Citation : 2012 Latest Caselaw 3647 Del
Judgement Date : 31 May, 2012
IN THE HIGH COURT OF DELHI AT NEW DELHI
O.M.P. No. 439 of 2004
Reserved on: May 3, 2012
Decision on: May 31, 2012
DELHI DEVELOPMENT AUTHORITY .....Petitioner
Through: Ms. Geeta Mehrotra with
Mr. Rahul Tomar, Advocates.
Versus
H.S. KHANNA ..... Respondent
Through: Mr. Vivekanand, Advocate.
CORAM: JUSTICE S. MURALIDHAR
JUDGMENT
31.05.2012
1. Although this petition was filed under Section 34 of the Arbitration
and Conciliation Act, 1996 ('1996 Act') to challenge the Award dated 6th
July 2004 passed by the sole Arbitrator, inasmuch as the disputes
commenced before coming into the of the 1996 Act, a preliminary issue
arose as to whether the present proceedings should be under the
Arbitration Act, 1940 ('1940 Act'). I.A. No. 9572 of 2006 was filed by
the Delhi Development Authority ('DDA') for this purpose. The said
application was disposed of on 21st July 2009 with the Court clarifying
that the present case was under the 1940 Act and that the present petition
should be treated as objections under Sections 30 and 33 of the 1940 Act.
Accordingly the present petition has been considered as such by the
Court.
2. The disputes between the parties arose out of a contract awarded by
the DDA in favour of the Respondent for construction of 148 houses on
36 sq.m. plots including services in Shalimar Bagh, Block A, Pocket G.
An agreement dated 7th April 1980 was executed between the parties
wherein the date of commencement of the work was 5th April 1980 and
the date of completion was indicated as 4th October 1980. The work was
actually completed on 17th November 1984. Disputes that arose between
the parties were referred to arbitration by a sole Arbitrator who was
appointed by an Engineer-Member, DDA by his letter dated 1st August
1985. When the Respondent objected to the said appointment and filed
OMP No. 29 of 1989 under Sections 5, 8, 11 and 12 of the 1940 Act, this
Court by an order dated 24th August 1994 appointed Justice G.C. Jain
(retired), as Arbitrator. On the expiry of Justice G.C. Jain, a learned
Advocate of this Court was appointed as the sole Arbitrator and the
impugned Award was pronounced by him on 6th July 2004.
3. Of the twelve items of claims, the learned Arbitrator rejected Claim
Nos. 1, 5, 8, 9 and 10. The Respondent was awarded a total sum of Rs.
3,55,833 with pendente lite and future simple interest at 9% from the date
of proceedings till the date of payment.
4. Claim No. 2 was for an additional sum of Rs.75,000 under Clause
12(v) of the Agreement for the extra works executed. The case of
Respondent was that the previous contractor had not completed the work
awarded to him and the balance work was thereafter awarded to the
Respondent. By various letters, the Respondent informed the DDA about
the extra work that was executed and had also claimed extra payment.
The case of the DDA, on the other hand was that the additional work
alleged to have been executed by the Respondent had been paid for in the
Running Account bills ('RA bills') as extra works and these RA bills had
been accepted by the Respondent without protest. Secondly, it was
pointed out that since the Respondent had restricted its claim to Rs.
75,000 instead of Rs. 83,698 as originally claimed, it was apparent that
the claim was fictitious and was an afterthought. It was further
contended that the Respondent was supposed to maintain a day-to-day
record and the fact that the site order book was not made available by the
DDA to the Respondent, was not relevant to the execution of the alleged
extra works. By a letter dated 24th April 1981 the DDA informed the
Respondent that he had never been directed to execute any
extra/substituted items. However, the Respondent filed details of the
extra work exhibited as Ex. C-29.
5. The learned Arbitrator found that the items claimed by the
Respondent had not been included in the running bills. It was apparent
from the bill of the previous contractor that no payment had been made
for the various items. The second factor was that only some of the
measurement books ('MBs') could be produced by the DDA, and that too
after a considerable period. The Respondent also took a stand that there
were no MBs maintained which would show the extra work done by the
Respondent. Since the relevant records had not been produced by the
DDA, an adverse inference was drawn against it on a preponderance of
probabilities and it was held that the version of the Respondent was more
probable. Accordingly, Claim No. 2 was allowed in favour of the
Respondent.
6. The contention of DDA is that no reasons have been given by the
learned Arbitrator in coming to the above conclusion and that it is based
on surmises and conjectures. This Court does not find any merit in the
above contention for the simple reason that a perusal of the Award shows
that there is a detailed discussion in paras 16.1 to 16.5 of the Award as
regards Claim No. 2. The reasons are comprehensive and clear. If
indeed the DDA was unable to produce MBs to prove its claim that no
extra work was performed by the Respondent, then an adverse inference
had necessarily to be drawn against the DDA. This Court, therefore,
rejects DDA's objection to the Award as regards Claim No. 2.
7. Claim No. 3 was for a sum of Rs. 85,000 for the work executed but
not measured. Originally the Respondent had claimed a sum of Rs.
97,131.41 as per the details given in Ex. C-30. Later this claim was
restricted to Rs. 85,000. The work executed but not measured pertained
to "centering and shuttering; cement slurry; excavation in trenches;
dismantling of brick work; wrongful deduction; providing grooving in
plaster; reinforcement of overweight steel etc." The learned Arbitrator
referred to the correspondence between the parties and to the fact that
before the previous Arbitrator the DDA had sought opportunities from
time to time to carry out the measurement but failed to do so. On the
other hand, when the Respondent sought production of the site order
book, the overweight steel record and the day-to-day record of the
balance work maintained by the DDA, the DDA simply informed the
Respondent by a letter dated 6th January 1996 that the site order book and
steel register were not traceable, that the previous contractor's bill had
not been finalized and that it was not necessary to maintain a day-to-day
register. It was in those circumstances that the learned Arbitrator again
drew an adverse inference against the DDA since despite seeking several
adjournments it was unable to produce the relevant records. After
considering the amount of Tor Steel, the claim was restricted to Rs.
81,297.97 and learned Arbitrator awarded a sum of Rs. 81,298.
8. The objection of the DDA as far as the above Award is that all RA
bills have been accepted by the Respondent and that the Respondent
failed to submit any documents to support his claim. As already pointed
out, the failure by the DDA to produce relevant records, which could
have actually demonstrated its defence that it had paid for the work that
was measured, resulted in the learned Arbitrator drawing an adverse
inference. This was but natural considering that much of the
Respondent's claim was dependent on the records maintained by the
DDA itself. Therefore, there is no merit in this objection and it is
accordingly rejected.
9. Claim Nos. 4 and 5 were adjudicated together. Claim No. 4 was for
the restoration of a sum of Rs. 85,000 held under part rate statement and
extra and substituted items, and Claim No. 5 was for Rs. 15,000
wrongfully withheld by the DDA. While the Respondent contended that
the work was completed on 15th December 1981, the DDA relied on the
letter dated 17th November 1984 to show that the work was not
completed satisfactorily. During the course of arbitration the DDA
produced the 17th RA bill (Ex. R-28) from which it was apparent that an
amount of Rs. 1151.28 and Rs. 20,000 have been withheld on account of
rectification of defect vide M.B. No. 1084 on or about 1st June 1983.
Certain entries showed that a sum of Rs. 1651.20 was withheld. Further,
a sum of Rs. 2302.80 was withheld for anticipation of cement recovery.
10. The learned Arbitrator found that the fact that the work was
completed was demonstrated by the certificates issued by the officials of
the DDA. Ex. C-37 was one such certificate which not only recorded that
the work had been completed satisfactory but recommended that the
work of a bigger magnitude could be entrusted to the Respondent. It was
observed by the Arbitrator that in the facts and circumstances, the burden
was on the DDA to show that the work performed by the Respondent
was defective and not in accordance with the CPWD specifications.
Further, the Respondent had been paid only part of the rate without any
basis and the reduction of the rates by the DDA could not be done
unilaterally. In the circumstances, the claim in the sum of Rs. 29,506.16
was found to be justified. After accounting for the withheld sums, a total
sum of Rs. 51,157 was awarded against Claim No. 4.
11. The contention of the DDA in regard to the above claim was that the
completion certificate produced by the Respondent was a "procured one"
and is not correct and genuine. The learned Arbitrator has referred to Ex.
