Citation : 2021 Latest Caselaw 1577 j&K
Judgement Date : 1 December, 2021
Sr. No. 08
HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT JAMMU
CCP(S) No. 507/2019
CM No. 563/2020
Khem Raj .... Petitioner/Appellant(s)
Through:- Mr. Sachin Sharma, Advocate.
V/s
Khursheed Ahmed Shah and anr. .....Respondent(s)
Through:-
Mr. Ravinder Gupta, AAG for R-1 and
2
Mr. H.A. Siddiqui, Sr. AAG for R-3
and 4.
CORAM : HON'BLE MRS. JUSTICE SINDHU SHARMA, JUDGE
ORDER
The petitioner seeks compliance of the judgment & order dated
23.07.2018 vide which the respondents were directed to clear the admitted
and undisputed liability of the petitioner. In the statement of facts, the
respondents have admitted the liability but the same has not been released
till date.
Mr. Siddiqui, learned AAG submits that it is only because of some
query raised by the JKIDFC Cell, that the concerned Executive Engineer,
PWD (R&B) Division Udhampur, was requested to revisit the earlier
proposal, and clarify the issue.
Mr. Ravinder Gupta, learned AAG submits that the Nodal Officer
has stated that the funds are available but the same be uploaded on portal
for payment.
The compliance cannot be delayed due to their inter-departmental
issues. Let order dated 23.08.2018 be complied and compliance report be
filed by the next date, failing which respondent 2 and 4 shall appear in
person on the next date.
List on 30.12.2021.
(Sindhu Sharma) Judge JAMMU 01.12.2021 MICHAL
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!