Citation : 2022 Latest Caselaw 4272 Guj
Judgement Date : 20 April, 2022
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
R/SPECIAL CIVIL APPLICATION NO. 19500 of 2021
FOR APPROVAL AND SIGNATURE:
HONOURABLE THE CHIEF JUSTICE MR. JUSTICE ARAVIND KUMAR
and
HONOURABLE MR. JUSTICE ASHUTOSH J. SHASTRI Sd/-
==================================================
1 Whether Reporters of Local Papers may be allowed to Yes see the judgment ?
2 To be referred to the Reporter or not ? Yes
3 Whether their Lordships wish to see the fair copy of the No judgment ?
4 Whether this case involves a substantial question of No law as to the interpretation of the Constitution of India or any order made thereunder ?
================================================== M/S BACKBONE PROJECT LTD.
Versus SARDAR SAROVAR NARMADA NIGAM LTD.
================================================== Appearance:
MR. JAIMIN R. DAVE (7022) for the Petitioner(s) No. 1 MR. S M DAVE (11268) for the Petitioner(s) No.1 MR. PRIYANK S DAVE (9465) for the Petitioner(s) 1
MS MANISHA LAVKUMAR, GOVERNMENT PLEADER WITH MR. K.M.ANTANI,
==================================================
CORAM:HONOURABLE THE CHIEF JUSTICE MR. JUSTICE ARAVIND KUMAR and
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
HONOURABLE MR. JUSTICE ASHUTOSH J. SHASTRI
Date : 20/04/2022
CAV JUDGMENT
(PER : HONOURABLE MR. JUSTICE ASHUTOSH J. SHASTRI)
[1] The petitioner by way of the this petition under Article 226
of the Constitution of India is challenging the legality and validity
of the decisions taken by respondent authority dated
21.12.2019, 08.04.2021 and 28.06.2021 and consequently
sought for release of an amount of Rs.74,29,134/-. To be precise
prayers sought for reads as under:-
"8.a. Your LORDSHIPS may be pleased to allow this petition;
b. YOUR LORDSHIP may be pleased quash and set aside the decision taken by the Respondent vide letter dated 21.12.2019, 08.04.2021 and 28.06.2021
c. YOUR LORDSHIP may be pleased direct the Respondent to consider the claim of the Petitioner independent of undertaking dated 13.01.2006 and direct Respondent to release an amount of Rs.74,29,134/- (Rupees Seventy-Four Lacs Twenty-Nine Thousand One Hundred Thirty-Four);
d. any other and further relief deemed just and proper be granted in the interest of justice;
e. to provide for the cost of this petition."
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
[2] The background of the facts leading to the rise of petition is
that petitioner is a company incorporated under the provisions of
the Companies Act, 1956 and being a "juristic person" has
invoked extraordinary jurisdiction of this Court. The respondent
floated a tender during April, 1999 for the work of Constructing
Minors (Earthwork, Brick Lining, Structures) and Road of
Distributaries for Block No. 9A5 Package-I (which would refer as
"the said work" for the sake of brevity). The said tender work
was for a total consideration of Rs.7,03,78,267/- which came to
be accepted by respondent authority by issuing a letter of intent
dated 05.05.2000 and thereby the respondent authority called
upon the petitioner to execute an agreement and to deposit an
amount towards security deposit. On 12.06.2000, an agreement
came to be executed bearing No. SSP/B-2/7 of 2001-2002 and as
per the requirement upon deposit of security amount the Work
Order also came to be issued on 29.06.2000. Petitioner pursuant
to it mobilized the manpower and machinery to complete the
work within the time scheduled as prescribed under the contract.
However, delay has occasioned on account of various
circumstances and the work ultimately could not be completed
within stipulated time.
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
[2.1] It is the case of the petitioner that respondent herein as a
result of which decided to withdraw remaining tender work from
the petitioner to assign the same to third party at the risk and
cost of the petitioner and to that effect a letter was
communicated to the petitioner on 12.08.2005. Petitioner
requested the respondent vide letter dated 08.10.2005 to revoke
the decision as it was inclined to carryout the remaining portion
of work. Later on, the said request was accepted by respondent
authority and permitted the petitioner to complete the remaining
tender work as intimated by communication dated 01.12.2005
subject to the condition that petitioner would not claim price
escalation during the period of completion of remaining tender
work after the original date of completion under the contract. So
much so, petitioner was asked to furnish an undertaking to that
effect which also came to be forwarded and later on despite
resistance and obstruction of the farmers / landowners and all
other contingencies the work was processed but on account of
the said circumstances vide letter dated 15.01.2007, the
petitioner was constrained to make a further request for
enlargement of time for completion of remaining portion of work.
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
It was also requested that since the circumstances were not
related to the petitioner in completion of work and the delay has
occurred on account of respondent's default, petitioner
requested the respondent to consider the petitioner's request to
pay price escalation but finally on 04.06.2007 the respondent
agreed to grant an extension to the petitioner and according to
the petitioner also agreed to consider the request for price
escalation subject to furnishing the evidence. The said
circumstances, according to the petitioner, are reflected in
letters dated 15.01.2007 and 04.06.2007.
[2.2] It is further the case of the petitioner that surprisingly vide
communication dated 27.08.2007 the respondent terminated the
contract itself and informed the petitioner that final
measurement will commence on 10.09.2007 and to this, the
petitioner raised strong objection in the form of letter dated
10.09.2007 raising protest against the termination of contract
and sought for release of the outstanding payment along with
price escalation. In response to this, vide letter dated
06.02.2010, the respondent proposed to debar the petitioner
from all its tender works as a result of this, a specific objection
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
has been raised against such proposed action of debarring vide
detail communication dated 08.02.2010 and also incidentally
requested to grant an opportunity of hearing before taking any
action in that direction.
[2.3] It is further the case of the petitioner that on 24.02.2010,
the respondent called upon the petitioner to attend the meeting
with the Joint Managing Director (Finance) on 25.05.2010. The
petitioner remained present and voiced out the grievances
before the authority and in the said meeting, the Deputy General
Manager and the Chief Engineer, Canals-1 were also present and
they, according to petitioner, have accepted that there was some
delay on the part of respondent in providing structure drawings
and providing land to the petitioner and also accepted that they
could not provide requisite borrow areas to the petitioner due to
non-availability. The said meeting resulted into an execution of
Supplementary Contract Agreement dated 15.03.2010 and in the
said agreement also it was specifically agreed, according to the
petitioner, that balance payment for the work executed will be
paid as per the original tender rate with price escalation at
frozen indices of April 2007. According to the petitioner, it was
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
also agreed that payment of additional structures of 29 numbers
and borrow area excavation shall also be paid as per the SOR
2008-09 and as such the respondent became liable to pay the
price escalation, as indicated above. The petitioner has
submitted that even work completion certificate was also issued
on 31.12.2010 indicating satisfaction about the work which was
carried out.
[2.4] It is further the case of the petitioner that vide letter dated
16.05.2011, the petitioner claimed specifically the price
escalation as per the Supplementary Contract Agreement and
also claimed the payment of difference of star rate of cement
and steel during the said period in view of Clause 57 of the
contract amounting to Rs.12,14,484/-. Several representations
have been made in this regard to the respondent but the
respondent refused to release the payment of price escalation,
even as per the contract and went on repeating by indicating
that by virtue of such undertaking dated 13.01.2006 the request
is not possible to be accepted. The detailed representations
have been made time and again in this regard by the petitioner
clarifying the entire situation that the undertaking which was
already given was in respect of a different situation but by virtue
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
of fresh agreement the request deserves to be considered but
respondent once again vide communication dated 08.04.2021
rejected the request which has again led the petitioner to make a
further fresh representation on 15.05.2021 then again the
authority has not considered the case reiterated its early
decision in the from of fresh letter dated 28.06.2021. As a result
of this, petitioner has approached this Court by way of present
petition under Article 226 of the Constitution of the India.
[3] Pursuant to the notice having been issued, the respondent
authority has appeared, filed a detailed reply and as such upon
request of both the learned advocates appearing for the
respective side, the matter is taken up for final hearing.
[4] Mr. Jaimin R. Dave, learned advocate appearing for the
petitioner has vehemently contended that action of the
respondent authority is not only unjust and arbitrary but tainted
with mala fides. It has been contended that sole reason which
has been assigned for impugned action is that in the month of
January, 2006, the petitioner tendered an undertaking and as
such it is not entitled to seek release of price escalation and star
rate difference. It has been submitted that such undertaking has
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
no role to play specially when the fresh contract came to be
executed between parties to the proceedings and as such said
agreement having been executed and after certifying the
completion of work satisfactorily now when a difference of price
escalation is to be made the authority has gone back to the year
2006 and resorted to an undertaking which cannot be applied at
all and hence, the action initiated by respondent is absolutely
arbitrarily, unreasonable.
[4.1] It has been contended by Mr. Dave, learned advocate
appearing for the petitioner that it is not in dispute that work has
been completed long back in December, 2010 for which the
authority has also issued a certificate which is reflecting on page
159 (Annexure-M) and once having completed the work which
was allowed by the very same respondent authority it is now not
open for it to raise a plea of undertaking just to deny the benefit
and as such the action is unsustainable in the eye of law.
[4.2] Mr. Dave, learned advocate appearing for the petitioner
has further submitted that it is settled position of law that when
the action of authority is arbitrary, unreasonable and apparently
not sustainable the writ court always can exercise extraordinary
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
jurisdiction as held in catena of decisions and here is the case in
which the background of facts would clearly indicate that action
of authority under challenge is absolutely arbitrary. Hence, he
has prayed for issuance of writ in the context of relief which are
sought for in the petition.
[4.3] Mr. Dave, learned advocate has also submitted to
strengthen his argument by making a reference that undertaking
was given to the effect that petitioner will not seek nor raise
grievance with regard to price escalation during the period after
original date of completion and the said undertaking dated
13.01.2006 has lost its significance by virtue of Supplementary
Contract Agreement which came to be executed on 15.03.2010.
That being so apparently action is not sustainable. A further
reference is made to few of the conditions contained in
Supplementary Contract Agreement reflecting at page 155
(Annexure-L) and has submitted that a specific stipulation was
contained in the said contract that payment of balance work
executed will be paid as per the original tender rate with price
escalation at frozen indices of April 2007 and that being so, there
is hardly any reason for authority to relate back to the
undertaking of 2006. This supplementary contract is executed in
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
the month of March, 2010 with aforesaid rider. Hence, the action
of the respondent in depriving the price escalation and star rate
difference to petitioner is ill-founded. Hence, he has prayed for
the reliefs sought for being granted in the interest of justice.
[4.4] Mr. Dave, learned advocate has submitted that the work
has been completed way back in the year 2010 and since then
petitioner has represented to respondent demanding payment
and only when the denial has taken place right to agitate has
accrued in favour of the petitioner. Mr. Dave, learned advocate
has submitted that there is a strong case existing in favour of the
petitioner.
[4.5] To substantiate his aforementioned brief contentions, Mr.
Dave, learned advocate appearing for the petitioner has referred
to few decisions, which are narrated hereunder:
(i) In the case of ABL International Ltd. and another
versus Export Credit Guarantee Corporation of
India Ltd. and others reported in (2004) 3 SCC 553.
(ii) In the case of Food Corporation of India and
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
another versus Seil Ltd. and others reported in
(2008) 3 SCC 440.
(iii) In the case of Surya Constructions versus State of
Uttar Pradesh and others reported in (2019) 16 SCC
(iv) In the case of Uttar Pradesh Power Transmission
Corporation Limited and another versus CG Power
and Industrial Solutions Limited and another
reported in (2021) 6 SCC 15.
(v) In the case of Unitech Limited and others versus
Telangana State Industrial Infrastructure
Corporation (TSIIC) and others reported in 2021
SCC OnLine SC 99.
By referring to aforesaid decisions, Mr. Dave has reiterated
his submission that action of respondent is arbitrary and has also
contended that instead of relegating the petitioner to any
alternative forum, writ court may exercise its discretion in
present peculiar background of fact.
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
[5] To counter the submissions made by Mr. Jaimin R. Dave,
learned advocate appearing for the petitioner, Ms. Manisha
Lavkumar Shah, learned Government Pleader assisted by Mr. K.
M. Antani, learned Assistant Government Pleader appearing on
behalf of the respondent authority has vehemently opposed the
petition inter alia contending that petition suffers from the vice
of delay and laches and on this count alone, petition is liable to
be dismissed. In addition to it, it has been submitted that work
entrusted to petitioner was of public importance but petitioner
had miserably failed in carrying out the work and respondent
was constrained to invoke the clauses contained in the contract
to terminate the said contract. According to learned
Government Pleader, the request was made by the petitioner not
to blacklist as a result of this, after considering the request of the
petitioner the work was allowed to be completed which was left
out and the supplementary contract was executed. It has been
submitted that petitioner had completed only 31.10% work up to
the stipulated date of completion and it is only upon the request
of petitioner a pragmatic view was taken and time limit was
extended up to 28.04.2007 and yet petitioner did not complete
the work which led the respondent to terminate the contract for
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
non performance on 30.07.2007. It has been submitted that
after considering the overall circumstances and after granting a
personal hearing, a decision was taken then to allow the
petitioner to conclude the work vide decision dated 04.03.2010
and prior to it, it was deliberated in the meeting dated
25.02.2010 and it was made it clear to the petitioner that all
other terms and conditions of the original contract will remain
unchanged and other remaining work as per the original contract
is to be completed by the agency and as such the terms and
conditions discussed in the meeting having been accepted by the
petitioner and the original terms and conditions remained intact
with further addition, there is no absolute right of the petitioner
to agitate as if it is a fundamental right to seek a relief and that
too invoking Article 226 of the Constitution of India when
disputed question of facts are there.
