Citation : 2023 Latest Caselaw 4511 Guj
Judgement Date : 15 June, 2023
C/SCA/8584/2020 JUDGMENT DATED: 15/06/2023
IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
R/SPECIAL CIVIL APPLICATION NO. 8584 of 2020
FOR APPROVAL AND SIGNATURE:
HONOURABLE THE ACTING CHIEF JUSTICE MR. JUSTICE A.J.DESAI
and
HONOURABLE MR. JUSTICE BIREN VAISHNAV
==========================================================
1 Whether Reporters of Local Papers may be allowed
to see the judgment ?
2 To be referred to the Reporter or not ?
3 Whether their Lordships wish to see the fair copy
of the judgment ?
4 Whether this case involves a substantial question
of law as to the interpretation of the Constitution
of India or any order made thereunder ?
==========================================================
CHANASMA TALUKA SARVODAY MAZOOR KAMDAR SAHAKARI
MANDALI LTD. THROUGH ITS SECRETARY
Versus
THE UNION OF INDIA THROUGH MINISTRY OF PETROLEUM AND
NATURAL GAS
==========================================================
Appearance:
MR ANUJ H DAVE(8333) for the Petitioner(s) No. 1
MS AISHWARIYA REDDY, ADVOCATE FOR GUPTA LAW
ASSOCIATES(9818) for the Respondent(s) No. 2
RULE SERVED for the Respondent(s) No. 1
==========================================================
CORAM:HONOURABLE THE ACTING CHIEF JUSTICE MR.
JUSTICE A.J.DESAI
and
HONOURABLE MR. JUSTICE BIREN VAISHNAV
Page 1 of 16
Downloaded on : Fri Jun 16 20:40:22 IST 2023
C/SCA/8584/2020 JUDGMENT DATED: 15/06/2023
Date : 15/06/2023
ORAL JUDGMENT
(PER : HONOURABLE MR. JUSTICE BIREN VAISHNAV)
1. By way of this petition, under Article 226 of the
Constitution of India, the petitioner has prayed for
quashing and setting aside the termination letter dated
25.03.2020 by which the petitioner's contract for grass
cutting and bush cutting at various well sites and
approach roads in ONGC Mehsana Asset was terminated.
The petitioner has also prayed for quashing and setting
aside the letter dated 13.05.2020 by which as a sequel to
the termination of the contract agreement, the petitioner
is put on a holiday for a period of two years from the date
of the order.
2. Facts in brief are as under:
2.1 The petitioner is a society registered under the
Gujarat Co-operative Societies Act, 1961. The respondent
C/SCA/8584/2020 JUDGMENT DATED: 15/06/2023
ONGC on 20.02.2019 issued a notice inviting tender for
hiring of services for grass cutting and bush cutting at
various well sites at approach roads and installations and
approach roads in ONGC Mehsana Asset. In the bidding
process, the petitioner was declared as a successful
bidder. Accordingly, a notification awarding the contract
for the aforesaid services was issued to the petitioner.
The duration of the contract was for a period of three
years from the date of commencement of services.
2.2 On compliance of the conditions of notice of
awarding the contract, a contract agreement was entered
into between the petitioner and the ONGC on 25.09.2019.
It is the case of the petitioner that after the execution of
the contract, the petitioner started diligently working on
the project assigned to it in accordance with the contract
agreement.
2.3 On 17.01.2020, the respondent ONGC issued a letter
to the petitioner informing it that as per the intimation
C/SCA/8584/2020 JUDGMENT DATED: 15/06/2023
from the user section of the six work orders placed for
the contract, despite the scheduled completion date
having passed, the work completion status as on
08.01.2020 was 'not completed'. The petitioner was
advised to comply with the communications in
accordance with the terms of the contract within ten days
from the issue of the said letter.
2.4 The petitioner on that very date i.e. 17.01.2020
responded setting out that it had infact completed the
works and in three of the projects, work completion
certificates were not received. In response to the letter,
on 06.02.2020, the respondent corporation in accordance
with clause 9 and 18.4 of the general conditions of the
contract, issued a notice informing the petitioner that
despite multiple communications, the petitioner has failed
to comply with the terms of the contract and the work on
the six installations has not been completed till date.
2.5 The petitioner was therefore asked to show cause as
C/SCA/8584/2020 JUDGMENT DATED: 15/06/2023
to why the contract be not terminated. The petitioner
responded by letters dated 16.02.2020 and 26.02.2020
disputing the stand of the respondent. By the impugned
communications under challenge, not only has the
contract of the petitioner been terminated but the
petitioner has been put on holiday for two years as far as
the contract with ONGC is concerned.
3. Mr. Anuj Dave, learned advocate for the petitioner
would invite the court's attention to clause 9 of the
conditions of the contract and would submit that the
clause required the corporation to put to the petitioner's
notice any defect or deficiencies and give the petitioner a
time frame of ten days to remedy the same and only
thereafter the contract could have been terminated after
a 30 days' written notice which has not been done in this
case.
3.1 Mr. Dave, learned advocate for the petitioner would
invite the court's attention to the letter dated 17.01.2020
C/SCA/8584/2020 JUDGMENT DATED: 15/06/2023
and submit that of the six installation projects as far as
NK-III, NS-ETP work completion certificates were not
issued. For the remaining four, in two cases such
certificates were attached whereas it was pointed out for
other two that certificates could be submitted after
completion of projects within a short span. He would
therefore submit that because of non-availability of
completion certificates from the respondent, the
petitioner could not be blamed for over shooting of the
scheduled time frame of completing the projects.
3.2 Inviting the court's attention to the letter dated
26.02.2020, Mr. Dave, learned advocate for the
petitioner would submit that in some cases there was a
delay in completion work as the commencement of the
work was rescheduled based on the ONGC's requirement
of work and in certain cases when the petitioner's
labourers went on to the well sites, it was noticed that the
area of allotment is increased from the area originally
mentioned in the work order. For instance, in NK-GGS-2
C/SCA/8584/2020 JUDGMENT DATED: 15/06/2023
(23 wells), the area as per the work order was 18,584 sq.
mtrs but the actual completed area was 1,03,783 sq mtrs.
Obviously, therefore, the stand of the corporation that the
work was incomplete was unjustified.
3.3 Mr. Anuj Dave, learned advocate for the petitioner
would further submit that if the period in question is
noticed it was during the lockdown period where
sufficient workforce was not available and therefore the
petitioner could not have been faulted for completion of
work.
3.4 In support of his submission that the termination of
the contract was in compliance of clause 9 of the General
Conditions of the contract, Mr. Dave relied on a decision
of the Hon'ble Apex Court in the case of MP Power
Management Company Limited, Jabalpur vs. Sky
Power Southeast Solar India Private Limited and
Others [(2023) 2 SCC 703]. Relying on para 108 of the
decision, he would submit that clause 9 of the Article in
C/SCA/8584/2020 JUDGMENT DATED: 15/06/2023
contract before the Apex Court was identical to the one in
the case on hand where the Hon'ble Apex Court had
interfered with the termination as there was no default
notice in accordance with the said clause as in the
present case.
5. Ms. Aishwariya Reddy, learned advocate appearing
for Gupta Law Associates, learned advocate for the
respondent ONGC per contra would submit that since the
petition pertains to contractual obligation between
parties, this court should refrain from assuming
jurisdiction under Article 226 of the Constitution of India.
The petitioner has an effective alternative remedy of
invoking conciliation proceedings before Outside Expert
Committee in accordance with clause 27.3 of the
contract.
5.1 On merits, Ms. Reddy would submit that the
petitioner was informed about the methodology of
executing the contract because especially time was the
C/SCA/8584/2020 JUDGMENT DATED: 15/06/2023
essence as well sites needed to be cleared off the grass
and tall bushes as such growth was highly inflammable
and could result in accidents on the well sites. The
petitioner was time and again informed regarding the
importance of timely completion of work orders issued by
the corporation.
5.2 Ms. Reddy would draw the court's attention to the
communications addressed to the petitioner on
25.09.2019 and 10.10.2019 constantly emphasizing on
the fact that the work of grass cutting at the installations
should be completed within the time frame. On
06.11.2019, the petitioner was addressed an e-mail in
detail pointing out that the petitioner had overshot the
work schedule and had not completed the work. Even by
letters dated 29.11.2019, 05.12.2019, 08.12.2019,
10.12.2019, the petitioner was issued several reminders
and the petitioner failed to take corrective measures. The
response of the petitioner on 25.12.2019 was not a
satisfactory explanation as to why the work was not
C/SCA/8584/2020 JUDGMENT DATED: 15/06/2023
completed. In fact on 27.12.2019, of the 14 installations
assigned to the petitioner, even 50% of the work was not
completed. It was in light of this that the petitioner was
issued a notice on 17.01.2020. She would submit on
reading the notice dated 17.01.2020, it is evident that it
was in fact a default notice in accordance with clause 9 of
the contract. Having failed to carry out the work on
06.02.2020, the corporation was left with no option to
issue a notice of 30 days in accordance with clause 9 and
18.4 of the contract asking the petitioner to show cause
as to why the contract be not terminated. Post the
period, by a communication dated 25.03.2020, the
contract was terminated and thereafter by the other
impugned communication the petitioner was put on a
holiday.
5.3 Ms. Reddy would also invite the court's attention to
the contention in the reply where relying on clause 19 of
the scope of work she would submit that it was
categorically provided that the total area of grass cutting
C/SCA/8584/2020 JUDGMENT DATED: 15/06/2023
in a year shall be 18,00,000 m/2 whereas the total area of
work assigned to the petitioner was 9,76,520 m/2. She
would further submit that it is evident from the table
annexed to the reply that in fact the petitioner had not
completed the work and there is no material for the
petitioner to show that the work was infact completed.
6. Having considered the submissions made by the
learned advocates for the respective parties, what is
evident is that an agreement was entered into between
the petitioner and the respondent corporation for grass
cutting and bush cutting at various well sites in ONGC
Mehsana Asset. It is the case of the petitioner that the
termination of the contract and the consequential black
listing was in violation of the terms of the contract
especially clause 9 thereof. Clause 9 of the contract
reads as under:
"9.0 PERFORMANCE The CONTRACTOR shall undertake to perform all services under this CONTRACT with all- reasonable skill, diligence and care in accordance with sound industry practice to the
C/SCA/8584/2020 JUDGMENT DATED: 15/06/2023
satisfaction of the CORPORATION and accept full responsibility for the satisfactory quality of such services as performed by them. Any defect, deficiencies noticed in the CONTRACTOR's service will be promptly remedied by the CONTRACTOR within 10 days upon the receipt of written notice from the CORPORATION to improve their performance failing which the CORPORATION may terminate the CONTRACT by giving the CONTRACTOR 30 (thirty) days written notice."
6.1 Six work orders were issued to the petitioner at
various well sites and the date of the work orders and the
scheduled completion date were brought to the notice of
the petitioner by the letter of 17.01.2020. Reading of the
letter indicates that it was the case of the corporation
that since the petitioner had not completed the work
within the time limit so stipulated the petitioner was
categorically put to notice to comply with the requisitions
contained in the communications referred to in the letter
and update the status within ten days of the issue of the
letter.
6.2 In the communication so addressed, reference has
C/SCA/8584/2020 JUDGMENT DATED: 15/06/2023
been made to various letters of the corporation dated
29.11.2019, 05.12.2019, 08.12.2019, 10.12.2019 and
26.12.2019. These communications referred to in the
default notice are on record. Reading these
communications annexed to the reply indicate that the
petitioner was informed that it has not finished the work
at several installations till date and there were several
installations where the work had yet not started. The
communication further indicates that the petitioner had
not deployed sufficient number of teams for grass cutting
and therefore the undue delay in execution and
completion of work at installations is hampering the
safety of the workers and the installations. The petitioner
was requested to take corrective measures. One of the
letters also indicates that as a result of the slow progress,
the corporation had encountered three fire incidents and
despite reminders the petitioner had done nothing.
6.3 Reading of the affidavit-in-reply would further
indicate that though alleged by the petitioner that though
C/SCA/8584/2020 JUDGMENT DATED: 15/06/2023
work completion certificates were not issued inspite of
work having been completed, the tabular statement
indicates that the work was in fact not completed within
the time frame and that even the contention of the
petitioner that the work area had increased beyond what
was stipulated in the work order is misconceived.
7. Reading the communication dated 06.02.2020,
which again reiterates the earlier communications
indicates that the petitioner was given a 30 days' notice
prior to the termination of the contract by the impugned
communication dated 25.03.2020 as the response of the
petitioner was found unsatisfactory. This too therefore
was also in compliance with clause 9 of the conditions of
the contract and therefore the contention of learned
advocate for the petitioner that the orders impugned are
in violation of clause 9 of the conditions of the contract
also cannot be accepted.
8. Perusal of the affidavit-in-reply indicates that the
C/SCA/8584/2020 JUDGMENT DATED: 15/06/2023
respondent corporation through a tabular statement has
set out the factual position that infact the work which was
assigned to the petitioner could not be carried out in the
time schedule that it was expected to be done. The
contention of the petitioner that work was in fact
completed for which no work certificates were issued is
not based on any material and even otherwise it being a
disputed question of fact is best left untouched.
9. Even otherwise it is well settled by several decisions
of the Hon'ble Apex Court that when the power of judicial
review is invoked in matters relating to tender or
awarding of contracts, if the decision relating to such
contracts is bonafide, the courts will not in exercise of
powers of judicial review interfere even if a procedural
aberration or error in assessment is made out. In the
case on hand, the petitioner has failed to even make out
any procedural defect in his challenge to the order of
termination of contract and of black listing.
C/SCA/8584/2020 JUDGMENT DATED: 15/06/2023
10. In view of the above, finding no merit in the petition,
the same is dismissed. Rule is discharged.
(A.J.DESAI, ACJ)
(BIREN VAISHNAV, J) DIVYA
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!