Tuesday, 19, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Gambhirsinh Juvansinh Gohil vs Deputy Executive Engineer
2024 Latest Caselaw 829 Guj

Citation : 2024 Latest Caselaw 829 Guj
Judgement Date : 31 January, 2024

Gujarat High Court

Gambhirsinh Juvansinh Gohil vs Deputy Executive Engineer on 31 January, 2024

                                                                                 NEUTRAL CITATION




      C/SCA/16907/2023                             ORDER DATED: 31/01/2024

                                                                                  undefined




             IN THE HIGH COURT OF GUJARAT AT AHMEDABAD

              R/SPECIAL CIVIL APPLICATION NO. 16907 of 2023

==========================================================
                         GAMBHIRSINH JUVANSINH GOHIL
                                    Versus
                          DEPUTY EXECUTIVE ENGINEER
==========================================================
Appearance:
MS SUDHA C SHUKLA(3804) for the Petitioner(s) No. 1
MS SUMAN MOTLA, AGP for the Respondent(s) No. 1
==========================================================

     CORAM:HONOURABLE MRS. JUSTICE MAUNA M. BHATT

                               Date : 31/01/2024

                                 ORAL ORDER

1. This petition is filed challenging the award of the Labour Court, Bhavnagar dated 30.05.2023 in Reference (LCB) No. 47 of 2019 wherein the Reference filed by the workman was rejected.

2. The facts in brief are as under:-

The workman for his alleged illegal termination raised a dispute before the Labour Court, Bhavnagar registered as Reference (LCB) No. 47 of 2019. The Labour Court upon adjudication and after taking into consideration the evidence on record, rejected the reference on the ground of delay as well as on the ground that the workman failed in discharging his primary onus to establish that he had completed 240 days in preceding year. Aggrieved by the rejection of reference by

NEUTRAL CITATION

C/SCA/16907/2023 ORDER DATED: 31/01/2024

undefined

award dated 30.05.2023, present petition is filed.

3. Heard learned advocate Ms. Sudha Shukla and learned Assistant Government Pleader Ms. Suman Motla for the respondent - State.

4. Learned advocate for the petitioner submitted that the award of the Labour Court dated 30.05.2023 is erroneous since it failed to consider that the delay occasioned in preferring the reference was genuine and well-explained. Further, since the petitioner was working as a dailywager, he preferred an application for production of documents. The said application though was allowed, no documents were produced by the respondent - State and therefore the inference drawn that the workman failed in discharging the primary onus for completion of 240 days is erroneous. She therefore submitted that the award of the Labour Court dated 30.05.2023 deserves to be quashed and set aside.

5. On the other hand, learned Assistant Government Pleader Ms. Suman Motla for the respondent - State submitted that the Labour Court as passed the award after taking into consideration the evidence on record. Admittedly there was delay of 16 years in raising the dispute. Further, the workman also failed in leading evidence in relation to completion of his 240 days and therefore, question of breach of Section 25 F, G and H of the Industrial Disputes Act, 1947, would not arise and therefore no interference of this Court is required.

5.1 In support of her submissions on delay, she relied upon

NEUTRAL CITATION

C/SCA/16907/2023 ORDER DATED: 31/01/2024

undefined

the decision of this Court in the case of Pravinbhai Nanjibhai Bharadava V/s. State of Gujarat in Letters Patent Appeal No. 307 of 2016 decided on 26.04.2016.

6. Considered the submissions and the decision relied upon. Admittedly for the termination w.e.f. 30.03.2003, the dispute was raised in the year 2019. Thus, there is a delay of 16 years in raising the dispute.

This Court in Pravinbhai Nanjibhai Bharadava [supra] on belated raising of dispute has held as under:-

"5. It is to be noticed that though it is the case of the workman that he was discontinued from service on 15.9.1999, the dispute was raised in the year 2008. It is true that the provisions of Limitation Act, 1963 would not apply in stricto senso to the disputes under the Industrial Disputes Act but in the judgment in the case of Assistant Engineer, Rajasthan State Agriculture Marketing Board, sub-division, Kota (supra) and further in the judgment of Prabhakar V/ s Joint Director Sericulture Department, reported in JT 2015(9) SC 83, the Supreme Court has clearly held that in a case of unexplained delay and laches on the part of the workman, the Court shall bear in mind such objection before grant of relief. It is also to be noticed that there is a specific case of the petitioner that the petitioner last worked only upto 1989 and on his own he discontinued from attending the work. In spite of such contention, there is no material placed before the learned Single Judge to

NEUTRAL CITATION

C/SCA/16907/2023 ORDER DATED: 31/01/2024

undefined

show that he has continued in service after the year 1989. In that view of the matter, we are of the view that the learned Single Judge rightly placed reliance on the judgment referred above and allowed the petition. With regard to the other submissions made by learned advocate for the appellant that he may be awarded compensation at least in terms of the ratio of the laid down in Assistant Engineer, Rajasthan State Agriculture Marketing Board, sub-division, Kota (supra), it is to be noticed that in that set of facts, there was a delay of six years and he has admittedly worked from 1.11.1984 to 17.2.1986. In this case, having regard to the statement made by the employer before the Labour Court that the petitioner discontinued from the year 1989 on his own, we are of the view that this is not a fit case to grant any compensation also. Granting of compensation instead of reinstatement is also a matter which depends on various factors."

6.2 In view of above, delay of 16 years in initiating proceedings before the Labour Court cannot be ignored. Further, no justification was provided for such delay and therefore the findings of the Labour Court does not call for any interference.

7. On the aspect of non-production of documents upon application filed by the workman, the Labour Court has observed that in the cross-examination the workman admitted that he has no evidence to support his case that he has continuously worked for 240 days. On the contrary, he admitted that the evidence produced by the respondent for his

NEUTRAL CITATION

C/SCA/16907/2023 ORDER DATED: 31/01/2024

undefined

presence for the year 1988 - 89 to 1998 is correct. He also admitted that he did work as and when the work was available. Therefore, there is no error in the findings that the workman failed in discharging his primary onus to establish that he had worked for 240 days in a year. No interference is called for.

8. In view of above, in the opinion of this Court, no case is made out by the petitioner for interference by this Court. The petition is accordingly rejected.

(MAUNA M. BHATT,J) SHRIJIT PILLAI

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter