Citation : 2026 Latest Caselaw 1658 Guj
Judgement Date : 25 March, 2026
NEUTRAL CITATION
C/FA/2274/2000 CAV JUDGMENT DATED: 25/03/2026
undefined
Reserved On : 11/03/2026
Pronounced On : 25/03/2026
IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
R/FIRST APPEAL NO. 2274 of 2000
FOR APPROVAL AND SIGNATURE:
HONOURABLE MR. JUSTICE J. C. DOSHI
==========================================================
Approved for Reporting Yes No
==========================================================
EXECUTIVE ENGINEER
Versus
KATARIA CONSTRUCTION CO.
==========================================================
Appearance:
MR VISHRUT JANI for MR RC JANI(357) for the Appellant(s) No. 1
NOTICE SERVED for the Defendant(s) No. 1
==========================================================
CORAM:HONOURABLE MR. JUSTICE J. C. DOSHI
CAV JUDGMENT
1. Present first appeal is directed against the judgment and decree dated 8th March 2000 passed by the learned Second Joint Civil Judge (SD), Kachchh at Bhuj, whereby the learned trial court has dismissed the suit of the plaintiff and allowed the counter claim of the defendant and directed the plaintiff to pay Rs. 6,52,050/- with 12% interest per annum from the date of the suit till realization.
2. The factual aspects born out of the record are that the
NEUTRAL CITATION
C/FA/2274/2000 CAV JUDGMENT DATED: 25/03/2026
undefined
Gujarat Water Supply and Savage Board in capacity of the plaintiff filed the Special Civil Suit No.210 of 1991 against respondent Katira Construction Company Limited, to recover the damage of Rs.17,28,855.65 Paise at the yearly interest of 18% on the ground and reason that the plaintiff board had given a contract for construction of ESR and underground sump at the cost of Rs.23,08,712.50 paisa to the defendant with the condition to complete the construction work within 12 months from the date of receipt of the work order.
2.1 The defendant since did not complete the work of construction within 12 months, but raised various disputes, he has been issued legal notices on 3 rd March 1999, 18th July 1990 and 28th September 1990 respectively and the contract in question was severed with the blockage of risk and cost of the defendant. The remaining work thereafter was carried out through other agency, and since the plaintiff board incurred expenditure, it has asked the relief of damage from the defendant.
2.2 On being served, the defendant appeared and filed written statement-cum-counterclaim at Exh.28 raising the dispute that the design for the work which was to be carried out was sanctioned late by four months by the plaintiff, hard rock cutting was not anticipated, thus hard rock cutting consumed time. It is also disputed that when excavation work was started by the defendant, the landowners and nearby persons compelled the defendant to stop the work at the midst of the contract work. The quantity of the reinforcement (steel) was unilaterally increased by the plaintiff board. All these has
NEUTRAL CITATION
C/FA/2274/2000 CAV JUDGMENT DATED: 25/03/2026
undefined
been pleaded to claim that because of such approach of the plaintiff, the defendant could not complete the work and instead of paying the risk and cost, rather, is entitled to damage occurred to him on various count and therefore, the defendant filed counterclaim under Order 8 Rule 6A of the Code of Civil Procedure, 1908 (in short "the Code") for recovery of Rs. 24,79,000/-.
2.3 The learned trial court went into trial after framing the issue and permitted both the parties to lead oral as well as documentary evidence. At the end, the learned trial court dismissed the suit of the plaintiff and partly allowed the counterclaim of the defendant in tune of the aforesaid decree.
2.4 Being aggrieved by the judgment and decree to the extent of partially allowing the counterclaim, the plaintiff board filed the first appeal.
3. Before proceed to record the arguments of learned advocate, Mr. Vishrut, Jani for learned, advocate Mr. RC Jani for the plaintiff, let me observe that the plaintiff board has not filed appeal challenging the impugned judgment and decree insofar as it relates to dismissal of the suit of the plaintiff. Simulteneously, it is to be noticed that though notice was served to the defendant, he chose not to remain present and to contest the appeal.
