Sunday, 26, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Himachal Futuristic vs I.T.I Ltd.
2017 Latest Caselaw 2097 Del

Citation : 2017 Latest Caselaw 2097 Del
Judgement Date : 28 April, 2017

Delhi High Court
M/S Himachal Futuristic vs I.T.I Ltd. on 28 April, 2017
$~OS-20
*      IN THE HIGH COURT OF DELHI AT NEW DELHI
%                                            Date of decision: 28.04.2017
+      O.M.P. 54/2013
       M/S HIMACHAL FUTURISTIC               ..... Petitioner
                    Through  Mr.Rakesh Tiku, Sr.Advocate with
                             Mr.Vivek Ojha & Mr.Sandeep
                             Kumar, Advocates for the HFCL

                    versus
       I.T.I LTD.                                      .... Respondent
                             Through   Mr.Ashok Kumar Singh, Sr.Advocate
                                       with Mr.Prannoy Raikhy, Advocate
                                       for ITI

       CORAM:
       HON'BLE MR. JUSTICE JAYANT NATH


JAYANT NATH, J. (ORAL)

I.A.No.1105/2017

1. This is an application filed under Section 5 of the Limitation Act seeking condonation of delay of 40 days in re-filing of the objections under Section 34 of the Arbitration and Conciliation Act.

2. The petitioner has filed objections to the award dated 07.07.2012. The dispute centres around the delay in re-filing of the objections. This court on 09.01.2015 allowed this application noting that there was a genuine issue regarding objections raised by the Registry about the court fees that was required to be paid on the amount awarded by the arbitrator. The court concluded that sufficient cause has been shown by the petitioner to condone

O.M.P. 54/2013 Page 1 the delay in re-filing the objections and allowed the application.

3. The above order of this court was impugned before the Division Bench. The Division Bench on 07.04.2015 concluded that the delay in re- filing for the period between 09.10.2012 to 27.11.2012 has not been considered by the learned Single Judge. Hence, the matter was remitted back to consider the application a fresh regarding delay in re-filing of the objections for the said period in question. The petitioner was permitted to file an additional affidavit giving explanation for the period in question.

4. Hence, the present arguments are confined only to the directions of the Division Bench dated 07.04.2015 whereby the explanation of the petitioner for the period from 09.10.2012 to 27.11.2012 for condonation of delay in re-filing the objections has to be considered.

5. In compliance with the directions of the Division Bench dated 07.04.2015, the petitioner has filed an additional affidavit. The additional affidavit states that in terms of the objections raised by the Registry on 09.10.2012, the main objection raised was regarding the „new format‟ which was recently introduced for the purpose of filing of the petition. It is urged that there was some ambiguity among lawyers regarding the new procedure/ format for filing. Inquiry was made and the petition was reformatted in terms of the „new format‟. It is further stated that during this period from 09.10.2012 to 27.11.2012, there were vacations due to festive seasons, i.e. Dussehra on 24.10.2012, Eid on 27.10.2012, Diwali on 13.11.2012, Moharram on 25.11.2012 and Guru Nanak Birthday on 28.11.2012. It is urged that the court and the office of the lawyer remain closed during Dussehra and Diwali vacations. The papers of the present case were also accidentally misplaced. The clerk of the counsel also went to his hometown

O.M.P. 54/2013 Page 2 Uttarakhand during Diwali and returned after celebrating Diwali. It is also urged that during this period, time was spent in attempting to remove the objections, which were raised by the Registry.

6. I have heard the learned senior counsel for the parties.

7. The learned senior counsel for the respondent has vehemently opposed the condonation of delay in re-filing the objections relying upon the various judgments of this court, which are as follows:

i. Gautam Associates v. Food Corporation of India, 2009 (111) DRJ 274;

ii. Prakash Atlanta JV v. National Highways Authority of India, EFA(OS) No.4 of 2013 dated 12.02.2013; iii. NTPC Limited v. Gannon Dunkerley & Co. Ltd., FAO(OS) No.89 of 2013 dated 12.02.2013;

iv. Union of India v. M/s Popular Construction Co., AIR 2001 SC 4010;

v. Delhi Transco Ltd. & Anr. v. Hythro Engineers Pvt. Ltd.

2012(3) ARBLR 349 (Delhi);

vi. The Executive Engineer (Irrigation & Flood Control) v.

Shree Ram Construction Co., 2010(10) AD Delhi 180; vii. Union of India v. Harbhagwan Harbhajan Lal, O.M.P.

No.30 of 2010, dated 11.03.2010 and viii. Delhi Development Authority v. M/s Durga Construction Co., ILR(2014) 1 Delhi 153."

