Tuesday, 19, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

(Earlier Known As Board Of Trustees Of ... vs Marinecraft Engineers Private Limited
2025 Latest Caselaw 1749 Cal/2

Citation : 2025 Latest Caselaw 1749 Cal/2
Judgement Date : 13 June, 2025

Calcutta High Court

(Earlier Known As Board Of Trustees Of ... vs Marinecraft Engineers Private Limited on 13 June, 2025

Author: Sabyasachi Bhattacharyya
Bench: Sabyasachi Bhattacharyya
                             In the High Court at Calcutta
                              In Its Commercial Division
                          Ordinary Original Civil Jurisdiction

     The Hon'ble Justice Sabyasachi Bhattacharyya



                              A.P.-COM No.296 of 2024
                              (Old No. A.P. 179 of 2023)

                         The Board of Major Port Authority
                   for the Syama Prasad Mukherjee Port, Kolkata
            (earlier known as Board of Trustees of the Port of Kolkata)
                                         Vs.
                        Marinecraft Engineers Private Limited




     For the petitioner             :     Mr. Krishnaraj Thaker, Adv.,
                                          Mr. Ashok Kr. Jena, Adv.

     For the respondent             :     Mr. Shounak Mukhopadhyay, Adv.,

Mr. S. Bhattacharya, Adv., Ms. Anewesha Guha Roy, Adv., Mr. Abhijit Guha Roy, Adv.

     Heard on                       :     08.07.2024, 29.11.2024,
                                          31.01.2025, 25.04.2025
                                          and 16.05.2025.

     Hearing concluded on           :     16.05.2025.

     Judgment on                    :     13.06.2025.



     Sabyasachi Bhattacharyya, J.:-

1. The present application under Section 34 of the Arbitration and Conciliation

Act, 1996 (hereinafter referred to as "the 1996 Act") has been preferred

against an award passed in respect of a claim filed by the respondent herein

in a reference under Section 18 of the Micro, Small and Medium Enterprises

Development Act, 2006 (for short, "the 2006 Act").

2. Initially, conciliation proceedings commenced under Section 18(2) of the

2006 Act. Subsequently, the present petitioner having failed to appear in

the said proceedings, it was recorded by the Micro and Small Enterprises

Facilitation Council (in brief, "the Council") that the conciliation had

terminated. The dispute was accordingly taken up for resolution by

arbitration under sub-section (3) of the Section 18 of the 2006 Act.

3. Learned counsel appearing for the petitioner contends that the impugned

award is a nullity, since the mandate of the Council as the arbitral tribunal

had already terminated when the award was passed, by operation of Section

29-A of the 1996 Act, the provisions of which statute were applicable in

terms of Section 18(3) of the 2006 Act. The mandatory timeline as stipulated

in Section 29-A(1) of the 1996 Act, it is argued, had expired before passing

of the award.

4. Learned counsel next argues that the principles of natural justice were

violated by the Council in failing to grant adequate opportunity to the

present petitioner to place its case on merits before the Council. It is argued

that initially the matter came up for conciliation. Upon termination of the

conciliation, however, no opportunity was granted to the petitioner to argue

its case on merits. The Council proceeded on the premise that the parties

had already placed their respective cases by way of their written statements;

however, denying opportunity to advance oral arguments to the petitioner.

This, it is contended, brings the award within the purview of Section 34 of

the 1996 Act for violation of the fundamental policy of Indian Law and basic

notions of justice.

5. The petitioner next argues that no GC-3 Form was submitted by the

respondent/claimant, which was mandatory for disbursal of the dues of the

claimant as per the contract between the parties, as borne out by the tender

document. Thus, the award is vitiated, having not taken into consideration

such aspect of the matter and the legal effect thereof. It is argued that the

claimant/respondent did not become entitled to get its dues, even if any, in

view of non-submission of such Form.

6. On merits, learned counsel for the petitioner argues that the Council erred

in law and committed patent illegality in allowing the respondent‟s claims in

respect of the illegal deductions and interests and other aspects of the

matter. It is submitted that the Council could not have proceeded on the

concessions given during conciliation proceedings but ought to have

independently adjudicated the dispute on merits by granting opportunity of

hearing to the petitioner.

7. It is further submitted that the Council initiated conciliation amid the

arbitration proceedings and, as such, committed a patent illegality in

deciding the matter on merits during such conciliation attempts, by

construing the said proceedings to be an arbitral proceeding under Section

18(3) of the 2006 Act.

8. Learned counsel for the petitioner next argues that the Council committed

jurisdictional error amounting to patent illegality in delegating its authority

by leaving the task of computing the interest to the claimant/respondent,

through its designated Chartered Accountant (CA). Learned counsel cites

Usha Martin Limited v. Eastern Gases Limited, reported at 2022 SCC OnLine

Cal 3342, as well as an unreported judgment in AP No.90 of 2023

[Government of Maharashtra v. Shrivin Pharma], both Co-ordinate Bench

decisions of this Court, in support of such contention.

9. Learned counsel for the petitioner, during oral arguments, submits that the

dispute between the parties pertains to a "Works Contract" and, as such, is

not amenable to the jurisdiction of the Council under the 2006 Act,

although such point was not elaborated much in the written notes of

arguments filed by the petitioner.

10. Learned counsel for the respondent/claimant controverts the above

submissions and submits that it has been settled by this Court that the

provisions of Section 29-A of the 1996 Act are not applicable, particularly

insofar as the timelines are concerned, to a proceeding under the 2006 Act.

In such context, learned counsel cites a judgment of this Court in Porel Dass

Water & Effluent Control Private Limited v. West Bengal Power Development

Corporation Limited and others, reported at 2024 SCC OnLine Cal 8927.

11. Learned counsel for the respondent next takes the court through the various

dates of the arbitral proceeding, as reflected in the impugned award of the

Council, to show that sufficient opportunity was given at every stage to the

petitioner to address the dispute on merits. It is submitted that the

petitioner filed its Statement of Defence as well as written statement,

including notes of arguments, and also, on several occasions, addressed the

Council on the merits of the dispute.

12. On the issue of natural justice, it is argued that the reliance by the

petitioner on Ssangyong Engineering and Construction Company Limited v.

National Highways Authority of India (NHAI), reported at (2019) 15 SCC 131

is misplaced, since adequate opportunity of hearing was given to the

petitioner in the present case.

13. Learned counsel for the respondent next argues that GC-1 and GC-2 Forms

were duly submitted and, on the basis of those, the petitioner had certified

and approved the completion of the work by the claimant/respondent. A

GC-3 Form, it is contended, is only submitted when there is no further

dispute regarding the dues, since it is in the nature of a "No Dues

Certificate". There was no occasion for the respondent to submit such

Form, since the dues of the respondent were not cleared by the petitioner,

which is the very crux of the present dispute.

14. Insofar as the merits of the claim are concerned, it is argued that the

Council dealt with the matter at length, considering the arguments of both

sides as well as their pleadings, and accordingly came to its conclusions. It

is submitted that the Council equally considered the contentions of both

parties and, in fact, a part of the claim was not granted by the Council as

well. Thus, there cannot be a reopening of the award under Section 34 of

the 1996 Act.

15. Insofar as the attempts at conciliation during arbitral proceedings are

concerned, learned counsel for the respondent points out that such efforts

were taken only at the behest of the petitioner itself and did not partake the

character of pre-arbitral conciliation, since such stage was already over and

the Council had made it clear that the pre-arbitral conciliation had failed

and was terminated, fixing the matter for arbitration.

16. It is submitted that the power of the Council of adjudicating interest was not

delegated to a CA. The Council came to specific conclusions as to the date

from which and the rate at which the interest is payable. Thus, it was

merely the arithmetical calculations which were left to the CA.

17. Hence, it is argued that the decisions cited by the petitioner on such count

are not germane in the context of the present case.

18. Learned counsel relies on (2021) 3 SCR 1044 [M/s Silpi Industries v. Kerala

State Road Transport Corporation & Anr.] for the proposition that the 2006

Act is a beneficial legislation to be read for the benefit of MSME units such

as the respondent and that Sections 15 to 23 of the 2006 Act have

overriding effect on any other statute, including the 1996 Act.

19. Insofar as Work Contracts are concerned, it is argued that such contracts

came within the ambit of adjudication by arbitration by the Council under

the 2006 Act, provided the concerned unit is registered as an MSME Unit

under the Act, which criterion is met by the respondent in the present case.

Learned counsel cites Hindustan Petroleum Corporation Limited v. West

Bengal State Micro, Small Enterprises Facilitation Council, reported at 2023

SCC OnLine Cal 1700 in such context.

20. Upon hearing learned counsel for the parties, it transpires that several

issues have cropped up for consideration, which are dealt with sequentially

as follows:

Bar under Section 29-A of the 1996 Act

21. This issue was dealt with at length in Porel Dass (supra), where it was held

that the timeline stipulated under Section 29A of the 1996 Act are not

applicable to an arbitral proceeding under the 2006 Act. Rather, the period

stipulated under Section 18(5) of the 2006 Act is the relevant guiding factor.

However, the latter period is directory and not mandatory.

22. It has to be noted here that the 2006 Act is a special statute insofar as

MSME Enterprises are concerned and is a piece of beneficial legislation in

aid of such units. The provisions of the Act, including the non obstante

clause in Section 18 of the 2006, makes it abundantly clear that in case of

conflict between two statutes, the 2006 Act would prevail.

23. The power of the Council to arbitrate disputes arising in respect of MSME

units flows from Section 18 of the 2006 Act and not the 1996 Act. Sub-

section (3) of Section 18 of the 2006 Act confers such power and enables the

provisions of the 1996 Act to apply to such disputes. Thus, it has to be kept

in mind that the arbitration contemplated under the 2006 Act emanates

from the said statute (and not from the 1996 Act), and Section 18 the 2006

Act provides a complete eco-system of pre-arbitral conciliation, followed in

case of failure of the same by arbitration.

24. A composite reading of Section 29A of the 1996 Act and Section 18 of the

2006 Act clearly shows that there is a direct conflict between the two

provisions as to the respective timelines provided for completion of an

arbitral proceeding under the two statutes.

25. In the first place, the timeline of twelve months under sub-section (1) of

Section 29-A of the 1996 Act is made applicable to the date of completion of

pleadings under sub-section (4) of Section 23 of the said Act. Section 23 of

the 1996 Act operates within the window of the 1996 Act, under which

arbitral proceedings are commenced in terms of Section 21 of the 1996 Act.

As opposed thereto, the commencement of an arbitral proceeding under

Section 18 of the 2006 Act is under sub-section (3) of Section 18 itself, on

failure of conciliation proceedings. Thus, Section 29A of the 1996 Act does

not come into play at all in respect of such arbitral proceedings before the

Council, which are commenced under and by virtue of the 2006 Act.

26. As opposed to the timeline stipulated in Section 29A (1) of the 1996 Act,

sub-section (5) of Section 18 of the 2006 Act independently stipulates period

of 90 days from the date of making the reference for the completion of the

arbitral proceedings. On a proper reading of sub-section (5) of Section 18, it

is seen that although the expression "shall" has been used, the provision is

couched not in a negative way, debarring the Council from proceeding with

the reference after the expiry of 90 days, in stark contradistinction with sub-

section (4) of Section 29A of the 1996 Act which stipulates that the mandate

of the arbitrator itself terminates after the timeline stipulated in sub-Section

(1) of Section 29A expires, unless the mandate is extended in terms of sub-

Section (4) the said provision. As opposed thereto, Section 18 or, for that

matter, any other provision of the 2006 Act, does not carry any sanction

(such as termination of the mandate of the Council) or penalty for non-

completion of the reference within the said period.

27. Whereas Section 29-A of the 1996 Act hits at the very mandate of the

arbitral tribunal, rendering the tribunal functus officio after the expiry of the

stipulated time, Section 18(5) merely nudges the Council to adhere to a

timeline for the completion of the reference, without translating over-

stepping such period into a termination of the mandate of the Council itself.