4. Learned advocate Mr. Jani, in his crisp submissions, mainly refers to the counter claim filed by the defendant, precisely, various claims ranging from claim Nos.1 to 9 vis-a-
NEUTRAL CITATION
C/FA/2274/2000 CAV JUDGMENT DATED: 25/03/2026
undefined
vis the impugned judgment and decree and submitted that to establish various claims made in the counter claim, the defendant has not filed any documentary evidence, which can strengthen, base, and establish the case of the defendant to recover the amount stated therein in different claims. He would further submit that the claim No.1 was not accepted by the learned trial Court and no appeal against rejection of claim No.1 has been preferred by the defendant, therefore, to that extent, the judgment and decree attained finality.
4.1 Insofar as other claims on record and allowed by the learned trial Court is concerned, learned, advocate Mr. Jani would submit that the claim No.2, whereby the learned trial court has granted Rs. 3,23,000/- on the ground that the work has been done, but not paid, is not proved by any evidence on record. Claim No.3, in regards to cutting of hard rocks, whereby the learned trial court granted Rs. 64,000/-, is totally in teeth of conditions of tender at Exh.120, whereby it was deemed that the contractor has inspected the site and satisfied himself about the nature of whole work of existing road waterway, and other means and cost talong side, which is sufficient to believe that there cannot be any separate claim for cutting the hard rock. Claim No.4 is in regards to passing of water through pipelines, which is granted in tune of Rs. 9000/-, but it relates to the work contract, which was required to be carried out and cannot be separately claimed, and so far as claim No.5 granting the amount to the tune of Rs. 81,250/- for the escalation in the price of material and remuneration of the labour is concerned, there is no evidence worth piece of paper produced by the defendant and yet, the learned trial
NEUTRAL CITATION
C/FA/2274/2000 CAV JUDGMENT DATED: 25/03/2026
undefined
court passed the award.
4.2 Insofar as claim No.6 for loss of profit of Rs.1 lakh and granted by the learned trial court, is concerned, learned, advocate, Mr. Jani, relied upon the judgment, in case of M/s Unibros Vs. All India Radio, 2023 INSC 931 to submit that for the claim related to loss of profit, the defendant was required to lead the evidence and establish that he has suffered profitability or opportunity to succeed and delay in completion of the work was attributable only to the plaintiff.
4.3 Learned advocate Mr. Jani would further submit that therefore, grant of claim or compensation in claim Nos.2 to 6 by the learned trial court is totally without evidence and deserves to be quashed and set aside by interfering with the findings of the learned trial Court in judgment of the counterclaim.
4.4 As far as last claim is concerned, whereby learned trial court granted amount of Rs.74,800/-, learned advocate Mr. Jani would submit that it is a refund of security deposit.
4.5 In the aforesaid premises, learned advocate, Mr. Jani would submit that the judgment of the learned trial court, as far as partly allowing the counterclaim is concerned, it is based upon the principle of no evidence, and thereby it requires to be interfered with.
4.6. Mainly upon above submission, learned advocate Mr. Jani would submit to allow the first appeal by quashing and
NEUTRAL CITATION
C/FA/2274/2000 CAV JUDGMENT DATED: 25/03/2026
undefined
setting aside the impugned judgment and award as far as it relates to partly allowing the counter claim.
5. As observed here in above, the defendant though served, did not remain present. The counter claim is defined under Order 8 Rule 6A of the Code. It has an effect of the suit. It is in nature of the suit and requires to be proved as like suit. The provisions of the Evidence Act in regards to burden of proof, etc. equally applies in counterclaim upon the defendant as far as establishing the facts of the case. Having noted so, the issue arose for the determination that (i) whether the learned trial Court committed error much less error of understanding the fact and law in partly allowing the counter claim? (ii) whether the learner trial court partly allowed the counterclaim on no evidence? (iii) What order?
6. It is apposite to refer counter claim of the defendant at Exh.28/B. As far as counter claim No.1 granting Rs.3,52,000/- on account of loss due to idle labour staff and machinery is concerned, out of said claim, they are viz. Rs.96,000/- loss due to idle labour and staff; Rs.2,24,000/- towards loss of labour and cost of establishment from February 1990 till August 1990 and Rs.32,000/- on account of cost of establishment from September, 1990 to December, 1990. The pleading in this regard has been made vide claim No.2, which was made for Rs.3,23,000/- on account of work done but not paid. It is claimed by the defendant that 11% of total work amounting to Rs.2,53,000/- was done by the defendant and his due and payable amount with interest of Rs.70,000/- was claimed on account of work done between March 1990 and July 1990.