8. The legal position regarding condonation of delay in re-filing of objections under section 34 of the Act were considered and settled by the

O.M.P. 54/2013 Page 3 Division Bench of this court in the case of Delhi Development Authority v. M/s Durga Construction Co.(supra). Relevant paras are as follows:

"19. It follows from the above that once an application or an appeal has been filed within the time prescribed, the question of condoning any delay in re-filing would have to be considered by the Court in the context of the explanation given for such delay. In absence of any specific statute that bars the jurisdiction of the Court in considering the question of delay in re-filing, it cannot be accepted that the courts are powerless to entertain an application where the delay in its re-filing crosses the time limit specified for filing the application.

20. Although, the courts would have the jurisdiction to condone the delay, the approach in exercising such jurisdiction cannot be liberal and the conduct of the applicant will have to be tested on the anvil of whether the applicant acted with due diligence and dispatch. The applicant would have to show that the delay was on account of reasons beyond the control of the applicant and could not be avoided despite all possible efforts by the applicant. The purpose of specifying an inelastic period of limitation under section 34(3) of the Act would also have to be borne in mind and the Courts would consider the question whether to condone the delay in re-filing in the context of the statute. A Division Bench of this High Court in M/s. Competent Placement Services through its Director/Partner v. Delhi Transport Corporation through its Chairman: 2011 (2) R.A.J. 347 (Del) has held as under:-

"9. In the light of these provisions and decisions rendered by the Hon'ble Supreme Court, it is thus clear that no petition under Section 34 of the A&C Act can be entertained after a period of three months plus a further period of 30 days, subject to showing sufficient cause, beyond which no institution is permissible. However, the rigors of condonation of delay in re-filing are not as strict as condonation of delay of filing under Section 34(3). But that does not

O.M.P. 54/2013 Page 4 mean that a party can be permitted an indefinite and unexplainable period for refilling the petition."

9. The twin arguments were raised by the petitioner for condonation of delay. Firstly, about the „new format‟ having been introduced. Hence, it took some time to re-format the objections after having obtained the correct format. Secondly, the fact that it was festive seasons which resulted in repeated holidays when the lawyers office was closed. Connected with this plea is the fact that the clerk of the counsel for the petitioner had also gone to his hometown for celebration of Diwali.

10. In this context reference may be had to the judgment of the Supreme Court in Northern Railway vs. M/s.Pioneer Publicity Corp.Pvt.Ltd. being Civil Appeal No.10340 of 2016. In that case the Supreme Court was dealing with an issue of condonation of delay of 65 days in re-filing the objections under section 34 of the Act. The Supreme Court held as follows:-

"Mr. Amarjeet Singh Chandiok, learned Senior Counsel appearing for the Respondent submitted that Section 34(3) of the Act bars re-filing beyond the period stipulated therein. The said sub-section reads as follows:

"34. (3) An application for setting aside may not be made after three months have elapsed from the date on which the party making that Application had received the Arbitral Award or, if a request had been made Under Section 33, from the date on which that request had been disposed of by the Arbitral Tribunal:

Provided that if the Court is satisfied that the Applicant was prevented by sufficient cause from making the Application within the said period of three months it may entertain the Application within a further period of thirty days, but not thereafter.

O.M.P. 54/2013 Page 5 We find that said Section has no Application in re-

filing the Petition but only applies to the initial filing of the objections Under Section 34 of the Act. It was submitted on behalf of the Respondent that Rule 5(3) of the Delhi High Court Rules states that if the Memorandum of Appeal is filed and particular time is granted by the Deputy Registrar, it shall be considered as fresh institution. If this Rule is strictly applied in this case, it would mean that any re-filing beyond 7 days would be a fresh institution. However, it is a matter of record that 5 extensions were given beyond 7 days. Undoubtedly, at the end of the extensions, it would amount to re-filing.

We are not inclined to accept this contention particularly since the Petitioner has offered an explanation for the delay for the period after the extensions.

Having regard to the overall circumstances of the case, we consider it appropriate in the interest of justice to set aside the impugned Order."

11. Keeping in view the legal position and the facts above, in my opinion, there are sufficient reasons given for the condonation of the delay which occurred. I may also note that the Award is against the respondent and in favour of the petitioner. The respondent has also filed objections under section 34 of the Arbitration and Conciliation Act which are pending. In view of the above, I allow the present application and condone the delay in re-filing the objections.

OMP 54/2013 List on 21.08.2017.

JAYANT NATH, J.

APRIL 28, 2017/v



O.M.P. 54/2013                                                              Page 6
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter