Citation : 2022 Latest Caselaw 5547 Chatt
Judgement Date : 6 September, 2022
1
NAFR
HIGH COURT OF CHHATTISGARH BILASPUR
WPC No. 1359 of 2022
• M/s Rana G Power Co., House No. 2752/02,
Samanbamdh Area, Behind Life Shepherd School, Ward
No. 15, The Hujur Nagar, Rewa- 486001, Madhya
Pradesh
Through- its Authorized Representative, Mr. Satish Singh
Tiwari S/o Lt. Shri Mahaveer Singh Tiwari, aged about 52
years, residing at House No. 2752/02, Samanbamdh
Area, Behind Life Shepherd School, Ward No. 15, The
Hujur Nagar, Rewa- 486001, Madhya Pradesh.
---- Petitioner
Versus
1. South Eastern Coalfields Limited Through its Chairman
cum Managing Director, SECL Headquarters, Seepat
Road Bilaspur, Chhattisgarh 495006.
2. Area General Manager, Dipka Area, South Eastern
Coalfields Limited Dist. Umaria, Madhya Pradesh.
3. Ms. Baghel Infrastructure (P) Ltd. Bhagel and Co
Aramachine CHOPAN, Dist. Sonebhadra, State Uttar
Pradesh, 231205
---- Respondents
(Cause-title taken from Case Information System)
For Petitioner : Mr. Aman Saxena, Advocate
For Respondents : Mr. Vaibhav Shukla and Ms. Astha Shukla,
Advocates
Date of hearing : 07.07.2022
Date of order : 06.09.2022
Hon'ble Shri Arup Kumar Goswami, Chief Justice
Hon'ble Shri Parth Prateem Sahu, Judge
C A V Order
Per Parth Prateem Sahu, J
Petitioner by way of filing this writ petition under Article 226
of the Constitution of India has challenged the letter of
2
communication of the order dated 07.1.2022 (Annexure P/1) issued
by respondent No.2 by which Letter of Intent ('LOI') bearing No.
SECL / BSP/ CMC/ LOA/ e-NIT-463/JOH/2021-22/1182 dated
22.10.2021 was cancelled, petitioner firm was banned for a period of
24 months from participating in any future tender in South Eastern
Coalfields Limited ('SECL') and subsidiaries of Coal India Limited
('CIL') and penalty of Rs.52,67,06,535.95 (Rupees Fifty Two Crore
Sixty Seven Lakh Six Thousand Five Hundred Thirty Five and
Ninety Five paise only) was imposed.
2. Facts
relevant for disposal of this writ petition, are that,
petitioner is a joint venture of Ranavir Projects & Goldmine Power
Infrastructure Industries engaged in civil constructions and other
works. Respondent No.1 issued e-Tender (Annexure P/3) vide
Tender Notice No.SECL/BSP/CMC/e-Tender/463 dated 15.07.2021
for "Hiring of HEMM for all kind of strata/overburden loading into
tippers, transportation and unloading excavated materials & silt,
dumping, scraping/removal of bands, preparation and maintenance
of haul road, water sprinkling and spreading of excavated material at
the site shown and as per directives of the management/engineer in
charge at Kanchan Open Cast Mine of Johilla Area" of sub-work (a)
21,05,566.000 cubic meter (soft/loose soil) including drain quantity;
sub-work (b) 3,68,89,630.000 cubic meter (Hard Strata); total total
quantity of over burden of 3,89,95,196.000 Cubic meter (including
drain quantity of both sub-works) for a period of 1095 days with
minimum excavation of 35612 cubic meter per day. Petitioner along
with other tenderers submitted their bids, in which petitioner became
successful being L-1 bidder. Petitioner was issued LOI on
22.10.2021. As per requirement of tender conditions, petitioner was
required to furnish Performance Security Deposit ('PSD') in
prescribed form, details of which is given under Instructions to
Bidders. The amount of PSD was quantified as Rs.2,63,35,327/-,
which is equal to 3% of the annualized value of contract amount.
