Citation : 2009 Latest Caselaw 2038 Del
Judgement Date : 14 May, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ Date of Decision : 14.05.2009
% I.A. No. 1283/2000 in CS(OS) No. 1091A/1999
M/S. GANGADEEP BUILDERS PVT. LTD. ..... Petitioner
Through: Mr. Rohit Puri, Advocate
versus
M/S. MAHANAGAR TELEPHONE NIGAM LTD. ..... Respondent
Through: Mr. Harish Malhotra, Sr. Advocate
with Mr. Dipesh Sharma, Advocate.
CORAM:
HON'BLE MR. JUSTICE VIPIN SANGHI
1. Whether the Reporters of local papers may
be allowed to see the judgment? No
2. To be referred to Reporter or not? No
3. Whether the judgment should be reported
in the Digest? No
VIPIN SANGHI, J. (Oral)
1. These are objections preferred by the respondent MTNL to the
award passed by the learned Arbitrator Sh. N.K. Singhal, who was
appointed as the sole Arbitrator to adjudicate the claims and counter-
claims of the petitioner/claimant and respondent/non-claimant in
relation to the disputes which arose out of contract for construction of
Local Duct Network in Karol Bagh Exchange area bearing Contract
No.04/22/90. The learned Arbitrator was appointed by the Chief
General Manger, Delhi Telephones vide letter dated 20.05.1997. I may
notice at this stage that the arbitration agreement was invoked by the
petitioner on 01.12.1993 calling upon the respondent to appoint an
Arbitrator. Thereafter, the petitioner preferred Suit No.AA 62/96 under
Section 20 of the Arbitration and Conciliation Act, 1940 in this court on
17.05.1996. The said petition was disposed of by this court on
22.04.1997 directing the respondent to appoint the sole Arbitrator in
terms of the contract. It appears that only thereafter on 20.05.1997,
the Chief General Manager appointed Mr. N.K. Singhal as the sole
Arbitrator. By virtue of Section 21 of the Arbitration and Conciliation
Act 1996, the arbitral proceedings in respect of the claims of the
petitioner commenced with the request for them to be referred to
arbitration being made and received in December, 1993, i.e. prior to
the coming into force of the 1996 Act. Consequently, the arbitration
award in question is governed by the Arbitration Act 1940. I may also
notice that the parties have also proceeded on the foundation that the
arbitration proceedings and the award are governed by the provisions
of the Arbitration Act 1940. Consequently, the respondent has
preferred the objections under Section 5, 16, 30, 33 of the Arbitration
Act, 1940. The same have been filed on 11.01.2000 though the award
was made by the Arbitrator on 01.05.1999.
2. Mr. Harish Malhotra, learned senior counsel for the
respondent/objector has argued specific objections in relation to Claim
Nos.1, 2, 3, 6, 9, 12 and 14 and the award made on counter-claim Nos.
1, 2 and 3. Claim No. 1 was made by the petitioner/claimant on
account of escalation in the price of PVC Pipes. Before the sole
Arbitrator the said Claim was made for Rs.20,63,255/-. The amount
was revised to Rs.11,35,151/- before the Arbitrator. The learned
Arbitrator has allowed this claim for Rs.11,35,151/-.
3. The basis for making this claim was that the respondent MTNL
had not allowed escalation in PVC Pipes prices beyond the extended
date of completion on the plea that the contractor had failed to
complete the work.
4. The learned Arbitrator returned the finding that permission for
road cutting was not available from MCD in such a manner that work
could be continuously carried out. In fact, the contractor continued to
execute the work even when permission was not available. This
caused losses by way of material and T&P being taken away and the
labour of the contractor being disbanded by the MCD staff. The
Arbitrator held that the period of completion of eight months was fixed
by not taken into consideration the possibility of the road cutting
permission not being available.
5. The learned Arbitrator made his award by taking into
consideration para 8 of Clause 70 on page 120 of the agreement which
reads as follows:
"The escalation of price on PVC pipe is applicable only upto the original date of completion as per stipulation in the contract. However, if the delay in completion is beyond
the control of the contractor and works are agreed to be executed beyond the stipulated completion period, such escalation / de- escalation is permissible."
6. It is also seen that so far as the quantity and the rates of PVC
pipes are concerned, the learned Arbitrator adopted the quantity and
rate as verified by the respondent in its letter dated 15.04.1999.
7. There is no objection raised by the respondent to the
recording of these facts and figures. The only submission of Mr.