[5.1] Learned Government Pleader has submitted that original
contract was of the year April, 1999 for estimated cost of
Rs.823.66 lakhs and it is on account of delay in not completing,
the respondent authority had to face an awkward situation and
time schedule of completion miserably was not maintained by
petitioner. It has been submitted that petition is brought in the
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
year 2021 for the cause which has accrued allegedly way back in
the year 2010. On the contrary, 12 years back, the security
deposit has also been refunded to petitioner which is not in
dispute and all throughout petitioner has remained silent except
making representations which would in no way help the
petitioner to seek equitable relief by ignoring the principle of
delay and laches.
[5.2] Learned Government Pleader for the respondent authority
has then taken us to an exhaustive affidavit-in-reply filed by the
respondent pointing out the chronology of events right from
02.05.2000 till 13.09.2012. On the contrary, the final RA Bill was
released by the respondent on 25.07.2011 amounting to
Rs.67.92 lakhs and even security deposit was also refunded to
the petitioner way back on 10.05.2011 and 13.09.2012
respectively which position is not in dispute at all as the said
amounts have been acknowledged by the petitioner and as such
when there is such a huge unexplained delay to claim a relief in
the form of monetary benefits, extraordinary jurisdiction may not
be allowed to be invoked by the petitioner and it is settled
position of law that making of representation continuously will
not allowed a litigant to go out of a well recognized a principle of
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
delay and laches and for that purpose. learned Government
Pleader has referred to a decision, which is in the case of
Karnataka Power Corporation Ltd. and another versus K.
Thangappan and another reported in (2006) 4 SCC 322.
[5.3] Learned Government Pleader for the respondent authority
has further submitted that even if the date of return of security
deposit is not to be treated as a date for reckoning the period
but then also, the decisions which have been taken where
merely a reiteration of the stand has already been taken by the
respondent authority and as such no case is made out by the
petitioner to maintain the present proceedings after huge
unexplained delay, as indicated above.
[5.4] Learned Government Pleader for the respondent authority
has also submitted that since the terms and conditions of the
original contract is maintained as it is and remained operative
and binding on the petitioner, petitioner instead of rushing to this
Court ought to have resorted to ventilate the grievance through
a specific mechanism provided under the original contract itself
and referred to Clause-29(b) which relates to the arbitration and
contends said fact finding authority, namely, the Tribunal can
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
examine all the details about delay, applicability of undertaking
and examination of terms in the context of conduct of the
petitioner and it would be desirable for the petitioner to resort to
such proceedings to be initiated before the Arbitration Tribunal
or to seek any other remedy under civil law. As a result of this,
learned Government Pleader has prayed for dismissal of this
application.
[5.5] With respect to refund of security bill and payment of RA
Bill necessary particulars have been provided and brought to the
notice of this Court by way of an affidavit dated 19.03.2022
submitted on record and upon perusal, a request is made not to
entertain the petition as no case is made out calling for
interference.
[6] In rejoinder to this, Mr. Jaimin R. Dave, learned advocate
appearing for the petitioner has submitted that delay cannot be
attributed to the petitioner since the time to agitate or challenge
would arise only on cause of action being accrued and according
to him, the denial which has taken place in the recent time and
the limitation beguns to run and therefore delay and laches
principle would not come in the way of petitioner to claim the
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
equitable relief. Hence, he has prayed that on the basis of the
undisputed factual position, the relief can be granted by this
Court instead of relegating the petitioner to an alternative forum,
in the interest of justice. No other submissions have been made
by learned advocates appearing for the respective parties.
[7] Having heard the learned advocates appearing for the
respective parties and having gone through the relevant material
on record, we are of the view that detailed chronology of events
which has commenced from the issue of work order in the year
2000 till the request of the petitioner to carry out the work to be
completed by extending opportunity to the petitioner requires to
be tabulated and same is tabulated hereinbelow:
Date Description of event
02.05.2000 The Petitioner was awarded the Tender
contract floated by the Respondent for
"work of constructing minors (Earthwork, Brick lining, Structures) and Road distributaries for Block No. 9A5 (P.I.) for Rs. 707.78 lacs.
05.05.2000 Letter of Intent issued by the Respondent to the Petitioner 12.06.2000 Petitioner and the Respondent executed the Agreement bearing no. SSP/B-2/7 of
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
2000-2001.
It is stated that Tender Agreement provided for the stipulated time schedule within which the Petitioner was required to complete the work. Copy of the executed Tender Agreement is annexed herewith and marked as ANNEXURE - R-4.
As per this schedule the entre work was to be completed by the Petitioner by 28.06.2003 29.06.2000 Work Order was issued by the Executive Engineer, Narmada Project Canal Dn No. 1/5Jambusar vide letter No.-NPCD.1/5/AB- TC/WO/C/42 of 2000 Dated:- 29.06.2000.
30.06.2001 The Respondent addressed a letter to the Petitioner raising concern with respect to the progress of the work as the same did no commensurate with the stipulated time schedule provided in the Tender Agreement since only 6.46% of the work was executed even after a period of One year.
Copy of the letter dated 30.06.2001
addressed by the Respondent to the
Petitioner is annexed herewith and
marked as ANNEXURE R-5.
19.01.2002 The Respondent through various letters
13.03.2002 addressed to the Petitioner raised
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
17.07.2002 concerns over the progress of the work
and also held meeting with the Petitioner with regard to the same. Despite Copy of the letter dated 19.01.2002, 13.03.2002 and 17.07.2002 addressed by the Respondent to the Petitioner is annexed herewith and marked as ANNEXURE R-6 (Colly).
07.12.2002 The Petitioner was required to complete
the work by 28.06.2003, however when
around 28.27% of the work was done by
December 2002, the Respondent
addressed a letter calling upon the
Petitioner for a meeting.
25.02.2004 It is pertinent to mention that the
09.04.2004 stipulated time period to complete the
work already stood expired on
28.06.2003, however, despite extension granted by the respondent, till February 2004, only 28.27% work was completed by the Petitioner. The Respondent raised grave concern over the same as the Petitioner had reneged from its assurance to start work from 14.02.2004 under its letter dated 05.02.2004.
Not only the Petitioner time and again failed to meet its commitment, but audaciously, the Petitioner even failed to
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
remain present for the meetings called for by the Respondent.
Copy of the letters dated 25.02.2004 and 09.04.2004 addressed by the Respondent to the Petitioner is annexed herewith and marked ANNEXURE R- 7(Colly).
19.06.2004 Letter addressed by the Respondent to the Petitioner raising concern over only 31.16% work having been completed till such date and the complete failure of obligation of the Petitioner under the Tender contract for achieving the targeted progress. Hence, vide this letter the Respondent intimated the Petitioner that the extension of time sought by the Petitioner would be difficult in such circumstance.
Copy of the letter dated 19.06.2004 addressed by the Respondent to the Petitioner is annexed herewith and marked as ANNEXURE R-8.
12.10.2004 The Petitioner addressed a letter to the Respondent that it has a plan to complete the work by June-July 2005 and furnished an assurance to complete the work with the time frame proposed. Copy of the letter dated 12.10.2004 addressed by the Petitioner to the Respondent is annexed herewith and marked as ANNEXURE R-9.
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
14.02.2005 After giving its assurance to complete the 10.03.2005 work by Jun-July 2005, the Petitioner vide letter dated 14.02.2005, surreptitiously, attempted to raise issues of purported obstructions to justify the impairment of the progress of the work. However, the contents of this letter were refuted by the Respondent vide its reply dated 10.03.2005.
Copy of the letter dated 14.02.2005 addressed by the Petitioner to the Respondent and Copy of the reply dated 10.03.2005 addressed by the Respondent to the Petitioner is annexed herewith and marked as ANNEXURE - 10(Colly).
08.04.2005 The Petitioner furnished an unconditional undertaking for extension of time to complete the work as per Clause 6, Page TC-6 of the Tender Contract stating that it shall accept and abide by the final decision of the Respondent regarding the request for extension of time.