NEUTRAL CITATION
C/FA/2274/2000 CAV JUDGMENT DATED: 25/03/2026
undefined
7. Claim No.3 is made for Rs.64,000/- on account of excavation of hard rock, whereas, claim No.4 is made for Rs.9000/- on account of pumping and bailing out water. Claim No.5 of Rs.81,250/- is made for the loss due to increase in the prices of labour and material suffered until July 1990 explaining that how the defendant suffered increase in the price of labour and material, which consist of base concrete foundation and bottom slab. Claim No.6 is made for Rs.12,35,000/- claiming loss due to blockage of machine, shuttering, scaffolding etc. including claim of Rs.6,37,500/- on account of depreciation and Rs.2,30,800/- on account of loss of profit.
8. No claim under the head of claim No.7 is preferred, but claim No.8 is in regards to loss on the overhead, whereas, claim No.9 is made for the purpose of reimbursement of Rs.74,800/- of FDR., whereby, on FDR of Rs.55,000/-, interest at the rate of 18% per annum being Rs.19,800/- was added to claim, totalling amount of Rs.74,800/-. Claim No.10 is for Rs.3 lakh for loss of business elsewhere.
9. The learned trial Court went into trial after framing the issues at Exh.30. Out of several issues framed by the learned trial Court, issue Nos.5 & 6 are in regards to relief claimed in counterclaim. They being relevant are extracted as under:-
"5. Whether defendant prove the counter claim?
6. Whether defendant is entitled for the interest, if yes, than at what rate?"
NEUTRAL CITATION
C/FA/2274/2000 CAV JUDGMENT DATED: 25/03/2026
undefined
10. The issue No.5 is answered in affirmative and issue No.6 is answered with the finding that the defendant is entitled to 12% interest per annum. Apt to note that the learned trial Court has framed these issues for counter claim submitted by the defendant. Though, the defendant has raised as many as 10 claims in counter claim on various grounds, making various averments in support of such counter claim, none of them have been put to adversarial filter by the learned trial Court by framing separate issues for each claim.
11. In background of the aforesaid aspect, it could be relevant to refer findings of the learned trial Court qua issue Nos.5 to 7, which have been decided simultaneously. Para 9 to 14 reads as under:-
"9. The defendant has presented his counter claim vide Exh.28 for Rs.24,79,000/- under ten claims. However, it will be interesting to take note of defendants' letter dated 10.2.1990 at Exh. 128, letter dated 5.2.1991 at Exh.138. By both these letters, defendants have produced claims to the plaintiff. There are also several letters on the record which require to be taken to consideration. There are three works which were to be undertaken by the Contractor and there were two sites where these works to be done viz at Chopadva and Gandhidham. If we go throgh the papers, it transpires that Drawing and Designs for chopadva work were finalised as per letter dated 7.8.1989 vide Exh. 172. And as per defendant letter dated 16.11.1989 at Exh. 155, it says that excavation has been done for 15 to 20 days, but work has been stopped by people and another letter of the same day i.e 16.11.1989, Exh. 173 by the defendant that due to hard rock work has become slow, Now, therefore, nothing comes out from the record that as to why the work was not started from
NEUTRAL CITATION
C/FA/2274/2000 CAV JUDGMENT DATED: 25/03/2026
undefined
7.8.1989 till the end of october.
10.. Similarly, for the work to be carried out at Kandla, drawings were approved by the end of November- 1989 vide Exh. 175. However, Exh. 174 says that there is some dispute about the land.
11.. Then, Ex. 177 is letter dated. 1.2.1990 by the plaintiff says that as the work at Chopadva has not been restrted, the measurement will be taken on 7.2.1990. thereafter the defendant has by his letter dated 20.5.1990 at Exh. 159 has said that work is stopped due to nonpayment of work done.
12.. The defendant in his deposition at Exh. 165 in para 6 has admitted that after the drawings and designs were approved, they had gone on site for starting the work. As stated above the drawings and designs for Chopadva work were approved in August- 1989 and for Gandhidham work in November-1989. Therefore, it is difficult to come to the conclusion that staff, establishment, machinery etc. were lying idle at the site. At the same time, from the letters narrated above it comes out that the defendant himself had stopped the work, though for non-payment, but that default cannot entitle him for compensation.
The plaintiff has submitted a letter at Exh. 137 and alongwith that a statement showing the financial position of the work done and to be done is also submitted. Now, if we look to that statement, the work done has been shown in all the three works, and the defendant does not seem to have denied that position directly. However, the defendant has been done by him and in the claim, the figures thereof have been shown.
14.. I have gone through the deposition of the defondent wherein he has narrated the claims. After careful consideration, I have come to conclusion that the following claims are sustainable:-
Claim No.2 for Rs.3,23,000/-
NEUTRAL CITATION
C/FA/2274/2000 CAV JUDGMENT DATED: 25/03/2026
undefined
Claim No.3 for Rs. 64,000/-
Claim No.4 for Rs.9,000/-
Claim No.5 for Rs.81,250/-
Claim No.6 for Rs.1,00,000/-
Claim No.9 for Rs.74,800/-
Total 6,52,050/-
12. Plain reading of the reasons assigned by the learned trial Court to answer issue Nos.5 and 6, this Court failed to find the discussion on the evidence, if any, led by the defendant before the learned trial Court to establish various claims narrated herein above. Mere pleadings would be incapable to result into decree. It is the proof of the pleadings, which is required to secure the decree. The learned trial Court referred to various letters exchanged between the parties claiming and determining each of the claims. However, they cannot be treated as reason or evidence to establish various claims like claim for work done but not paid, claim for loss due to idle labour and staff and machinaries, expenditure of amount for excavation of hard rock or the amount for pumping and bailing out water or loss due to increase in the prices of the labour and material suffered or loss due to blockage of machine, shuttering, scaffolding etc., loss of depreciation, losses on overheads, loss of profit or loss of business. All these claims based upon assertion of particular facts needed to be proved by leading cogent and convincing evidence. The defendant was required to prove that he has
NEUTRAL CITATION
C/FA/2274/2000 CAV JUDGMENT DATED: 25/03/2026
undefined
done some work, which is measured and yet, it has not been paid.
13. Learned advocate Mr. Jani brought to the notice of this Court Exh.147 and submit that the plaintiff board has measured the work carried out by the defendant contractor and prepared bill of Rs.8,45,550/-. The amount has been paid and thereby, entire amount assessed for work done by the contractor has been squared off. In total, Rs.9,38,680/- has been paid to the plaintiff. Thus, it would be highly improper for the defendant to claim that he has done the work and yet he has not been paid, more particularly, when he has accepted the amount of the bill prepared by the plaintiff board without raising any right to raise the dispute.
14. For claim Nos.3 and 4, while granting the amount of compensation, perhaps the learned trial Court failed to read condition No.2 of the tender notice produced at Exh.120 (page 97 of first paper book). Condition No.2 reads as under:-
"2 Tenderer will be deemed to have inspected the site and to have satisfied himself as to the nature of all works, all existing roads, water-way and other means of communication and access to and from the site and work and the building that may be required for temporary purpose in connecction with the construction, completion and maintenance of the works and must make his own enquiries as to work, yard sites and depot, and dums and as to the acquisition of such additional sites and areas as may be necessary for temporary purpose for constructing, completing and maintaining the works."
NEUTRAL CITATION
C/FA/2274/2000 CAV JUDGMENT DATED: 25/03/2026
undefined
15. Plain reading of aforesaid condition interpret claim Nos.3 and 4. But, the learned trial Court in hurry of granting claims raised by the defendant, without referring to the tender executed between the parties, wrongly passed the judgment.
16. Claim No.5 is in regards to loss due to increase in the price of labour and material, but such claim is made without producing any documentary evidence that how and in which way, the defendant suffered loss due to increase in the price of labour and material. The defendant, who failed to carry out anything beyond 11% of the total work, cannot claim that he has suffered loss due to increase in the price of labour and material. It also includes escalation in the price of material and remuneration of the labour which again covers under clause (2) of the tender. Thus, such claim was not maintainable.