Malhotra, learned senior counsel for the objector was that for the
period after extension of time had expired, and no further extension
had been granted, no escalation could be awarded. He also submitted
that sales tax and transportation was not to be paid since it was
included in the price. He further submits that the learned Arbitrator
held that the contractor was not to blame for delay as road cutting
permission was not available. He submits that at the same time, even
the MTNL was not responsible for the said permission not being
granted by MCD and, therefore, the MTNL could not be saddled with
the escalation costs.
8. In my view, there is no merit in these objections of the
respondent. On a reading of the award, the period for which the
escalation has been awarded is not discernible. The award has been
made under Arbitration Act 1940 and there was no contractual
requirement that the award had to contain reasons. Even otherwise,
since the petitioner/claimant had continued to execute the works even
beyond the period for which extension was granted, the claimant
would be entitled to claim escalation since it was established before
the learned Arbitrator that the petitioner/claimant was not responsible
for delay in the execution of the work. So far as the submission with
regard to the inclusion of sales tax and transportation in the claim for
escalation is concerned, I see no merit in the same as the quantity and
rates for computation of escalation were verified by the respondent.
There is nothing to suggest that the escalation awarded is inclusive of
sales tax and transportation.
9. Merely because the respondent consider itself not responsible
for the road cutting permission not being available, it does not follow
that the contractor could have been asked to bear, or even share the
burden of escalation on account of such permission not being
available. Admittedly, it was for the respondent to arrange for, and
obtain the necessary permission for road cutting from the MCD. If the
same was not so arranged, the burden would fall on the
employer/respondent and not on the contractor. Consequently, I reject
the objections to the award on Claim No.1.
10. So far as Claim No. 2 is concerned, the same was made for Rs.
4,55,000/- for work done but not paid. The amount was reduced to Rs.
3,58,206/- vide letter dated 09.11.1998 before the Arbitrator. The
finding of the learned Arbitrator on this Claim is a pure finding of fact.
He has held that the work had been carried out as per the directions of
the respondent and he has allowed the same partly for Rs. 45,000/-. In
my view, there is no merit in the objection to this particular Claim and
no specific objection has been raised by the respondent.
11. Claim No. 3 was made by the claimant/petitioner for
Rs.8,11,882/- towards refund of retention money lying with the
respondent. This included retention money in cash as well as in the
form of bank guarantees. The only justification given by the
respondent for retaining the retention money was that the work had
not been completed and tested. The learned Arbitrator held that after
the abandonment of the work, since 1993 no effort was made by the
respondent to get the work completed. The cost adjustment for
deficiencies in work has been separately discussed in Claim No. 12. In
these circumstances the learned Arbitrator allowed the refund of
Rs.5,79,703.80/- which had been deducted in cash, and released by
bank guarantees of Rs.2,32,178.20/-.
12. Mr. Malhotra argued that the learned Arbitrator had wrongly
concluded that no action has been taken by the respondent to get the
work completed. However, he has not been able to point out from the
record as to how the said finding could be said to be perverse or
contrary to the record. Since the work had to be abandoned as the
road cutting permission was not available, in any event, there could be
no justification for withholding the retention money of the claimant. I
find no error in the award made on Claim No.3. The objection of the
respondent is, therefore, rejected.
13. In respect of Claim No.6, which was made for Rs.22,95,000/-
on account of loss of idle staff and establishment, the learned
Arbitrator awarded the amount of Rs.3,52,550/-. The learned
Arbitrator restricted the Claim on the ground that it was well within the
knowledge of the contractor that road cutting permission is not within
the hands of the respondent. Further, work had been stopped due to
non-payment of escalation charges.
14. The submission of Mr. Malhotra is that the learned Arbitrator
has not given any reasons for arriving at the amount of Rs.3,52,550/-
awarded by him on Claim No.6. As aforesaid, there was no obligation
for the Arbitrator to give a reasoned award. It is not open to the court
to go behind the award and to enquire into the reasons which may
have prevailed upon the Arbitrator in making his award. Consequently,
I reject the objection made by the respondent to the Claim No. 6.
Same is the position with regard to Claim No. 7 which had been made
by the claimant for Rs. 66,51,500/- towards hiring charges/depreciation
of machinery, and had been allowed by the Arbitrator to the extent of
Rs. 1,00,000/-.
15. Claim No. 9 had been made by the claimant for Rs. 5,00,000/-
as bank charges/commission for extending bank guarantees beyond
stipulated period. The Claim had been revised to Rs. 91,984/- vide
letter dated 09.11.1998. The learned Arbitrator hold that since the
work had not been completed due to various reasons beyond the
control of both the parties, the actual expenditure incurred by the
claimant should have been reimbursed. Consequently, the Claim was
allowed for Rs. 91,984/- and the respondent was also directed to
release the expired bank guarantee within 30 days from the
publication of the award. I find no merit in the objection raised to this
part of the award on account of the extension of the contract. The
claimant could not have been made to suffer towards bank
charges/commission for extending the validity of the bank guarantee.
The objection to the award on Claim No.9 is, therefore, rejected.
16. So far as Claim No. 12 is concerned, I find that no objection
has been raised in the objection petition to the award on Claim No.12.
Consequently, I do not consider it necessary to go into the objection
argued by Mr. Malhotra.
17. The next objection raised by Mr. Malhotra is to the award
made in Claim No. 14 which was the claim for interest at the rate of
24% per annum. The learned Arbitrator awarded simple Interest at the
rate of 16.5% on the amount of Rs. 23,64,388.80/- which is the
aggregate of amount awarded on Claim Nos. 1, 2, 3, 6, 7, 9 and 12
w.e.f. 01.12.1993 to 30.04.1999 (the award was made on 01.05.1999).
The amount of interest for the aforesaid period has been worked out at
Rs. 21,13,171.20/-. Further interest at the rate of 15 per cent has been
allowed on the amount of Rs. 45,27,560/- which is the aggregate of the
principle awarded amount of Rs. 23,64,388.80/- and the interest
thereon calculated up to 30.04.1999. The Arbitrator has awarded
interest on the aforesaid aggregate amount at the rate of 15% per
annum in case the payment is not made within 60 days from the date
of publication of the award till payment.
18. The submission of Mr. Malhotra is that the Arbitrator has, in
the aforesaid manner, awarded compound interest, inasmuch as, on
the amount of Rs.21,13,171.20/- which was the component of interest
for the period of 01.12.1993 to 30.04.1999 further interest has been
awarded at the rate of 15% per annum. He also submits that the rate
of interest awarded by the learned Arbitrator is on the higher side.
19. Having considered the submissions of the parties, I am of the
view that the learned Arbitrator could not have awarded interest on
interest. There was no agreement between the parties for award of
interest to the petitioner/claimant. Even otherwise, I find that the rate
of interest awarded is on the higher side considering that in such like
awards, the interest at the rate of 9-12 per cent has been maintained
by the courts. Consequently, I modify the award on Claim No. 14. The
rate of interest for all the periods is reduced from 16.5% and 15% to
9% per annum. It is further directed that on the amount worked out as
interest for the period 01.12.1993 to 30.04.1993, on the principle
awarded amount or Rs.23,64,388.80/-, no further interest shall accrue
and interest shall continue to run only on the principle liability of
Rs.23,64,388.80/- at the aforesaid rate of 9% per annum till realization.
20. Mr. Malhotra has then submitted that the award on Counter-
claim No.1 is erroneous. The MTNL had made the said Claim to
recover the road restoration charges paid by the MTNL from the
petitioner claimant. The said claim was rejected by holding that there
is no such provision in the contract for the contractor to bear such
charges. I find no error in the award since no clause of the contract
has been placed before me which fastens the liability towards payment
of road restoration charges on the contractor. Objection to the award
on Counter-claim No.. 1 is, therefore, rejected.
21. In respect of Counter-claim No.. 2, which was made for
Rs.1,17,532/- towards repair charges payable to MCD for 12" dia water
pipeline, I find that the claimant had agreed to pay the amount as per
actual expenditure incurred by MTNL towards the said repair. It was
for the respondent MTNL to substantiate the said claim to claim
reimbursement. However, it appears that was not done. In view of the
aforesaid, there possibly cannot be any objection to the award made
by the Arbitrator. The award on Counter-claim no.2 is therefore
rejected.
22. Counter-claim No. 3 was made towards liquidated damages
towards 10% of the contract value. The learned Arbitrator has rejected
the same and, in my view, rightly so by holding that the work had been
delayed beyond the control of both the parties and, therefore, levy of
such compensation was not justified. Only in the event of it being
established that the delay in the execution of the work was attributable
to the claimant contractor, liquidated damages could have been
imposed under the contract. Since that is not the case, in my view, no
error can be found in the award made by the learned Arbitrator.
23. For the aforesaid reasons the award made by the learned
Arbitrator Mr. N. K. Singhal, dated 01.05.1999 is made "Rule" of the
court subject to the modification made as aforesaid in relation to the
award of interest under Claim No. 14. Parties are left to bear their
respective costs.
VIPIN SANGHI, J.
MAY 14, 2009 dp
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!