Tuesday, 19, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Rsa No.262/2024 vs Partap Singh Chauhan
2025 Latest Caselaw 704 HP

Citation : 2025 Latest Caselaw 704 HP
Judgement Date : 9 May, 2025

Himachal Pradesh High Court

Rsa No.262/2024 vs Partap Singh Chauhan on 9 May, 2025

2025:HHC:13579

IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA RSA No.262/2024.

Date of Decision: 09th May, 2025.

The Managing Director & Anr. .....Appellants.

                              Versus

      Partap Singh Chauhan                                           .....Respondent.
      Coram

The Hon'ble Mr. Justice Bipin Chander Negi, Judge.

Whether approved for reporting?1

For the Appellants: Mr. Durga Singh Kainthla, Advocate.

For the Respondents: Mr. P.S. Goverdhan, Sr. Advocate with Mr. Rakesh Thakur, Advocate, for the respondent.

Bipin Chander Negi, Judge (oral).

The Appellants, by filing this appeal under Section 100

of the Code of Civil Procedure (for short, CPC), has assailed the

judgement and decree dated 28.02.2023 passed by learned

District Judge, Solan, in Civil Appeal No. 42-S/13 of 2022,

whereby Appeal filed by the Appellants against the Judgement

and Decree dated 20.12.2019, passed by the learned Civil

Judge Court No.1, Solan, HP in Civil Suit No. 52/1 of 2016 was

partly allowed.

2. The parties shall hereinafter be referred to as "plaintiff"

and "defendants" in accordance with their status before the trial

Court. The facts leading up to the present appeal are that the

plaintiff's case, as set out in the plaint, was that a contract for

felling and conversion of 377 trees comprised in Lot No.5/2011-

12 (Rajgarh HL), including engraving, haulage of forest

Whether reporters of Local Papers may be allowed to see the judgment? YES

2025:HHC:13579

produce, carriage, and dispatch up to the roadside depot in

Forest Division Rajgarh, was awarded to him by the Himachal

Pradesh Forest Development Corporation, Shimla, through its

Divisional Manager, vide agreement dated 04.08.2011. Prior to

the execution of the agreement, the plaintiff deposited a sum of

₹50,000/- as security with defendants No. 3 and 4. The plaintiff

claimed to have executed the contract as per its terms and

conditions to the satisfaction of the said defendants. Upon

completion of the work, he submitted his bills to defendant No.

4 for payment, but an amount of ₹84,000/- was deducted as

extension fee, despite the fact that he had never sought any

extension of time for completing the work. Additionally, the

defendants No. 3 and 4 allegedly retained the security amount

of ₹50,000/- without any justification.

3. The plaintiff further contended that when he visited the

site after the assignment of work, he found that the trees to be

felled and converted were not bearing any hammer

or khudan marks, making them unidentifiable and rendering the

execution of the work practically impossible. He made

representations to the Divisional Manager, Forest Division,

Solan (D-4), pursuant to which a joint inspection was conducted

by a team of the Forest Department and the Forest

Development Corporation, leading to the re-enumeration of 377

trees. Only after this exercise could the plaintiff proceed with

the felling and conversion of the trees and dispatch the forest

2025:HHC:13579

produce to the roadside depot of defendants No. 3 and 5. The

plaintiff asserted that the defendants were not entitled to

deduct any amount towards delayed execution of the

agreement, as the delay was attributable to their failure to

properly mark the trees. Accordingly, he sought recovery of

₹1,34,000/- (₹84,000/- as extension fee and ₹50,000/- as

security) along with interest at the rate of 16% per annum from

July 2014 till realization.

4. Defendants No. 3 and 4 filed a joint written statement

contesting the suit on preliminary objections regarding

maintainability, cause of action, valuation, and jurisdiction. On

merits, while admitting the execution of the agreement dated

04.08.2011, they denied the remaining allegations. They

contended that the plaintiff informed them about the non-

marking of trees only after six months from the date of

allotment of work. They asserted that there was a delay in the

completion of work by the plaintiff, and in terms of Clause 12(b)

of the agreement, they were entitled to deduct an extension fee

at the rate of 1% per month of the contract value for the

leftover work. Since the plaintiff failed to complete the work

within the stipulated time, the deduction was lawful. They

prayed for the dismissal of the suit.

5. Defendants No. 1 and 2, namely the State of Himachal

Pradesh and the Secretary (Forest), did not file a separate

written statement but adopted the defence of defendants No. 3

2025:HHC:13579

and 4. In his replication, the plaintiff denied the allegation that

he informed the authorities about the non-marking of trees only

after six months. He reiterated that the work could not

commence on time due to the absence of hammer

or khudan marks on the trees, making them unidentifiable at

the site.

6. On the basis of the pleadings, the learned trial court

framed the following issues on 03.05.2017:

1. Whether the plaintiff is entitled for recovery of ₹1,74,299/- along with future interest @ 16% per annum from the date of institution of the suit till the realization of the whole amount, as prayed for? OPP

2. Whether the suit is not maintainable in the present form, as alleged? OPD

3. Whether the plaintiff has no cause of action to file the present suit, as alleged? OPD

4. Whether the plaintiff has not come to court with clean hands and has suppressed material facts from this court, as alleged? OPD

5. Whether the suit has not been properly valued for the purpose of court fee and jurisdiction, as alleged? OPD

6. Whether this court has no jurisdiction to try and decide the present suit, as alleged? OPD

7. Whether the plaintiff is estopped by his own act, conduct, deeds, admissions, omissions, and acquiescence from filing the present suit, as alleged? OPD

7. After recording the evidence of the parties and hearing

their arguments, the learned trial court concluded that the

stipulated time period for completion of work could not be

adhered to by the plaintiff because the trees to be cut and

converted were not properly marked and identified by

defendants No. 3 and 4. The fault lay with the defendants, and

therefore, they were not entitled to retain any amount from the

plaintiff on account of delayed execution of the agreement.

2025:HHC:13579

Accordingly, the trial court decided Issue No. 1 in favour of the

plaintiff and the remaining issues against the defendants,

decreeing the suit for a sum of ₹1,71,299/- with interest at the

rate of 6% per annum from the date of the suit till realization.

8. Aggrieved by this judgment and decree, defendants No.

3 and 4 had preferred a first appeal, contending that the trial

court failed to appreciate the evidence in the correct

perspective. They argued that the plaintiff did not comply with

the terms of the agreement within the stipulated time and

initiated work only after six months from the date of allotment,

raising the plea of unmarked trees belatedly. Despite this, the

defendants accommodated the plaintiff by getting the trees re-

enumerated. They asserted that, in terms of Clause 12(b) of the

agreement, they were entitled to deduct the extension fee from

the plaintiff's final bills on account of the delay attributable to

him.

9. The first appellate court partly allowed the appeal of

defendants No.3 and 4. The decree passed by the trial court

was partly modified and the suit was decreed to the following

effects:-

(a) Plaintiff were held entitled to recover amount of ₹1,34,000/- with pre-suit interest at the rate of 6% per annum from July 2014 till filing of suit i.e. 21.4.2016.

(b) The plaintiff was further held entitled to recover the principal so adjudged [i.e. ₹1,34,000/- plus pre- suit interest component as awarded vide (a) above], with interest at the rate of 6 % from the date of suit till realization.

(c) The amount of ₹50,000/- was held to be released to the plaintiff towards security during pendency of

2025:HHC:13579

suit on 13.6.2016, which was ordered to be deducted from the principal (as standing on that date for further calculations)

(d) The suit was decreed against defendants No.3 and

10. Against the aforesaid modification in the judgement &

decree of the trial court no further appeal had been preferred by

the plaintiff. Aggrieved by the impugned judgment and decree,

the defendant has filed this second appeal.

11. Perused the impugned judgment and heard counsels for

the parties.

12. Upon careful consideration of the material on record and

the submissions advanced, this Court finds that the two courts

below have concurrently and correctly held that while there was

no dispute regarding the allotment of work in 2011, the

defendant's own witness admitted that hammering and marking

of trees was done only on 20.10.2012, after which the plaintiff

commenced work in November 2012. The defendant's primary

contention that the work was not completed within the

stipulated time stands rebutted by the evidence on record,

which clearly establishes that the delay was attributable to the

defendant's failure to provide proper tree markings.

13. The contention raised by the learned counsel for

defendants No.3 and 4 regarding excessive pre-suit interest was

found to be reasonable and well-founded by the courts below. A

cumulative sum of Rs.1,34,000/- was retained by defendants

No.3 and 4 as extension fee and security. The plaintiff,

2025:HHC:13579

however, claimed a principal amount of Rs.1,71,299/- as on the

date of the suit by including interest calculated at 16% per

annum, as evident from para-No.7 of the plaint. Since the

agreement Ex.PW1/A did not stipulate any interest rate payable

on dues, the plaintiff was held to be entitled to interest only at a

reasonable rate on the amount found due by both the Courts. I

see no infirmity in the same.

14. In the aforesaid facts and attending circumstances,

there arises no question of law, much-less a substantial

question of law for consideration of the Court, therefore, the

appeal is dismissed being devoid of any merit. Pending

miscellaneous applications, if any, also stand disposed of.

(Bipin Chander Negi) Judge

09th May, 2025 (T.B/Gaurav Rawat)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter