jhelum Construction .....Appellant(s)/Petitioner(s)
Company
Through: Mr. M. K. Bhardwaj, Sr. Advocate with
Mr. Gagan Deep Sharma, Advocate and
Mr. Gagan Kohli, Advocate.
vs
Union of India and others ..... Respondent(s)
Through: Mr. Vishal Sharma, ASGI
Coram: HON'BLE MR. JUSTICE RAJNESH OSWAL, JUDGE
JUDGEMENT
1. On joint request, all the petitions were taken up together for final
disposal/consideration.
2. The petitioner claims to have executed number of contracts both for the
Government of Jammu and Kashmir as well as for Border Road
organisation (hereinafter BRO), over a period of time. The petitioner has
mentioned various contracts executed by the petitioner for the Government
of Jammu and Kashmir, as also for the Border Road Organisation. It is
along with connected matters
stated that the tenders No. CE(P) DPK-10 of 2019-20, dated 29.11.2019,
and CE(P) DPK-11 of 2019-20, dated 29.11.2019, came to be floated by the
respondents and the petitioner being eligible on all counts participated
therein by submitting its tenders and in respect of certain plant/machineries
as to its availability, tax invoices were obtained from concerned agencies
for procurement of plant and machinery to be utilised for execution of
work, in case of allotment of contract. The requirement of the said
documents arose on account of condition No. 6.3.1 of tender document,
however, the said tenders of the petitioner were not accepted, regarding
which suitable action came to be taken by the petitioner firm. This,
however, did not find favour with the authorities, as is evident from the
communication dated 27.01.2020, wherein the rejection of the tender has
been held to be valid. The petitioner realizing that inadvertently some
documents have been uploaded which were not relevant so far as tenders in
question were concerned, accordingly informed the respondents vide
communication dated 05.02.2020, that the petitioner no longer intends to
participate in the tender that may be deemed to have been closed together
with the withdrawal of the writ petitions filed by the petitioner before the
High Court of Himachal Pradesh at Shimla, apprehending rejection of the
tenders. Since the respondents were asking for uploading of the deficient
documents and not accepting the documents submitted by the petitioner,
vide communication dated 19.05.2021 and 07.06.2021, the petitioner
informed the respondents that similar documents in respect of other bidders
have been taken into consideration. Yet vide communication dated
along with connected matters
05.06.2021, these documents and reasons for placing reliance thereupon
were not accepted by the respondents and appeal was rejected on this
ground. As the respondents were adopting partisan role in respect of
acceptance of bids, the petitioner was constrained to file a complaint before
the Chief Vigilance Officer, vide communication dated 17.06.2021, which
came to be confirmed by the petitioner in terms of communication dated
16.08.2021. It is also stated that it appeared to be a turning point in the
entire case as respondents, in particular respondent No. 4 took it as personal
issue and vide communication dated 16.08.2021, issued a show cause
notice calling upon the petitioner why action be not taken against him for
submitting the forged/fake documents. This communication came to be
issued only after the petitioner approached the office of Chief Vigilance
Officer against biased role of the respondents in scrutiny of the tender bids.
The said show cause notice came to be replied by the petitioner vide reply
dated 13.09.2021 and 17.09.2021. However, without appreciating facts in
correct perspective and only as a vendetta, order impugned dated
18.10.2021 came to be issued by the respondents whereby a severe penalty
of banning the petitioner for a period of 18 months in participating the bids,
came to be issued.
3. The petitioner being aggrieved of the order dated 18.10.2021 (hereinafter to
be referred as the order impugned) by virtue of which the petitioner has
been barred for a period of 18 months from participating in any tender from
the date of issuance of this order, has filed the present petition thereby
challenging the order impugned on the following grounds:
along with connected matters
(i) That the order impugned is actuated with malice on behalf of the
respondents and particularly respondent No. 4 as the same was issued only
when the petitioner approached the vigilance officer for looking into the
matter, raising serious issues against the conduct of the respondents.
(ii) That on no occasion, any fake or forged documents were placed on record
or uploaded and therefore very edifice of the action of the respondents is
demolished. The petitioner had placed on record bill invoices of plant and
machinery required for the execution of the work to be purchased after
allotment of work and on realization that these documents are not favouring
the requirement of the tender, the petitioner showed his inability and
reluctance to participate in the said tender which was deemed withdrawn.
(iii) That the order impugned has not been passed by the competent authority
i.e. the Principal /Owner in terms of integrity agreement forming part of the
tender.
(iv) That the integrity agreement has lived its life being valid only for a period
of six months, therefore, no action in terms thereof could have been taken
against the petitioner.
(v) That the action is highly disproportionate as no benefit has been drawn so
the respondents have no justification in passing the order impugned.
4. The petitioner has placed on record the tender documents, the order
impugned, the NITs, integrity agreement, the show cause notices and also
the replies submitted by the petitioner as well as the other communications.
5. The response stands filed by the respondents in which it has been stated that
the writ petition is not maintainable as the petitioner is guilty of submission
along with connected matters
of false affidavit dated 06.12.2019, along with technical bid claiming
ownership of critical equipment and thereafter, knowing fully well about
the same to be based on false facts, submitted fake and forged documents to
substantiate its claim for securing a contract for financial gain. The
petitioner has committed the breach of trust as reposed in every Enlisted
Contractor registered with the respondents. It is stated that two tenders as
mentioned above were floated and as the work required to be executed
under the said tenders was of strategic nature and was to be executed in a
hilly and difficult terrain, thus the contractor submitting tender was required
to own critical equipment for being technically qualified, entitling it for
opening of the financial bid. The said critical equipment have been
mentioned in clause 6.3.1, in which the description of
equipments/plant/vehicle has been mentioned as HMP min 40-60 TPH,
Stone Crusher-cum-screening plant (min 40 TPH), WMM Plant (04
Bin Type) Dumper/Tipper min (8-10 Cum capacity), Motor Grader,
Mechanical paver, Tandam Vibratory Roller (8-10 Capacity), Static
Roller, Soil Compacter. The petitioner substantiated his claim with regard
to ownership of critical equipment by filing an affidavit dated 06.12.2019,
along with the technical bids. On careful scrutiny by the Technical
Evaluation Committee, the technical bids of the petitioner were found
deficient, as required documents were not uploaded by the petitioner,
therefore, vide communication dated 30.12.2019, the petitioner was
intimated about the shortfall of the documents, so as to afford an
opportunity to the petitioner to remove the deficiencies, so that the bids
along with connected matters
submitted by the petitioner may be considered. In response to the letter
dated 30.12.2019, the petitioner vide letter dated 02.01.2020, uploaded its
reply along with the Tax invoice No. 13/2018-19, dated 20.05.2019,
allegedly issued by M/s Meghal Road Equipments, regarding purchase of
HMP-60 THP and Bill No. KVEW/341/14, dated 15.05.2017, regarding
purchase of Soil Compacter on the portal meant for uploading the requisite
documents. The said reply along with the documents was opened on
07.01.2020. On scrutiny of the documents, the Technical Evaluation
Committee entertained doubt about the authenticity of the said bills of
purchase of equipments uploaded by the petitioner. In order to clarify the
doubt, letter dated 07.01.2020, was sent by the Technical Evaluation
Committe to the vendor of said tax invoices, submitted by the petitioner,
alleged to have been issued by the M/s Meghal Road Equipment. In
response to the same, M/s Meghal Road Equipment, vide its letter dated
07.01.2020, categorically stated that the Bill No. 13/2018-19 dated
20.05.2019, has not been issued by M/s Meghal Road Equipment and the
said bill is fake. The said fact was supported by actual tax invoice No. 13,
dated 19.05.2019, along with the connected E-way Bill and Bilti, which
were sent to the respondents through e-mail and the said bill actually was
reported to have been issued to the firm namely R. P. Infrastructure Pvt.
Ltd. situated at Agra (U.P) and not to the petitioner. The above said
manufacturer also sent a letter dated 07.01.2020, duly certifying that as per
their record Bill No. 30/2019-20, along with the above mentioned
supporting documents was issued to the M/s R. P. Infrastructure Pvt. Ltd.
along with connected matters
Similarly a letter was sent to M/s KV Engineering Works to verify the
authenticity of the Bill No. KVEW 341/14, dated 15.05.2017. In response
to the same, said M/s KV Engineering Works intimated vide letter dated
08.02.2020, that the said bill has not been issued by them. The said
communication was supported by an affidavit dated 05.02.2020. Although
the verification letter dated 08.02.2020 was received subsequently, but the
petitioner kept silence with regard to forgery of the said documents.
Consequent upon receipt of the above mentioned letters and documents, the
Technical Evaluation Committee prepared assessment sheet and
recommended rejection of the technical bids of the petitioner on the ground
that the above mentioned Bill No. 13 submitted by the petitioner is fake and
fabricated and the said recommendation was uploaded on the CPP Portal on
08.01.2020. In the meanwhile, the petitioner sent reply through E-mail
dated 06.01.2020, which was never uploaded on CPP Portal as required
under Clause 6.2.3 of the tender documents, but the same was downloaded
on 09.01.2020,i.e. after the receipt of appeal to the Next Higher
Engineering Authority dated 08.01.2020, and representation dated
09.01.2020. Due to appeal and representation by the petitioner against the
rejection of the technical bid, the scheduled time of opening of the Q-Bid
was postponed and the T-Bid of the tender in question was again put up to
the Evaluation Committee for further decision. The meeting of the
Technical Evaluation Committee was again convened on 10.01.2020, and
the additional documents submitted by the petitioner through e-mail dated
06.01.2020, were also scrutinized. On scrutiny of the documents submitted
along with connected matters
by the petitioner, it was held by the Technical Evaluation Committee that
the said bills were not meeting the requirement, besides were neither self-
attested nor attested by the Gazetted Officer/Public Notary. The petitioner
has neither submitted the plant wise details mentioning the capacity nor a
bill for an assembled plant as whole equipment. The lose parts in the bill do
not specify any capacity and the capacity of the plant so built through these
parts cannot be said to be of the required capacity as per the tender, i.e. 40-
60 TPH. In the said meeting of the Technical Evaluation Committee, the
submissions made by the petitioner in appeal dated 08.01.2020, were also
taken into consideration and it was held that the Bill No. 13, as mentioned
hereinabove, was certified to be fake by the manufacturer firm and the
contention of the petitioner that there is some clerical mistake in the same is
not tenable. The petitioner failed to submit any document to prove that Bill
No. 13, as reported was not fake or forged, but tried to mislead the
authorities by submitting other bills of lose parts and plant. Thus the
technical bid of the petitioner was rejected by the Technical Evaluation
Committee as the petitioner tried to mislead the authorities by submitting
fake and forged documents. The rejection of the technical bid of the
petitioner was challenged by the petitioner by filing a writ petition before
the High Court of Himachal Pradesh wherein serious baseless allegations
were levelled by the petitioner against the senior functionaries of
respondent department. A prayer of the petitioner for grant of interim relief
was rejected and thereafter respondents also filed objections to the said writ
petition. The petitioner finding itself unable to justify the illegality, opted
along with connected matters
for withdrawal of the said writ petition. All the facts and circumstances and
conduct of the petitioner were brought to the notice of the Enlisting
Authority i.e. Director General, Border Roads Organisation, for intimation
of appropriate action for submitting false/ fake/forged documents vide letter
dated 12.05.2020.Due to spread of Covid 19 Pandemic, the said matter
could not be taken up by the competent authority, as during that period only
urgent work requiring immediate attention could be attended to and on
normalisation of the situation, the said matter was taken up for
consideration by the competent authority and show cause notice dated
16.08.2021, was served upon the petitioner. It is also stated that initiation of
action against the petitioner vide show cause notice dated 16.08.2021, has
no relevance to the alleged act of submission of complaint, claimed to have
been submitted by the petitioner with the Chief Vigilance Officer.The
detailed reply was submitted by the petitioner, wherein the factum of the
Tax invoice submitted by the petitioner to be fake and forged was not
denied but was claimed to have been submitted by mistake, however, no
explanation with regard to Bill No. KVEW 341/14 dated 15.05.2017, being
fake/forged was submitted by the petitioner, which makes it clear that
firstly a false affidavit was submitted and subsequently to substantiate the
claim made in the affidavit, fake/forged documents were submitted.
6. Thereafter, taking into consideration clause 2(d) and 3(a) of the integrity
agreement and conditions of Enlistment Criteria particularly Para 14 of the
Application for Enlistment submitted by the petitioner, the order impugned
along with connected matters
was passed by the competent authority, after affording reasonable
opportunity of being heard to the petitioner to defend itself.
7. Mr. M. K. Bhardwaj, learned senior counsel appearing on behalf of the
petitioner vehemently argued that the order impugned is actuated with
malice and for one and a half year, no action was taken by the respondents
and it was only when the petitioner confirmed his complaint with the Chief
Vigilance Officer on 16.08.2021, show cause notice was issued to the
petitioner. He further argued that the respondents had no jurisdiction to pass
the order impugned from the date of issuance of the said order and rather it
should have been from the date when the tender of the petitioner was
rejected. He further argued that order impugned has not been passed by the
competent authority. Mr. M. K. Bhardwaj, learned senior counsel has
placed reliance upon a judgment reported in 2004 (1) S.L.J 1.
8. Per Contra, Mr. Vishal Sharma, learned ASGI vehemently argued that the
petitioner is guilty of submitting forged documents for the purpose of
obtaining the contract for the works regarding which tenders were floated
by the respondents. He further argued that order impugned has been passed
after affording due opportunity of being heard to the petitioner and the
same has been passed by the competent authority in terms of clause 2(d)
and 3(a) of the integrity agreement and as per Para 14 of the Application of
the Enlistment as contractor. He also submitted that the approval order
dated 10.08.2017 also vests with the respondents the right of not to issue
the tender form in any particular case and also to suspend, remove or
blacklist the petitioner's name from the BRO list of contractors in the event
along with connected matters
of submission of non-bona fide tenders or other delinquency. He further
argued that merely a complaint was confirmed on 16.08.2021 and the show
cause notice was issued on same date, would not mean that the proceedings
were initiated with malice, particularly when there was admission on the
part of the petitioner that wrong documents were furnished by the
petitioner. He further laid stress that the action could not be taken against
the petitioner for a period of one and half year because of the Covid 19
Pandemic and it was only when the situation was normalised, the
proceedings were initiated and the order impugned was passed. He also
urged that the respondents have taken lenient view by debarring the
petitioner for 18 months, as the petitioner could have been barred forever.
9. Heard learned counsel for the parties and perused the record.
10. Before appreciating rival arguments of the parties, it is apt to mention here
that while exercising the power of judicial review, thereby examining the
validity of the order of blacklisting/debarring the contractor from
participating in future contracts, the court is required to consider as to
whether opportunity of being afforded has been afforded before the
issuance the order of "Blacklisting or Debarring", further whether there is
arbitrariness in the said decision and lastly the proportionality. If the order
of blacklisting/debarring qualifies the above tests, then there is no scope for
interference with the said order as the court is not supposed to act as court
of appeal while examining the validity of the said order. Apex Court in
Kulja Industries Ltd. v. Western Telecom Project BSNL, reported in
(2014) 14 SCC 731 has held as under:
along with connected matters
"16. A literal construction of the provisions of Paras 31 and 32 extracted above would mean that the power to disqualify or blacklist a supplier is available to the purchaser only in the three situations enumerated in Paras 31 and 32 and no other. Any such interpretation would, however, give rise to anomalous results. We say so because in cases where a supplier is found guilty of much graver offences, failures or violations, resulting in much heavier losses and greater detriment to the purchasers in terms of money, reputation or prejudice to public interest may go unpunished simply because all such acts of fraud, misrepresentation or the like have not been specifically enumerated as grounds for blacklisting of the supplier in Paras 31 and 32 of the tender document. That could in our opinion never be the true intention of the purchaser when it stipulated Paras 31 and 32 as conditions of the tender document by which the purchaser has reserved to itself the right to disqualify or blacklist bidders for breach or violation committed by them. If the bidders who commit a breach of a lesser degree could be punished by an order of blacklisting there is no reason why a breach of a more serious nature should go unpunished, be ignored or rendered inconsequential by reason only of an omission of such breach or violation in the text of Paras 31 and 32 of the tender document. Paras 31 and 32 cannot, in that view, be said to be exhaustive; nor is the power to blacklist limited to situations mentioned therein.
17. That apart, the power to blacklist a contractor whether the contract be for supply of material or equipment or for the execution of any other work whatsoever is in our opinion inherent in the party allotting the contract. There is no need for any such power being specifically conferred by statute or reserved by contractor. That is because "blacklisting" simply signifies a business decision by which the party affected by the breach decides not to enter into any contractual relationship with the party committing the breach. Between two private parties the right to take any such decision is absolute and untrammelled by any constraints whatsoever. The freedom to contract or not to contract is unqualified in the case of private parties. But any such decision is subject to judicial review when the same is taken by the State or any of its instrumentalities. This implies that any such decision will be open to scrutiny not only on the touchstone of the principles of natural justice but also on the doctrine of proportionality. A fair hearing to the party being blacklisted thus becomes an essential precondition for a proper exercise of the power and a valid order of blacklisting made pursuant thereto. The order itself being reasonable, fair and proportionate to the gravity of the offence is similarly examinable by a writ court.