17. The defendant in claim No.6 even failed to clarify that which machines were blocked, shuttered or scaffolded. The submission of the defendant is insufficient to grant damage. This claim also includes claim of Rs.6,37,500/- on account of depreciation. The defendant, who claims damage for depreciation, could have placed on record books of account to establish claim of depreciation, but, no such documentary evidence are submitted by the defendant to claim the compensation.
18. Loss of profit at 10% was claimed to Rs.2,32,000/-.
NEUTRAL CITATION
C/FA/2274/2000 CAV JUDGMENT DATED: 25/03/2026
undefined
19. In Unibros (supra), the Hon'ble Apex Court in para 19 observed as under:-
"19. The law, as it should stand thus, is that for claims related to loss of profit, profitability or opportunities to succeed, one would be required to establish the following conditions: first, there was a delay in the completion of the contract; second, such delay is not attributable to the claimant; third, the claimants status as an established contractor, handling substantial projects; and fourth, credible evidence to substantiate the claim of loss of profitability. On perusal of the records, we are satisfied that the fourth condition, namely, the evidence to substantiate the claim of loss of profitability remains unfulfilled in the present case."
20. None of the conditions stated by the Hon'ble Apex Court in Unibros (supra) has been followed by the defendant to claim loss of profit. Thus, the damages under the head of this claim is found stale. Rest of the claims except claim No.9 i.e. for reimbursement of the FDR are also general and vague and even not supported by the evidence much less single evidence on record.
21. As fa as claim No.9 is concerned, it is undisputed that FDR of Rs.55,000/- has been submitted by the contractor towards security of the work. The learned trial Court while granting refund of the FDR was pleased to accept the contention that the defendant has accepted 18% interest p.a. on the FDR and granted Rs.74,800/- as damage or rather refund of the FDR with further interest at the rate of 12% p.a.. So, the learned trial Court on a claim of refund of the FDR
NEUTRAL CITATION
C/FA/2274/2000 CAV JUDGMENT DATED: 25/03/2026
undefined
partly allowed interest at the rate of 18% p.a. and then, granted 12% interest even on the interest amount and thereby, has granted compounding interest. This is something unusual, unprecedented and unheard of. But since, the learned trial Court was in mood of granting compensation towards suchclaims of the defendant, such mistake is bound to be happened. The amount of refund on FDR is required to be granted and to that extent, the defendant's counterclaim was maintainable. Grant of FDR is required to be granted with interest at 12% considering the FDR as security deposit in commercial transaction.
22. In the premises of the aforesaid reasons, this Court finds that the learned trial Court has committed serious and menifest error in partly allowing the counterclaim and allowing the decree to recover Rs.6,50,050/- with interest at 12% p.a. from the date of the suit (interest has to be started from the date of the counterclaim). The learned trial Court proceeded to partly allow the counterclaim on no evidence. Just pleadings and some of exchange of letters between the parties triggered the learned trial Court to grant the decree in favour of the defendant while decreeing the counterclaim partly. The complete erroneous approach taken by the learned trial Court is viewed by this Court and accordingly, present appeal deserves consideration.
23. In wake of aforesaid premises, present appeal is allowed. The judgment and decree passed by the learned trial Court in counterclaim is hereby modified to the extent that the
NEUTRAL CITATION
C/FA/2274/2000 CAV JUDGMENT DATED: 25/03/2026
undefined
defendant is entitled to amount of Rs.55,000/- being refund of FDR along with interest at 12% p.a. from the date of the counterclaim till realization. Rest of the decree passed by the learned trial Court below counterclaim is hereby quashed and set aside.
24. If any amount is deposited pursuant to the impugned judgment and decree, except the aforesaid amount decreed by this Court, shall be refunded to the plaintiff by the learned trial Court upon proper verification and identification.
25. Decree sheet be prepared accordingly.
26. Registry is directed to return back the R & P, if any, to the concerned Court forthwith.
(J. C. DOSHI,J) SHEKHAR P. BARVE
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!