The period prescribed for furnishing PSD was 21 days from the date
of issuance of LOI. Petitioner on 20.11.2021 wrote letter to
respondent No.2 submitting bank draft towards Bank Guarantee
from the EMERIO BANQUE Ltd. (Bank) for approval of SECL. The
Bank was a foreign bank. Petitioner wrote letter on 22.11.2021 to
respondent No.2 for approval of submitting bank draft towards Bank
Guarantee of Rs.2,63,35,327/- from EURO EXIM BANK LTD., a
foreign bank and thereafter another letter for approval of submitting
bank guarantee of the aforementioned amount from EUROPA Bank
Public Limited Company, a foreign bank. Petitioner failed to submit
PSD as required in terms of tender document, which made the
respondent No.2 to issue letters reminding the petitioner to submit
PSD within the stipulated period. Petitioner failed to submit PSD in
the form of Bank Guarantee in terms of tender document. Show-
cause notice issued by respondent No.2 was replied by the
petitioner and thereafter, considering the reply submitted to show-
cause notice to be non-satisfactory, order of cancellation of LOI,
banning the petitioner for a period of 24 months and penalty of
Rs.52,67,06,535.95 was issued. This made the petitioner to
approach this Court by way of filing this writ petition seeking
following reliefs :
"10.1 Quash the entire impugned Order dated 07.1.2022 (Annexure P/1) on account of it being violative of principles of natural justice, arbitrary, contrary to article 14 rule of law and being illegal.
10.2 Direct the Respondent SECL to accept the bank guarantee of EUROPA BANK Public Limited as valid on account of ECL having already accepted the same, to treat equals as equal under article 14.
10.3. Quash the fresh e-tender proceedings dated 12.01.2022 (Annexure P/2) as the tender notice dated 15.07.2021 and the LOA granted to the Petitioner continues to be valid on account of quashing of Impugned Order and acceptance of aforesaid bank guarantee.
10.4.Any other relief/reliefs, which this Hon'ble Court may think fit and proper in the facts and circumstances of the case may also please be granted to the Petitioner.
10.5. Quash the LOA dated 25.03.2022
issued to respondent no.3 as LoA granted to the Petitioner continue to be valid on account of quashing of impugned order and acceptance of aforesaid bank guarantee."
3. Respondents submitted reply to the writ petition raising
preliminary objection of maintainability of writ petition on the ground
of availability of efficacious alternative remedy under clause 13 &
13A of the Conditions of Contract. Further raised objection of
involvement of disputed facts. The dispute is a commercial
contractual dispute. There is delay and laches on the part of
petitioner in filing writ petition as petitioner approached the Court
after lapse of about more than two months from the date of passing
of the orders under challenge. It is pleaded that petitioner failed to
comply with the terms and conditions of tender document, not
furnished PSD of Scheduled Bank as required, not signed the
Integrity Pact & Agreement and failed to commence the work.
Therefore, after issuance of show-cause notice, order terminating
the LOI, forfeiture of Earnest Money Deposit ('EMD'), banning of
petitioner from participating in future bids and penalty of 20% of
value of work in terms of clause 9.2(c) of General Terms and
Conditions was issued. It is also pleaded that draft copy of bank
guarantee issued from Europa Bank Public Limited Company and
Emerio Banque Ltd., Chennai (Foreign Banks) sent by email, was
not acceptable in view of clause 4.2 of General Terms and
Conditions and clause 24.1 of Instructions to Bidders because the
Bank of which Bank Guarantee was submitted, was not a Scheduled
Bank. New tender is finalized and LOA dated 25.3.2022 is also
issued in favour of L1 M/s Baghel Brothers (Annexure R-3) and new
contractor already commenced the work.
4. Mr. Aman Saxena, learned counsel for the petitioner would
submit that action taken by respondent No.2 by way of issuance of
impugned order (Annexure P/1) is per se illegal and arbitrary. After
issuance of LOI, petitioner submitted PSD through Bank draft issued
by EMERIO BANQUE to the tune of INR Rs.2,63,35,327.00, a
Foreign Bank located at Kalaignar Karunanidhi Nagar, Chennai.
Clause 24.1(b) of Instructions to Bidders permits submission of Bank
Guarantee of Foreign Bank. Though as per clause 24, PSD is to be
submitted within 21 days from issuance of LOI, tender document
provides discretion of management for extending period by 14 days
on case to case basis, and therefore, delay, if any, in submitting
Bank Guarantee towards PSD is within the zone of discretion for
extension of time provided under tender document. Tender
document clearly prescribes for acceptance of Bank Guarantee of
Scheduled Bank or Foreign Bank located in India. Non acceptance
of the Bank Guarantee of EMERIO BANQUE Ltd. (Foreign Bank) or
other foreign banks, branch located in India, is arbitrary in view of
clause 24.1 (b) of Instructions to Bidders and 4.2 (b) of General
Terms and Conditions. Bank Guarantee of EMERIO BANQUE Ltd.
EURO EXIM BANK had been accepted by other Government
Departments and Organizations including National Highway
Authority of India and Directorate of Education Ministry, New Delhi. It
is submitted by him that another subsidiary of CIL i.e. Eastern
Coalfields Limited accepted the Bank Guarantee issued by
EUROPA Bank, and therefore, action taken by respondent -SECL is
discriminatory in not accepting the Bank Guarantee issued by
EMERIO BANQUE Ltd. Ltd. (Foreign Bank). He further contended
that in show-cause notice dated 30.11.2021, there is no specific
mention of proposed action of imposing penalty, but for cancellation
of LOI and banning for a minimum period of 24 months. After receipt
of show-cause notice dated 30.11.2021, petitioner immediately
submitted reply and had shown willingness to work and to submit
PSD. Order Annexure P/1 dated 07.1.2022 was passed without
application of mind and the same is a non-speaking order. It is
contended that respondent No.1 further erred in issuing fresh e-
Tender on 12.1.2022 and awarding it to respondent No.3.
Cancellation of LOI, banning and imposition of penalty is violative of
principles of natural justice. He pointed out that reading of clause 9.2
of General Terms and Conditions would show that penalty can be
imposed upon termination of contract or cancellation of contract,
whereas in the case at hand, there was no contract between the
parties. The show-cause notice was inadequate. In support of his
contention, he places reliance on the judgment passed by Hon'ble
Supreme Court in cases of Tata Cellular v. Union of India, reported
in (1994) 6 SCC 651 and Jagdish Mandal v. State of Orissa and
Others, reported in (2007) 14 SCC 517 and the orders passed by
this Court in Writ Petition (C) No.2856 of 2020 decided on
12.02.2021 (M/s. SBJ Projects (P) Ltd. v. South Eastern
Coalfields Limited & Another) and in Writ Petition (C) No.2577 of
2020, decided on 16.02.2021 (M/s Jai Ambey Roadlines v. South
Eastern Coalfields Limited & Another).
5. Per contra, Mr. Vaibhav Shukla, learned counsel for the
respondents would submit that, submission of learned counsel for
the petitioner that order impugned is passed in violation of principles
of natural justice and without application of mind is per se wrong. He
contended that the idea and understanding of petitioner that Bank
Guarantee of EMERIO BANQUE Ltd. being a Foreign Bank is in
accordance with terms and conditions of tender document, is also
not correct. In tender document under clause 4.2 of General Terms
and Conditions, there is a condition of furnishing 3% of annualized
value of contract amount or contract value whichever is lower within
a period of 21 days from issuance of LOA as PSD. It clearly
mentions the demand draft drawn on any of the Scheduled Banks.
Along with form of Bank Guarantee for performance security, list of
Scheduled Commercial Banks is also enclosed including Public
Sector Banks, Private Sector Banks and Foreign Banks. In the list of
Scheduled Foreign Banks, name of EMERIO BANQUE Ltd. and
EUROPA BANK of which petitioner furnished draft copy of Bank
Guarantee sent by email, is not mentioned, and therefore, draft copy
of Bank Guarantee submitted by the petitioner after prescribed
period of 21 days was found to be non-acceptable. It is submitted by
him that when tender document bears specific terms and conditions
of submission of Bank Guarantee from any of the Scheduled Banks,
it is for the petitioner to fulfill the requirement in terms of the
conditions as mentioned in tender document. When petitioner failed
to furnish Bank Guarantee as required under tender document and
failed to execute agreement, letter was issued to the petitioner
before expiry of period of 21 days reminding for submission of PSD
on 28.10.2021, 9/10.11.2021, 15.11.2021 and 22.11.2021. By letters
dated 20.11.2021 and 26.11.2021 petitioner was advised to submit
bank guarantee of scheduled foreign bank. Respondents have
given ample time and intimation for submission of PSD and to start
the work. As the Bank Guarantee submitted was of non-Scheduled
Bank, respondents have rightly not accepted the same,
consequently, show-cause notice was issued. Petitioner submitted
reply to show-cause notice, which was found to be non-satisfactory
and only thereafter, order impugned (Annexure P/1) was passed.
There is no illegality or arbitrariness in the action of respondents.
Principles of natural justice has been followed, amount of penalty is
also quantified and calculated in accordance with terms and
conditions of tender document. He also submits that no relief can be
granted to the petitioner as the petitioner is having efficacious
alternative remedy as provided under clause 13 of tender document
of settlement of disputes and clause 13A for settling the dispute
through arbitration. In support of his contention, he places reliance
upon the judgment of Hon'ble Supreme Court in cases of State of
Gujarat and Others v. Meghji Pethraj Shah Charitable Trust and
Others, reported in (1994) 3 SCC 552, State of U.P. and Others v.
Bridge & Roof Company (India) Ltd., reported in (1996) 6 SCC 22,
Kerala State Electricity Board and Another v. Kurien E. Kalathil
and Others, reported in (2000) 6 SCC 293 and Kisan Sahkari
Chini Mills Limited and Others v. Vardan Linkers and Others,
reported in (2008) 12 SCC 500.
6. We have heard the learned counsel appearing for the
parties and have perused the materials on record.
7. The root cause of passing the order dated 7.1.2022
Annexure P/1, cancelling the Letter of Intent dated 22.10.2021;
banning the petitioner firm for a period of 24 months from
participating in any future tender in respondent SECL and imposing
penalty of Rs.52,67,06,535.95, is that the petitioner failed to submit
Bank Guarantee towards PSD within the period prescribed in tender
document of the Scheduled Bank or of Bank acceptable to the
respondent.
8. To appreciate the submission of learned counsel for
respective parties, we find it appropriate to extract relevant clauses
of tender document including Instructions to Bidders and General
Terms and Conditions. Clause 24 of Instructions to Bidders deals
with performance security / security deposit. Relevant portion of
clause 24.1(i) reads as follows :
"24. PERFORMANCE SECURITY / SECURITY DEPOSIT
24.1 Security Deposit shall consist of two parts:
x x x
x x x
(i) Performance Security should be 3% of annualized value of contract amount or contract value whichever is lower (For contract having period upto 5 years) or (ii) Performance Security should be 5% of annualized value of contract amount (for long terms contract i.e. for a period exceeding 5 years) and should be submitted within 21 days of issue of LOA by the successful bidder in any of the form given below:
A Bank Guarantee in the form given in the bid document from any scheduled Bank. The BG issued by outstation bank shall be operative at its local branch at ------or branch at-----
Govt. Securities, FDR (Scheduled Bank) or any other form of deposit Stipulated by the owner.
Demand Draft drawn in favour of
...................on any Scheduled Bank
payable at its Branch at ........
The Earnest Money/Bid Security deposited is to be returned to the contractor after submission of performance security. The Earnest Money/Bid Security deposited may be adjusted against the security deposit (Performance Security) at Bidder's choice.
If performance security is provided by the Successful bidder in the form of bank guarantee it shall be issued either-
(a) at Bidder's option by a Scheduled Bank
or
(b) by a foreign bank located in India and acceptable to the employer.
9. Clause 4.2 of General Terms and Conditions of contract reads as
follows :
"4.2 Performance Security (first part of security deposit) should be 3% of annualized value of contract amount or contract value whichever is lower (For contract having period up to 5 years) or 5% of annualized value of contract amount
(for long terms contracts i.e. for a period exceeding 5 years and should be submitted within 21 days of issue of LOA by the successful bidder in any of the form given below:
A Bank Guarantee in the form given in the bid document from any scheduled Bank. The BG issued by outstation bank shall be operative at its local branch at ......or branch at......."
10. Clauses as mentioned above talk about Bank Guarantee
from any Scheduled Bank at bidders option. It is not in dispute
that Scheduled Bank means Banks forming part of list maintained by
Reserve Bank of India, which includes list of Scheduled Commercial
Banks, i.e., list of Scheduled Public Sector Banks, list of Scheduled
Private Sector Banks, list of Scheduled Small Finance Banks, list of
Scheduled Payment Banks, list of Scheduled Regional Rural Banks
and list of Scheduled Foreign Banks in India. List of Scheduled
Banks is filed by petitioner as Annexure P/9 in another writ
petition filed by petitioner bearing WPS No.1914/2022 which was
dismissed vide order dated 17.8.2022. Both the writ petitions were
heard together.
11. Perusal of list of Scheduled Foreign Banks in India would
show that name of EMERIO BANQUE Ltd. and EUROPA BANK of
which petitioner has submitted draft copy of Bank Guarantee (after
prescribed period of 21 days), does not find place. After submission
of draft copy of Bank Guarantee by the petitioner through email,
respondent No.2 immediately intimated the petitioner vide email
dated 20.11.2021 (Annexure R-7) that draft copy of Bank Guarantee
submitted was not acceptable. Original copy of bank guarantee of
scheduled bank is acceptable as per terms. The petitioner was
intimated that he is required to submit Bank Guarantee towards PSD
within 26.11.2021 (extended period).
12. The submission of learned counsel for the petitioner that
clause 24 of Instructions to Bidders provides for an option for
submission of Bank Guarantee issued by Scheduled Banks or
Foreign Banks located in India and Bank Guarantee submitted by
the petitioner being of a Foreign Bank is in accordance with terms of
the tender document is not acceptable in view of the specific words
used under clause 24.1(i)(b).
13. Clause 24.1(i)(b) of Instructions to Bidders clarifies the
Foreign Banks located in India "to be acceptable to the employer".
The words used in aforementioned clause "to be acceptable to the
employer" is with some purpose and only with an intent that the
employer should be satisfied with the credential of the non-
scheduled Bank, of which tenderer has submitted the Bank
Guarantee.
14. It is further case of the petitioner that the respondents have
intimated the petitioner on 20.11.2021 that Bank, of which copy of
draft towards Bank Guarantee submitted through e-mail is not
acceptable. It is not the case of the petitioner that respondents have
not given sufficient time to produce required Bank Guarantee of
Scheduled Banks. In another writ petition bearing WPC
No.1914/2022 intimation of not accepting bank guarantee of non-
scheduled foreign bank was given by respondents on 7.10.2021.
Even after intimating the petitioner that the Bank Guarantee
submitted was not acceptable and further specifying the period for
submitting the Bank Guarantee as prescribed under Clause 24.1 of
the instructions to Bidders, the petitioner failed to submit required
Bank Guarantee. Respondent SECL is a separate company under
CIL, and therefore, even if, the submission of learned counsel for the
petitioner is taken to be correct that any other coal company had
accepted Bank Guarantee from non scheduled Foreign Bank
(EUROPA BANK) the same will not be binding upon the
respondents. Here, in the instant case, respondents issued tender
notification mentioning terms and conditions, and therefore, as per
clause 24.1 of Instructions to Bidders and clause 4.2 of General
Terms and Conditions, Bank Guarantee submitted of a Foreign Bank
must be to the acceptance of respondent/SECL.
15. In case of Jagdish Mandal (supra), relied upon by learned
counsel for the petitioner, consideration before Hon'ble Supreme
Court was whether the decision of non-acceptance of the EMD of
the lowest tenderer with evidently low rate and awarding the work to
L-2 bidder is proper. In the said judgment, Hon'ble Court held thus :
"33. ................ If the committee found that the tender of fifth respondent should be rejected on that ground, the said decision cannot be termed as unreasonable or arbitrary. The committee has applied its mind and rejected the tender by assigning a reason which is neither irrational nor arbitrary. Neither the High Court nor this Court can sit in appeal over such technical assessment. There is no infirmity in the decision making process or the decision."
16. In case of Tata Cellular (supra), Hon'ble Supreme court has
laid down the principles, on which power of judicial review can be
exercised. It was held thus :
"77. The duty of the court is to confine itself to the question of legality. Its concern should be:
1. Whether a decision-making authority exceeded its powers?
2. Committed an error of law,
3. committed a breach of the rules of natural justice,
4. reached a decision which no reasonable tribunal would have reached or,
5. abused its powers.
Therefore, it is not for the court to determine whether a particular policy or particular decision taken in the fulfillment of that policy is fair. It is only concerned with the manner in which those decisions have been taken. The extent of the duty to act fairly will vary from case to case. Shortly put, the grounds upon which an administrative action is subject to control by judicial review can be classified as under:
(i) Illegality : This means the decision- maker must understand correctly the law that regulates his decision-making power and must give effect to it.
(ii) Irrationality, namely, Wednesday unreasonableness.
(iii) Procedural impropriety.
The above are only the broad grounds but it does not rule out addition of further grounds in course of time. As a matter of fact, in R. v. Secretary of State for the Home Department, ex Brind, (1991) 1 AC 696, Lord Diplock refers specifically to one development, namely, the possible recognition of the principle of proportionality. In all these cases the test to be adopted is that the court should, "consider whether something has gone wrong of a nature and degree which
requires its intervention."
17. In the case at hand, there is specific clause under
Instructions to Bidders specifying that Bank Guarantee shall be
submitted in the form of Bank Draft by a Foreign bank located in
India and acceptable to the employer. The Foreign Bank of which
copy of draft towards Bank Guarantee forwarded through email is
not Scheduled Foreign Bank. Non acceptability of the Bank
Guarantee to the employer was known to the petitioner. In view of
above, we do not find any arbitrariness in the decision making
process of the respondent.
18. We are of the view that there is no arbitrariness on the part
of respondents in holding that petitioner failed to comply with terms
and conditions of tender document after issuance of LOI.
19. Next question for consideration before this Court is whether
proceedings initiated by respondents are in accordance with law
following principles of natural justice. Issuance of show-cause notice
to the petitioner dated 30.11.2021 is not in dispute as copy of show-
cause notice is filed along with writ petition as Annexure P/13, to
which petitioner also submitted its reply vide Annexure P-14 dated
13.12.2021 through e-mail.
20. Perusal of show-cause notice would show that petitioner
was asked to submit a written explanation within a period of fifteen
days mentioning clauses of the General Terms and Conditions.
Relevant portion of show-cause notice is extracted below for ready
reference :
"....As you have neither furnished the Performance Security Deposit nor commenced the work till date even after communications made with you as referred, the management is entitled for Banning of Business with your for minimum 12 months from participating in future bidding, forfeiture of EMD and also termination/cancellation of LOI/ contract.
In view of the above this notice/show cause notice is hereby served to you to explain why not the mentioned subject work awarded to you shall be cancelled/ terminated and business with you shall be banned for minimum 12 months as per the conditions of the contract as stated above. You are advised to present your stand/defense in writing or in person within a period of 15 days to this office, failing which it shall be presumed that you have nothing to state in your defense and the management will be constrained to proceed further in accordance with the conditions of the contract.
Please treat this letter as FINAL NOTICE."
21. Perusal of aforementioned contents of show-cause notice
would reflect that in show-cause notice, there is specific mention of
action to be taken against bidder who failed to submit the PSD
within the stipulated time to cancel the work awarded (LOA),
banning for a minimum period of 12 months and forfeiture of EMD.
As there is specific mention of consequential action to be taken
against the petitioner of cancellation of award of work and also of
banning the petitioner it can not be said that said actions were
without providing opportunity of hearing to the petitioner. As such
principles of natural justice were followed towards those actions.
22. In tender matters, it is to be seen whether the decision taken
by authorities exceeded its power, reached a decision which no
reasonable tribunal or authority could have reached; whether
principle of natural justice is followed or not. In the facts of the case
as discussed in preceding paragraphs, we do not find any good
ground to interfere with the order of cancellation of LOI, forfeiture of
EMD and banning of petitioner for a period of 24 months.
23. So far as the action taken against the petitioner in the
impugned order of penalty under clause 9.2(ii) of General Terms and
Conditions is concerned, there is no notice to the petitioner for
taking such action against him. Respondents have placed on record
show-cause notice dated 30.11.2021. Show-cause notice does not
mention proposed action to be taken against petitioner with regard
to penalty. There was no proper and specific notice for the said
action to be taken against petitioner and, hence, the order impugned
(Annexure P/1) so far as it relates to imposition of penalty of
Rs.52,67,06,535.95 (Rupees Fifty Two Crore Sixty Seven Lakh Six
Thousand Five Hundred Thirty Five and Paise Ninety Five only), is
beyond the contents of show-cause notice issued to the petitioner.
24. It is settled law that no action can be taken against anyone
by surprise. Absence of specific mention of proposed action to be
taken against the petitioner of imposing penalty and its recovery,
deprived him of pleading defense in reply to the show cause notice
on the said action. The action of respondents of imposing penalty
and its recovery though forming part of terms and conditions of
tender document, but without notice, is in violation of principles of
natural justice. Hence, in the opinion of this Court, it is not
sustainable.
25. In case of UMC Technologies Private LImited (supra),
Hon'ble Supreme Court has held thus :
"13. ......The basic principle of natural justice is that before adjudication starts, the authority concerned should give to the affected party a notice of the case against him so that he can defend himself. Such notice should be adequate and the grounds necessitating action and the penalty/action proposed should be mentioned specifically and unambiguously.
An order travelling beyond the bounds of notice is impermissible and without jurisdiction to that extent. This Court in Nasir Ahmad v. Assistant Custodian General, Evacuee Property, U.P., Lucknow and Another, (1980) 3 SCC 1, has held that it is essential for the notice to specify the particular grounds on the basis
of which an action is proposed to be taken so as to enable the noticee to answer the case against him. If these conditions are not satisfied, the person cannot be said to have been granted any reasonable opportunity of being heard."
26. The case law relied upon by the respondent in State of
Gujarat & Ors. Vs. Meghji Pethraj Shah Charitable Trust (supra)
is distinguishable on facts. It was a case of granting admission in
professional college by Trust under some arrangement deed
between the Trust and the Chief Minister of the State and the
admission was found to be contrary to the law. Case law of Bridge
& Roof Company (India) Ltd. (supra) was a dispute of deduction
of sales tax from the payment due to the contractor. Hence, it is on
different sets of fact. In case law of Kurien E. Kalathil and other
(supra), the dispute was with regard to interpretation of the terms
and conditions of contract. In case law Vardan Linkers & Others
(supra) relied by counsel for the respondent, dispute was of
cancelling the order by Secretary. Hon'ble Supreme Court, while
discussing the issue, was of the view that unless the writ Court
found the Secretary's order to be arbitrary or unreasonable it should
have desisted from interfering with it. In the case at hand, the order
of penalty is without specific show cause notice.
27. As discussed above, respondents have imposed huge
amount of penalty without issuing show-cause notice, in violation of
principles of natural justice. Considering dictum of Hon'ble Supreme
Court in cases of Gorkha Security Services (supra) and UMC
Technologies Private Limited (supra), we are of the view that
order Annexure P/1 to the extent of imposing penalty of
Rs.52,67,06,535.95 (Rupees Fifty Two Crore Sixty Seven Lakh Six
Thousand Five Hundred Thirty Five and Paise Ninety Five only) is
not sustainable and it is hereby quashed. This is without prejudice to
the rights and liberties of the respondents to proceed with further
steps in this regard by issuing a proper notice calling for explanation
and to pass order afresh after affording an opportunity of hearing to
the petitioner in this regard. The other part of the order Annexure P/1
is not interfered with.
28. The writ petition is allowed in part to the extent as indicated
above.
Sd/- Sd/-/- /-
(Arup Kumar Goswami) (Parth Prateem Sahu)
Chief Justice Judge
roshan/-
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!