25. Suffice it to say that "debarment" is recognized and often used as an effective method for disciplining deviant suppliers/contractors who may have committed acts of omission and commission or frauds including misrepresentations, falsification of records and other breaches of the regulations under which such contracts were allotted. What is notable is that the "debarment" is never permanent and the period of debarment would invariably depend upon the nature of the offence committed by the erring contractor."
11. From the record, it is evident that proper opportunity of being heard was
afforded to the petitioner and there has been no violation of principle of
along with connected matters
natural justice by the respondents and being so, no such ground was either
taken in the writ petition or urged by the learned senior counsel for the
petitioner while advancing his arguments.
12. The first contention raised by the petitioner is that the proceedings were
initiated with malice, as the respondents were adopting partisan attitude that
necessitated the petitioner to file complaint with the Vigilance Officer
against the respondents on 17.06.2021 and confirm on 16.08.2021. It is also
contended that the no forged/fake document was submitted by the
petitioner. From the record, it is evident that there is admission on the part
of the petitioner that show cause notice was issued to him on 16.08.2021. A
perusal of the notice dated 16.08.2021, reveals that the petitioner was asked
to show cause for submission of forged documents. Another show cause
notice dated 06.09.2021,with reference to the notice dated 16.08.2021, was
also served upon the petitioner and the same has been admitted by the
petitioner. The petitioner has replied to the said show cause notices vide
replies dated 13.09.2021 and 17.09.2021 that the said documents were
submitted by the petitioner's firm due to clerical error/mistake. The
petitioner also made reference to his communication dated 05.02.2020. A
perusal of the communication dated 05.02.2020 of the petitioner reveals
that the petitioner had stated that due to clerical error/mistake, unsuitable
documents were submitted by his firm against the tenders and he further
submitted that the matter may please be treated as over/closed as no further
claim or objection stands from his end regarding the subject matter.
along with connected matters
13. It is relevant to reproduce Para G and H of the reply dated 13.09.2021 to the
show cause notices issued to the petitioner and the same are reproduced
here under:
"(G) It is hereby further submitted that false/fake documents were uploaded by one of my staff member and when the same came to our notice, the staff member responsible for the same was immediately terminated from his services.
(H) Moreover, our bid submitted against tender No. CE (P) HMK/13/2019-20 and CE (P) HMK-02/2020-21 were neither admitted nor evaluated due to Negative WLR. Hence, the false/fake documents uploaded mistakenly were neither evaluated nor admitted and thus no benefit from the submitted documents has been taken by my firm which might have caused damages to the department."
14. Thus, there is admission on the part of the petitioner that the false/fake
documents were uploaded though mistakenly. The fact that the documents
were submitted by the petitioner were fake, is also borne from the
communication dated 07.01.2020, issued by the M/s Meghal Road
Equipment and the communication dated 08.02.2020, issued by the M/s
KV Engineering Works. Both these communications clearly state that the
documents alleged to have been issued by both of them were in fact not
issued by them and the said documents were fake. The respondents as such,
had ample material on record, regarding submission of the fake/forged
documents and it cannot be said that the respondents have initiated
proceedings and have passed the order impugned with malice as merely
issuance of show cause notice dated 16.08.2021, the date on which the
petitioner too confirmed his compliant with Vigilance Officer would not
mean that the proceedings were actuated with malice. Otherwise also, how
could the respondents know that on 16.08.2021, when the show cause
along with connected matters
notice was issued to the petitioner, the petitioner has also confirmed his
complaint on the same date. Thus, there is no force in the said contention of
the petitioner and the same is rejected.
15. The other contentions of the petitioner are inter-related and as such are
taken up together. Mr. M. K. Bhardwaj, learned senior counsel appearing
for the petitioner vehemently argued that even if the petitioner was required
to be banned for a period of 18 months, then the same should have been
from the date of rejection of the tender. The petitioner has admitted the
execution of integrity agreement and has placed on record the same. The
clause 2(d) and 3(a) are reproduced here under:
"2(d) The bidder(s)/Contractor(s) will not, directly or through any other person or firm indulge in fraudulent practice means a wilful misrepresentation or omission of facts or Submission of fake/forged documents in order to induce public official to act in reliance thereof, with the purpose of obtaining unjust advantage by or causing damage to justified interest of others and/or to influence the procurement process to the detriment of the Government interests.
3(a) If the Bidder(s)/contractor(s), either before award or during execution of contract has committed a transgression through a violation of Para 2 above or in any other form, such as to put his reliability in question, the Principal/Owner after giving 14 days notice to the contractor shall have powers to disqualify the Bidder(s)/Contractor(s) from the Tender process or terminate/determine the Contract, if already executed or exclude the Bidder/Contractor from future contract award processes. The imposition and duration of the exclusion will be determined by the severity of transgression and determined by the Principle/Owner. Such exclusion may be forever or for a limited period as decided by the Principal/Owner."
16. Further Para 14 of the Application of enlistment as contractor duly signed
by the petitioner is also relevant and the same is reproduced here under:
"14. We understand and agree that the appropriate Border Roads Authority has the right as he may decide not to issue tender forms in any particular case and also to ban suspend remove downgrade or blacklist our name from BRO list of
along with connected matters
contractors in the event of our submission of non bonafide tenders or for technical or other delinquency in regard to which the decision of the appropriate BRO authority shall be final and conclusive."
17. From cumulative reading of the Clause 2(d) and 3(a) of integrity agreement
and Para 14 of the application of enlistment as contractor, it is evident that
the contractor can be banned, downgraded, suspended or black listed from
the list of contractors in the event of submission of non bonafide tenders or
for technical or other delinquency. More so, Clause 3(a) provides that
bidder/contractor can be excluded from future contract award process and
the imposition and duration of the exclusion will be determined by the
severity of transgression and determined by the Principal/Owner and such
exclusion may be forever or may be for a short period as decided by the
Principal/Owner.The approval order dated 10.08.2017 by virtue of which
the tendering limit upto Rs. 15.00 crores of the petitioner-firm was
approved, also bears the same clause like para-14 of the application of
enlistment of contractor. The order impugned has been passed by the
Director General, Border Roads Organisation.The clause-6 of the integrity
agreement provides the duration of the pact and it was binding for all the
bidders till the contract was awarded. It does not provide any period of
limitation for taking action for breach of integrity agreement and rather in
the instant case, the breach was committed during the participation in the
tender process, so contention that the action could not have been taken
beyond six months is mis-conceived. The petitioner has been banned for a
period of 18 months, after due opportunity of being heard was afforded to
the petitioner. The submission of the fake/forged documents for the
along with connected matters
purpose of obtaining the contract cannot be taken as misdemeanour.The
respondents could have barred the petitioner from all the future contracts as
per power vested in them but nonetheless, the respondents have treated the
petitioner very fairly and there is no force in these contentions of the
petitioner that the respondent had no authority to pass the order impugned
and the period of 18 months should have been reckoned from the date when
the tender of the petitioner was rejected.
18. The period of 18 months cannot be termed as disproportionate to the
delinquency of the petitioner. The petitioner himself has signed the
application for enlistment of petitioner as contractor, so the petitioner
cannot contend that the respondents had no authority to ban the petitioner
prospectively. More so, the mere delay in passing the order impugned can
hardly be a ground to quash the order impugned, particularly in view of the
fact that due to the Covid 19 Pandemic, whole of the world in fact had
come to standstill. This Court finds justification in the contention of Mr.
Vishal Sharma, learned ASGI that after the normalisation of the Covid 19
situation the proceedings were initiated and the order impugned was passed
against the petitioner.
19. The judgment relied by Mr. M. K. Bhardwaj, reported in 2004 (1) S.L.J 1is
not applicable in the present facts and circumstances of the case.
20. The order impugned has been passed after affording due opportunity of
being heard to the petitioner and this Court is not supposed to sit as an
appellate court over the decision of the respondents and this Court has only
to examine as to whether the principle of natural justice has been followed
along with connected matters
by the respondents, further the order impugned is not perverse/arbitrary and
the penalty is not disproportionate. As there was abundant material with the
respondents to initiate proceedings against the petitioner and for passing
the order impugned, so the decision of the respondents cannot be
considered as perverse or arbitrary. Therefore, this Court does not find any
reason, whatsoever, to show indulgence.
21. In view of the above, the present writ petition is found to be misconceived
and without any merits and the same is dismissed.
22. The decision in the connected writ petitions is dependent upon the decision
in the writ petition WP(C) No. 2410/2021. As the writ petition WP(C) No.
2410/2021 stands dismissed, so the connected petitions too are dismissed
accordingly.
23. Disposed of.
(RAJNESH OSWAL) JUDGE
Jammu 09.05.2022 Sahil Padha Whether the order is speaking: Yes Whether the order is reportable: Yes
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!