Copy of the undertaking dated 08.04.2005 furnished by the Petitioner to the Respondent is annexed herewith and marked as ANNEXURE -11.
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
30.06.2005 The Petitioner vide letter dated 25.08.2005 30.06.2005 sought extension of time to complete work till June 2006.
The Respondent vide letter dated 25.08.2005 intimated the Petitioner that the request for extension of time sought by the Petitioner was not genuine taking into consideration how the Petitioner had time and again reneged from its obligations under the Tender contract but also failed to complete the work even within the stipulated extended time frame. Hence, the Respondent vide this letter informed the Petitioner of its decision to take the possession of work and give to another contractor to complete the unexecuted work at the risk and cost of the Petitioner.
Copy of the letter dated 30.06.2005 addressed by the Petitioner to the Respondent and Copy of the letter dated 25.08.2005 addressed by the Respondent to the Petitioner is annexed herewith and marked as ANNEXURE - 12(Colly).
08.10.2005 The Petitioner addressed a letter to the Respondent admitting and acknowledging that despite extensions received from the Respondent it could not complete the
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
work within the stipulated time due to reasons attributable to the Petitioner.
Relevant part of the letter is reproduced as under:
"1. Under the above reference, our tender for the subject work has been rescinded and tenders have been invited for the balance work, which are due to be received and opened on 11.10.2005 @ Vadodara. We are aware that we had approached you personally last year with a request to allow us to complete the above work and you were kind enough to consider the case and allowed us additional time to complete the above work, but unfortunately, we could not complete the same due to various reasons attributed to us only. ......"
The Petitioner vide this letter requested the Respondent to grant it another opportunity to complete the work within one Year against which it offered to give double the amount of Security deposit and further stated that if they are not able to achieve the desired progress at the end of 6 months, the Respondent may be at liberty to forfeit the first Bank
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
Guarantee and if the work is not completed within One Year, the Bank Guarantee may also be forfeited and the work may be granted to another agency at its risk and cost.
Copy of the letter dated 8.10.2005 is
annexed herewith and marked as
ANNEXURE -13.
03.12.2005 Vide this letter the respondent accepted
the proposal of the Petitioner under letter dated 08.10.2005 subject to conditions including inter alia that the Petitioner shall seek, nor be entitled to price escalation during the period, after the original date of completion.
Copy of the letter dated 03.12.2005
addressed by the Respondent to the
Petitioner is annexed herewith and
marked ANNEXURE -14.
13.06.2006 The Petitioner in unequivocal terms,
furnished an undertaking to not seek, nor be entitled to price escalation during the period, after the original date of completion under the Tender contract.
Copy of the undertaking dated 13.06.2006 furnished by the Petitioner to
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
the Respondent is annexed herewith and marked as ANNEXURE -15.
Year 2006-2010 It is submitted that even after 2006, the Petitioner reneged from its undertaking and assurance to complete the work within One Year, and it was after another gross delay of 4 years that the work was completed.
During this period of 2006 to 2010 various communication were addressed to the Petitioner raising concerns over the progress of the work, a copy of which is annexed herewith and marked as ANNEXURE -16 (COLLY).
15.03.2010 Further, a Supplementary Contract dated 15.03.2010 was executed between the Petitioner and the Respondent, the copy of which has been annexed by the Petitioner at Annexure L.
25.07.2011 Final RA Bill was released by the
10.05.2011 Respondent amounting to Rs.67.92 Lakhs
13.09.2012 dated 25.07.2011 and Security Deposit
refunded to the Petitioner dated
10.05.2011 and 13.09.2012.
[8] The aforesaid sequence of events would clearly indicate
that work appears to have been completed only in the year 2010
i.e. on 31.12.2010, which was beyond the original time limit
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
which was provided under the original contract. The final
Running Account Bill also came to be released by the respondent
amounting to Rs.67.92 lakhs way back in July, 2011 and so also
the security deposit came to be refunded to the petitioner on
10.05.2011 and 13.09.2012 itself. However, the present petition
has been filed in the year October, 2021. It may be true that
petitioner was continuously submitted representations to the
authority but the fact remains that entire period right from 2012
to 2021 has remained unexplained from the petitioner's side
except stating that petitioner was making repeated
representations. We find no cogent explanation for such
enormous delay which has taken place to agitate the price
escalation having been given though final RA Bill was already
released way back in July, 2011 and same is also acknowledged
by the petitioner without any demur. Petitioner was quite well
aware and it was within the knowledge of petitioner in the year
2011 itself about alleged non-payment of amount which is now
claimed in this petition.
