Citation : 2022 Latest Caselaw 4677 Chatt
Judgement Date : 22 July, 2022
-1-
NAFR
HIGH COURT OF CHHATTISGARH, BILASPUR
Judgment Reserved on 01.07.2022
Judgment Delivered on 22.07.2022
ARBA No. 13 of 2020
1. State Of Chhattisgarh Through The Dy. Secretary, Government Of
Chhattisgarh, Water Resources Department, Mahanadi Bhawan,
Mantralaya, Atal Nagar , Nava Raipur Chhattisgarh...(Applicant No. 01),
District : Raipur, Chhattisgarh
2. Superintendent Engineer Barnai Canal Division, Water Resources
Department, Ambikapur , District Surguja Chhattisgarh...(Applicant No. 2)
3. Executive Engineer Barnai Canal Division , Water Resources Department
Ambikapur District Surguja Chhattisgarh...(Applicant No. 03)
---- Appellants
Versus
M/s. R.S. Bajwa And Company B- 4, Minocha Compound, Bilaspur ,
District Bilaspur Chhattisgarh..(Non Applicant), District : Bilaspur,
Chhattisgarh
---- Respondent
For Appellants : Shri Amrito Das, Addl. Advocate General
For Respondent : Shri Rajkamal Singh and Shri Suryapratap
Yuddhveer Singh, Advocates
D.B. : Hon'ble Shri Justice P. Sam Koshy &
Hon'ble Shri Justice Parth Prateem Sahu
CAV Judgment
Per Parth Prateem Sahu, J.
1. Appellants-State have filed this appeal under Section 13 of the
Commercial Courts Commercial Division and Commercial Appellate
Division of High Courts Ordinance, 2015 read with Section 37 of the
Arbitration and Conciliation Act, 1996 (for short "the Act of 1996")
challenging the order dated 28.11.2019 passed by Commercial Court
(District Level), Atal Nagar, Raipur, Chhattisgarh in Arbitration MJC
No.01/2019 whereby Presiding Officer of the Commercial Court dismissed
the application under Section 34 of the Act of 1996 on merits as well as
on the ground of limitation.
2. Facts relevant for disposal of this appeal are that respondent-Contractor
was awarded with the work of construction of Dam Overflow Block No.7, 8
& 9 in the erstwhile State of Madhya Pradesh. An agreement was
executed between the erstwhile State of Madhya Pradesh and
respondent, work order was issued on 25.03.1983. Contractor was paid
an amount of Rs.2,61,22,270/- for the work performed under the
agreement and final payment was made on 12.10.1994 (as pleaded in the
appeal). Some dispute arose between the parties to agreement.
Respondent submitted an application under Clause 52 of the agreement
executed between the parties, for appointment of sole Arbitrator vide
application dated 07.01.2006. Initially, the Chief Engineer (retired) was
appointed as sole Arbitrator but later on, he was replaced by appointing
Superintending Engineer as sole Arbitrator. After conclusion of the
arbitration proceedings, sole Arbitrator passed an award on 22.08.2006 in
favour of respondent-Contractor awarding Rs.2,19,64,449/-. Award
passed by the sole Arbitrator was submitted for its execution under Order
21 Rule 11 of CPC.
3. Appellants- State filed an objection before the Executing Court under
Order 21 Rule 26 read with Section 151 of CPC pleading therein that in
view of Section 3 of the Chhattisgarh Madhyastham Adhikaran Adhiniyam,
1983 (for short "Adhiniyam of 1983"), the award passed by sole Arbitrator
is without jurisdiction. Madhyastham Adhikaran (Arbitration Tribunal) was
constituted on 1st March 2005 whereas sole Arbitrator was appointed on
13th March 2006. The work awarded to respondent- Contractor was of the
nature of civil construction work. Cause of action arose on 20 th May 2005
whereas Arbitration Tribunal was constituted on 1st March 2005. Hence,
the Chief Engineer was not having jurisdiction to appoint sole Arbitrator.
Objection filed by the appellants was allowed on 05.05.2007 and the
application for execution filed by respondent-Contractor herein was
rejected.
4. This order of rejecting the application for execution of award passed by
sole Arbitrator was put to challenge by the respondent-Contractor by way
of filing writ petition bearing WP(C) No.3700 of 2008 seeking quashment
of the order dated 05.05.2007 by the District Judge, Ambikapur, District-
Sarguja in execution case. Writ petition filed by respondent-Contractor
came to be dismissed taking note of Section 20 of the Adhiniyam of 1983
and held that the Arbitration Tribunal was not having jurisdiction to make
an award. Respondent-Contractor aggrieved by the order passed in writ
petition filed Writ Appeal No.208 of 2008 which was allowed. The order
passed in Writ Petition by learned single Judge was set aside.
Consequently, order passed in execution proceedings by the District
Judge was also set aside. The case was remitted back to the District
Judge with a direction to decide application for execution of the award in
accordance with law.
5. Against the order passed in writ appeal, the appellant-State filed review
application which also came to be dismissed. The order passed by the
Division Bench in Writ Appeal No.208 of 2008 was put to challenge before
Hon'ble Supreme Court in Civil Appeal No.3666-3667 of 2012 which was
allowed and the case was remitted back to Division Bench of this Court
holding that other points would require consideration by the High Court.
Division Bench of the High Court, after receiving back the case in remand,
again heard counsel for respective parties and observed that against the
order under challenge in Writ Petition (C) No.3700/2008, civil revision
would lie. Direction was issued to Registry of High Court for registering
the Writ Petition (C) No.3700 of 2008 as Civil Revision and directed
learned Single Judge to decide Civil Revision on its own merits keeping in
view the observation made by Hon'ble Supreme Court in its order dated
17.4.2012. The Civil Revision was registered bearing No.7/2013. Learned
single Judge allowed the Civil Revision, set aside the order of learned
District Judge, Sarguja and restored the execution proceedings in the file
of learned District Judge. Further direction was issued to proceed in
execution proceedings in accordance with law. The appellant-State
aggrieved by the order passed by learned single Judge in Civil Revision
again filed SLP which was registered as Civil Appeal bearing No.11383 of
2017 which was decided on 8th March 2018. Appellant-State, thereafter
taking shelter of the order passed by Hon'ble Supreme Court filed an
application under Section 34 of the Act of 1996 read with Sections 5 & 14
of the Limitation Act, 1963 before the Commercial Court at Raipur. The
Commercial Court vide order dated 28.11.2019 dismissed the application
on the ground of delay as also observing that second application under
Section 34 of the Act of 1996 after rejection of first is not maintainable. It
is this order of Commercial Court which is under challenge in this appeal.
6. Shri Amrito Das, learned Addl. Advocate General appearing for
appellants-State submits that prior to this appeal, there were multiple
proceedings initiated by both the sides pursuant to dispute arose under
work order dated 25.03.1983 and the agreement executed between the
parties. He contended that the contract awarded in favour of respondent-
Contractor is one under the works contract. If any dispute arose between
the parties under the agreement entered into between them of works
contract, it will govern with the provision of Adhiniyam 1983. Provision of
the Act of 1996 would not be made applicable to such disputes. He
submits that prior to making application for appointment of sole Arbitrator,
Arbitration Tribunal under the Adhiniyam 1983 was constituted. Hence, on
the date Chief Engineer entertained the application for appointment of
sole Arbitrator on 07.01.2006, he was not having jurisdiction to appoint
sole Arbitrator under the provision of the Act of 1996. Even if the sole
Arbitrator was appointed contrary to Adhiniyam of 1983 and award was
passed, it would be a nullity in the eyes of law. It is submitted that learned
Commercial Court has not considered the entire facts and circumstances
of the case as also the tenor of the order passed by Hon'ble Supreme
Court wherein Hon'ble Supreme Court, in very specific term, has
protected the interest of appellants, observing that the order passed by
Supreme Court will not affect the remedy available under the Act of 1996,
which enables the appellants to invoke the provision under Section 34 of
the Act of 1996. The Commercial Court misunderstood the order passed
by Hon'ble Supreme Court and dismissed the application under Sections
5 & 14 of the Limitation Act as also the application under Section 34 of the
Act of 1996. The proceedings initiated by the respondent- Contractor,
from its inception, was illegal and without jurisdiction. He submitted that
appeal be allowed and the entire proceedings and award passed by sole
Arbitrator be set aside.
7. Shri Rajkamal Singh, learned counsel appearing for respondent-
Contractor would submit that appellants-State after taking work from the
respondent-Contractor are avoiding to make actual payment. He submits
that learned Commercial Court in impugned order of rejecting application
under Section 34 of the Act of 1996 clearly recorded that appellants have
earlier filed one more application under Section 34 of the Act of 1996
which was dismissed on the ground of limitation. The said order was not
put to challenge by the appellants, but they chose to raise objection in
the execution proceedings filed by the respondent. Appellants participated
in the arbitration proceedings before the sole Arbitrator but has not raised
any objection with regard to its jurisdiction. They, for the first time, raised
objection with regard to appointment of sole Arbitrator and his jurisdiction
to pass award in the execution proceedings i.e. after passing of award.
Hence, now the appellants could not raise the said objection which was
initially waived. Executing Court dismissed the execution application
which travelled to High Court and thereafter to Supreme Court. The
Supreme Court remitted back the case to High Court. High Court, after
receiving the case back in remand from Hon'ble Supreme Court has set
aside the order passed by the District Judge, Ambikapur, District-Sarguja,
holding that the executing Court has no jurisdiction to nullify the award
and allowed the Civil Revision. The order passed by learned single Judge
in Civil Revision was put to challenge before Hon'ble Supreme Court and
Hon'ble Supreme Court declined to interfere with the order passed by
learned single Judge, observing that the order passed by Hon'ble
Supreme Court will not affect the remedy of appellants under the Act of
1996, which does not mean to file again an application under Section 34
of the Act of 1996 knowing well that the first application under Section 34
of the Act of 1996 came to be dismissed much earlier in the year 2011.
Second application under the same provision and on similar facts is not
maintainable. Commercial Court discussed the entire facts and
circumstances of the case and have rightly dismissed the application
under Section 34 of the Act of 1996 to be not maintainable as also to be
barred by limitation and, therefore, it does not call for any interference.
8. We have heard learned counsel for the parties and also perused the
record of the Arbitration Appeal as also the compilation of the
applications, proceedings initiated by both the sides as also different
orders passed by the District Judge in Execution Case No.1 of 2007,
order passed by learned Single Judge in Writ Petition (C) No.3700 of
2008 challenging the rejection of execution application, order passed by
Division Bench in Writ Appeal No.208 of 2008, order passed in Review
Application No. 8 of 2011, order passed by Hon'ble Supreme Court in
Civil Appeal No.3666-3667 of 2012, order dated 18 th August 2011 passed
by District Judge, Sarguja (Ambikapur) in Civil Suit No. 12-A/2011
dismissing the application under Section 34 of the Act of 1996, order
passed in Writ Appeal No.208 of 2008 on 20.9.2012 after receiving back
the case on remand pursuant to order passed by Hon'ble Supreme Court
and order dated 12.05.2017 passed in Civil Revision No. 7 of 2013
passed in the case received on remand from coordinate Bench of this
Court wherein the Writ Petition No.3700/2008 was directed to be
converted into Civil Revision and order dated 8th March 2018 passed by
Hon'ble Supreme Court in Civil Appeal No.974 of 2012 (Madhya Pradesh
Rural Road Development Authority & Anr. Vs. M/s. L.G. Chaudhary
Engineers and Contractors) and batch of Civil Appeal including Civil
Appeal No.11383/2017 (arising from this proceeding as stated by counsel
for appellants).
9. During the Course of argument, this Court put specific query to learned
Addl. Advocate General for the State whether any objection with respect
to jurisdiction of sole Arbitrator was raised initially during arbitration
proceedings or not. He contended that the proceedings before the sole
Arbitrator was bi-parte proceedings and it is not appearing from the record
that any objection with regard to the jurisdiction of the sole Arbitrator was
raised. Perusal of the impugned order would show that learned
Commercial Court (District Level) dismissed the application under Section
34 of the Act of 1996 on two grounds, firstly on the ground that the
application to be hopelessly barred by limitation and also considered that
the appellants in the application under Section 34 of the Act of 1996 have
not specifically pleaded that earlier also appellants have filed an
application under Section 34 of the Act of 1996 which came to be
dismissed in the year 2011 i.e. 18th August 2011.
10. The second application under Section 34 of the Act of 1996 is filed under
the garb of order passed by Hon'ble Supreme Court on 8th March 2018 in
Civil Appeal No.11383/2017, which reads as under:-
"C.A. No.11383/2017:
Heard learned counsel for the parties.
We do not find any ground to interfere with the
impugned order. However, this order will not affect the
remedy of the appellants under the Arbitration and
Conciliation Act, 1996.
The appeal is disposed of in above terms."
11.For better understanding the purport of order passed by Hon'ble Supreme
Court we would like to again discuss the history of proceedings in this
appeal. Respondent- Contractor was awarded with the works contract
and an agreement to this effect was executed between the parties. The
said agreement bears the arbitration clause in Clause -52 of the
agreement. Respondent-Contractor raised dispute before the authority
and when it was not given any heed to, respondent filed an application for
appointment of sole Arbitrator. Application was allowed and the claim of
Contractor was considered by the Superintending Engineer (sole
Arbitrator) appointed by the Chief Engineer who passed the award which
was bi-parte award as stated by both the counsel. Before the sole
Arbitrator, objection of jurisdiction to entertain arbitration proceeding by
sole Arbitrator was not raised as admitted by counsel for the appellants
based on the documents available. Award passed by the sole Arbitrator
was put to execution by filing an application under Order 21 Rule 11 CPC.
In the execution proceeding, appellants raised objection which was
allowed and the application for execution was dismissed. This was put to
challenge before the High Court in Writ Petition (C) No.3700/2008 and
learned Single Judge dismissed the writ petition. The order passed in writ
petition was put to challenge in appeal before Division Bench of this Court
which was allowed. Order of Division Bench was challenged before the
Hon'ble Supreme Court. Hon'ble Supreme Court, observing that ruling
relied upon by Division Bench in case of VA Tech Escher Wyass Flovel
Flowr Ltd. Vs. Madhya Pradesh State Electricity Board and Anr (2011) 13
SC 261 has been reversed by the subsequent decision and other points
would require consideration, remitted back the matter to the High Court.
After receiving back the case on remand Division Bench of High Court
directed that writ petition be converted to Civil Revision. Accordingly, Civil
Revision was registered and came up for hearing. Learned Single Judge
allowed the revision petition taking note of the provision under Section 16
(2) of the Act of 1996 that the appellants have waived their opportunity to
plead and object, judgment passed by Hon'ble Supreme Court in the case
of M/S. MSP Infrastructure Ltd. Vs. M.P. Road Development Corp. Ltd.
decided on 05.12.2014. Order passed by learned District Judge, Sarguja
dismissing the execution application was set aside and it was directed to
proceed in the execution proceedings in accordance with law.
12. The order passed in Civil Revision was challenged before Hon'ble
Supreme Court as argued by the appellant in Civil Appeal
No.11383/2017. Hon'ble Supreme Court declined to interfere with the
order passed in Civil Revision No.7/2013. Hon'ble Supreme Court has
only observed that the order passed by the Supreme Court will not affect
the remedy of appellants under the Act of 1996.
13. Observation made by Hon'ble Supreme Court that "this order will not
affect the remedy available to the appellants herein under the Arbitration
and Conciliation Act, 1996" would definitely does not mean the remedy of
challenging the award dated 22/08/2006 passed by sole Arbitrator, under
Section 34 of the Act of 1996 again when the application under Section
34 filed by the appellant herein challenging the said award passed by the
sole Arbitrator was dismissed by the District Judge, Sarguja (Ambikapur)
much earlier on 18th August 2011 in Civil Suit No.12-A/2011. In the facts
of the case, filing of application again under Section 34 of the Act of 1996
challenging the same award passed by the sole Arbitrator on 22.08.2006
is not permissible under law. Plain reading of the observation made by
Hon'ble Supreme Court in its order dated 8th March 2018, in the opinion of
this Court, would mean further proceedings available to the appellants
pursuant to award passed by the sole Arbitrator which will be in
continuation. It does not provide availing of the same remedy which the
appellants have already availed under the Act of 1996.
14. For the foregoing discussions, submission of learned counsel for the
appellants-State that the observation made by Hon'ble Supreme Court in
order dated 8th March 2018 provides them remedy to file application
under Section 34 of the Act of 1996 is misconceived. Hence, the said
submission made by learned counsel for appellants is not sustainable
and it is repelled. As we have arrived at the conclusion that once the
application under Section 34 of the Act of 1996 challenging the arbitral
award dated 22.08.2006 passed by sole Arbitrator Mr. C.M. Malhotra
came to be dismissed vide order dated 18th August 2011 in Civil Suit No.
12-A/2011 by District Judge, Sarguja (Ambikapur), the second application
challenging the same award under the same provision i.e. under Section
34 of the Act of 1996 is not maintainable and, therefore, we are not
further dealing with the issue of limitation as projected in application
under Section 14 of the Limitation Act filed along with the application
under Section 34 of the Act of 1996.
15. For the foregoing discussions, we do not find any error in the finding
recorded by learned Commercial Court in impugned order that the
application under Section 34 of the Act of 1960 itself is not maintainable
and the said finding is affirmed.
16. Consequently, the Arbitration Appeal being devoid of any substance is
liable to be and is accordingly dismissed.
Sd/- Sd/-/-
(P. Sam Koshy) (Parth Prateem Sahu)
17. Judge Judge
Praveen
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!