C-37 and C-38 which were certificates issued by the Engineer-in-Charge,
DDA. If indeed, it was DDA's case that the said certificate is not
genuine, it would have not only made an averment to that effect in its
reply to the statement of claim but also produced the concerned Engineer
to prove it. It did not do either of these things. It is not possible,
therefore, to determine at the present stage under Sections 30 and 33 of
the 1940 Act whether in fact the said certificates are genuine. This is a
matter of evidence which had to be led by the DDA before the Arbitrator,
and which it failed to do so. The objection in regard to Claim No. 4 is
therefore rejected.
12. Claim No. 6 was for a sum of Rs. 23,876 on account of removal and
disposal of excavated earth dumped on the lanes and inside the houses.
Again, from the letters written by the Respondent to the DDA on various
dates which were referred to by the learned Arbitrator, it was found that
the Respondent had excavated the earth to the extent of 1458.16 cubic
meter. Here again the relevant MBs which could have shown the
performance of this work by the Respondent, were not produced by the
DDA despite being granted various opportunities by the learned
Arbitrator. If the earth was excavated by the earlier contractor and he
was not paid for its removal and disposal, then it was probable that it
must have been removed by the Respondent. The learned Arbitrator
referred to the letters written by the Respondent giving the details of the
earth removed from different portions of the work. In particular the
learned Arbitrator referred to Annexure E of C-22 which gave the total
amount expanded on this account as Rs. 23,873.07. Therefore, there is
no merit in the objection that this claim was based on probabilities or that
the learned Arbitrator overlooked the correspondence relied upon by the
DDA. This is a matter of appreciation of evidence and the learned
Arbitrator cannot be faulted for arriving at the conclusion that the
Respondent was entitled to a sum of Rs. 23,873.
13. Claim No. 7 was for a sum of Rs. 94,505 being the amount paid
short on account of steel doors, windows and ventilators. The
Respondent was claiming this amount for cost of fixing and welding and
had written various letters to the DDA in this behalf. The case of the
DDA was that the payments had been made in the 17th RA bill. The
Respondent pointed out that the said bill only showed the payment of a
sum of Rs. 50,100.42 whereas the total claim was for a sum of Rs.
1,44,605.69 for the entire work of fixing of steel doors, windows and
ventilators.
14. After discussing the letters written by the Respondent to the DDA, it
was concluded by the learned Arbitrator that the facts stated in those
letters remained unrebutted. A perusal of 17th RA bill also showed that
the plea of the DDA that the entire amount was paid to the Respondent,
was not sustainable. Since the Respondent had been paid a sum of Rs.
50,100.42, the learned Arbitrator held that the balance amount is payable
to the Respondent. This again is a question of appreciation of evidence
and this Court is not expected to sit in appeal over the determination of
the learned Arbitrator in that behalf. This Court is unable to discern any
error apparent on the face of the Award in regard to Claim No. 7.
15. Claim No. 11 was for a sum of Rs. 30,000 on account of theft of
material against the secured advance. The material handed over to the
DDA was placed in the lock and key of the DDA. The goods were stolen
after the possession was taken from the Respondent. Nevertheless a sum
of Rs. 30,000 was recovered/deducted from the bill of the Respondent.
Reliance was placed on a letter dated 8th September 1981 (Ex. C-13)
whereby the DDA was informed by the Respondent that the material was
lying in DDA's custody and the Respondent should not be held liable for
the loss of that material. The contents of the said letter are not denied by
the DDA. The learned Arbitrator rightly observed that since the material
comprised of brass bib cocks and other materials which were prone to
theft and pilferage, the Respondent rightly did not install them and gave
them to the DDA. In the circumstances, it was held that the sum of Rs.
30,000 was wrongly deducted from the bill of the Respondent. The only
defence of DDA in regard to this claim was that it was the responsibility
of the Respondent to protect the material from theft. It cannot be said
that the conclusion drawn by the learned Arbitrator was an improbable
one. The inference drawn on a reading of letters written by the
Respondent to the DDA was plausible and cannot be faulted.
16. The award of simple interest at 9% under Claim No. 12 cannot be
said to be unreasonable.
17. There are no grounds made out for interference with the impugned
Award of the learned Arbitrator. The objections are hereby rejected.
The Award dated 6th July 2004 is made rule of the Court. The decree
sheet be drawn up accordingly.
18. The petition is disposed of.
S. MURALIDHAR, J MAY 31, 2012 akg
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!