[9] The Hon'ble Apex Court in the matter of Karnataka Power
Corporation Ltd. (Supra) on the principle of delay and laches has
held:
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
"6.Delay or laches is one of the factors which is to be borne in mind by the High Court when they exercise their discretionary powers under Article 226 of the Constitution. In an appropriate case the High Court may refuse to invoke its extraordinary powers if there is such negligence or omission on the part of the applicant to assert his right as taken in conjunction with the lapse of time and other circumstances, causes prejudice to the opposite party. Even where fundamental right is involved the matter is still within the discretion of the Court as pointed out in Durga Prasad v. Chief Controller of Imports and Exports (AIR 1970 SC 769). Of course, the discretion has to be exercised judicially and reasonably.
9. It was stated in State of M.P. v. Nandlal (AIR 1987 SC
251), that the High Court in exercise of its discretion does not ordinarily assist the tardy and the indolent or the acquiescent and the lethargic. If there is inordinate delay on the part of the petitioner and such delay is not satisfactorily explained, the High Court may decline to intervene and grant relief in exercise of its writ jurisdiction. It was stated that this rule is premised on a number of factors. The High Court does not ordinarily permit a belated resort to the extraordinary remedy because it is likely to cause confusion and public inconvenience and bring, in its train new injustices, and if writ jurisdiction is exercised after unreasonable delay, it may have the effect of inflicting not only hardship and inconvenience but also injustice on third parties. It was pointed out that when writ jurisdiction is invoked, unexplained delay coupled with the creation of third party rights in the meantime is an important factor which also weighs with the High Court in deciding whether
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
or not to exercise such jurisdiction.
10. It has been pointed out by this Court in a number of cases that representations would not be adequate explanation to take care of delay. This was first stated in K.V. Raja Lakshmiah v. State of Mysore (AIR 1967 SC 973). This was re- iterated in R.N. Bose's case (supra) by stating that there is a limit to the time which can be considered reasonable for making representations and if the Government had turned down one representation the making of another representation on similar lines will not explain the delay. In State of Orissa v. P. Samantaraj (AIR 1976 SC 1617) making of repeated representations was not regarded as satisfactory explanation of the delay. In that case the petition had been dismissed for delay alone. (See State of Orissa v. Arun Kumar (AIR 1976 SC 1639 also)."
[10] From the aforesaid observations, we are of the considered
opinion that continuous representations or remaining in the lame
hope for all these years that one day authority will reconsider
would not absolve the petitioner from the vice of principle of
delay and laches. As a result of this, we are not in a position to
ignore the delay while arriving at final conclusion.
[11] In addition to this, a perusal of the terms of original
contract agreement and the supplementary contract if to be co-
related, the action may not be found to be so arbitrary which
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
may allow us to invoke extraordinary jurisdiction to grant the
relief sought for. The original contract contains terms and
conditions indicates that such a mammoth project which was
entrusted to be undertaken by petitioner consisting of a huge
estimated cost of Rs.823.66 lakhs was to be completed within
the period mentioned in the original contract and said contract
specifically being understood by the petitioner after careful study
of the conditions of the contract specification, it is too late in the
day to retrace the terms agreed to. The original contract also
dealt with the issue related to indemnity as well as the
recoveries of the claim stipulated vide Clause 33 and by virtue of
said Clause 33, the respondent is entitled to appropriate set off
the claim. The said original contract also contains an arbitration
clause which indicates that in the event of any dispute or
difference arising out of or in relation to the contract shall be
referred to arbitration Tribunal for arbitration constituted under
the provisions of the Gujarat Public Works Contract Dispute
Arbitration Tribunal Act, 1992 and the decision of the Tribunal
would be final and as such the petitioner has neither disclosed
cogent reasons for inordinate delay in not approaching the Court
nor has disclosed as to why till now has not redressed his
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
grievance though statutory mode under the contract itself was
available hence this conspicuous silence over this much period
also not impossible to be ignored by us.
[12] Now, coming to the terms of the undertaking dated
13.01.2006, reflected at page 138(A) given by petitioner indicate
that petitioner has agreed not to seek price escalation during the
period after the original date of completion. A perusal of
Supplementary Contract Agreement indicate that after giving the
opportunity and after considering the request of the petitioner,
the respondent has allowed the petitioner to complete the work
of on certain conditions and the said contract dated 15.03.2010
indicates that other terms and conditions of original contract will
remain unchanged and remaining work as per the original
contract is to be completed by the agency. The reliance on
Clause 3 and 4 of said agreement placed by the petitioner could
have well been agitated before an appropriate forum already
stipulated in the original terms as it is a disputed question of
fact. On perusal of the aforesaid circumstances prevailing on
record, we are of the opinion that petitioner was not remediless
and it could have agitated or made an attempt to ventilate the
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
grievance after receiving back security deposit. However, after
receipt of the security deposit without any objection as well as
payment under the final Running Account Bill it is loo late in the
day to contend petitioner is entitled to escalated charged and
that too after 12 years. Hence, we are of the view that equitable
jurisdiction in this peculiar background does not deserve to be
exercised.
[13] In the light of aforesaid chronology of events, we made a
pointed query to the petitioner's counsel that what was the
reason for remaining silent right from the year 2012 till 2021, he
candidly submitted that he was unable to explain the delay
except stating that petitioner was pursuing its grievance before
respondent by submitting representations. Hence, we are of the
opinion that delay and laches staring on the face of it cannot be
given a go bye in present background.
[14] Hence, we are not inclined to exercise our extraordinary
jurisdiction to grant the reliefs sought for. There can be no
dispute at all about the proposition that Writ Court cannot
exercise the discretion despite the availability of statutory
mechanism to ventilate the grievance and further it is also not in
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
dispute that no monetary relief can be granted in exercise of
jurisdiction under Article 226 of the Constitution of India.
However, it all depends upon fact of each case. In the instant
case we have specifically noticed that after accepting the refund
of security deposit and clearance of final RA Bill without any
demur after almost a decade an attempt is made by petitioner to
seek the relief though the petitioner was quite aware about the
fact that such grievance could have been raised at a relevant
point of time not only in view of the availability of specific forum
but also invoking the remedy under civil law. However, for
reasons undisclosed in the present proceedings the petitioner
has not availed the said alternative remedies and upon query
being raised about delay simple answer was that petitioner was
making continuous representations to respondent. This
explanation is not digestable in view of fact and as such when
these facts are quite apparent the decisions which have been
tried to be relied upon are not possible to be applied to the facts
on hand. Law of precedent is quite clear that one additional fact
may make a world of difference in applying the proposition.
Hence, having gone through the decision relied upon by the
petitioner at length, we are unable to extend our hands of justice
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
to the petitioner. Hence, we refrain ourselves from exercising
extraordinary jurisdiction in the present proceedings in the light
of undisputed facts prevailing on record as discussed above.
[15] At this stage, we may refer to the law laid down by Hon'ble
Apex Court last in the matter of Uflex Limited versus
Government of Tamil Nadu and others reported in (2022) 1 SCC
165 in which it has been made clear that judicial review in
contractual matters has its own limitation and it is invoked to
prevent arbitrariness, irrationality, unreasonableness, bias and
mala fides. The purpose is to check whether the choice of
decision is made lawfully and not to check whether the choice of
decision is sound. Following observations contained in
paragraph 2 reads thus:-
"2. The judicial review of such contractual matters has its own limitations. It is in this context of judicial review of administrative actions that this Court has opined that it is intended to prevent arbitrariness, irrationality, unreasonableness, bias and mala fide. The purpose is to check whether the choice of decision is made lawfully and not to check whether the choice of decision is sound. In evaluating tenders and awarding contracts, the parties are to be governed by principles of commercial prudence. To that extent, principles of equity and natural justice have to stay at a distance."
C/SCA/19500/2021 CAV JUDGMENT DATED: 20/04/2022
[16] In view of aforesaid observations, we are of the view that
petitioner has not made out any case of arbitrariness, mala fides
or unreasonableness which can be attributed to respondent.
Hence, we deem it proper not to exercise our extraordinary
jurisdiction at such a belated stage particularly when the delay
has not been explained with cause much less sufficient cause at
all. Hence, we deem it proper not to entertain this petition.
[17] However, while parting with the present judgment and
order, we may make it clear that dismissal of this petition may
not come in the way of petitioner ventilating its grievance in an
appropriate proceedings known to law and subject to just
exceptions. With these observations, present petition stands
dismissed with no order as to costs.
Sd/-
(ARAVIND KUMAR, C.J.)
Sd/-
(ASHUTOSH J. SHASTRI, J.) DHARMENDRA KUMAR
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!