28. In fact, a contrary interpretation would frustrate the very purpose of the

enactment of the 2006 Act, which categorically clothes the Facilitation

Council under the 2006 Act to conduct the arbitral proceedings in respect of

MSME Enterprises. If it is construed that the mandate of the Council

terminates after 90 days, the necessary corollary would be that it would be

open to the court, functioning independently under the 1996 Act, to

substitute the Council by any other arbitrator, or for the parties to initiate

fresh arbitral proceedings under the 1996 Act, thereby taking the arbitral

process itself beyond the pale of the 2006 Act, which is an absurd

interpretation, contrary to the very object and purpose of the 2006 Act.

Another possible corollary to such termination of the mandate of the Council

after 90 days would be that a fresh arbitral proceeding would be initiated

before the Council itself or the arbitrator appointed by it, which would be an

exercise in futility, since the Council or its appointed arbitrator would then

be already in seisin of the matter, having substantially completed the

arbitral process.

29. The root of the power of the Council is in consonance with the object of the

2006 Act, which is the promotion and development and enhancing the

competitiveness of MSME units, a part of which is early terminus to

disputes relating to such units by alternative dispute resolution, first by

conciliation and, if it fails, then followed by arbitration, by the Council or its

designated arbitrator under the aegis of the 2006 Act itself.

30. As such, the argument of the petitioner that the Council became functus

officio and the award was a nullity, due to the expiry of the timeline

stipulated in Section 29-A of the 1996 Act (or even under Section 18(5) of

the 2006 Act), cannot be accepted and is decided in the negative.

Violation of natural justice

31. The petitioner has alleged that the Council violated the principles of natural

justice by denying it opportunity of arguing on the merits of the case.

32. The impugned award itself contains the gist of the minutes of the previous

meetings of the Council, both at the conciliation stage and at the arbitration

stage. At the pre-arbitral conciliation stage, it was recorded by the Council

in its minutes dated February 16, 2016 that as the buyer unit (present

petitioner) was absent, it was not possible to amicably settle the matter and

a second notice for conciliation was issued to the parties. The petitioner

repeated its absence, due to which on November 16, 2016, the Council

recorded that the conciliation procedure as per Section 18(2) of the 2006 Act

had failed due to the abstinence of the petitioner in the conciliation

meetings. The Council decided simultaneously that the arbitration process

would be initiated as per the provisions of Section 18(3), in its minutes

dated November 16, 2016 itself.

33. Notice of termination of the conciliation process was issued vide Letter No.

D/845(2)/2017 dated December 4, 2017. Although the respondent initially

did not get a copy thereof, subsequently, the same was served on it. The

petitioner never complained that such notice was not served on it.

34. We find from the award that the claimant/respondent had submitted its

Statement of Facts before the Council with a copy to the buyer unit/present

petitioner. The petitioner also duly submitted its Statement of Defence as

well as points of arguments. The summary of the points raised by both the

parties in their respective pleadings were recorded at length in the impugned

award.

35. From the minutes dated February 26, 2018, it is found that despite being

aware since the year 2016 that arbitral proceedings were commenced on

termination of conciliation, the buyer unit (present petitioner) prayed for

time to submit written statement, upon which three (03) weeks‟ time was

granted to the petitioner on concession by the respondent. Yet again, on

April 24, 2018, the petitioner repeated its request for further time, to which

the claimant/respondent also did not raise any objection.

36. It was recorded in the minutes dated June 6, 2018, as reflected in the

impugned award, that the Statement of Defence was filed by the present

petitioner on June 5, 2018, but a copy thereof was handed over to the

claimant/respondent only on the date of hearing, that is, June 6, 2018. On

the said date, the learned advocate for the petitioner also commenced

arguments on merits and submitted that the supplier unit (present

respondent) had done additional work but the same was not approved by

the appropriate authority. The Council further recorded in its minutes

dated June 6, 2018 that the present petitioner also advanced arguments in

tune with its written notes. Arguments were also advanced by the present

respondent on the extra work done by it. Submissions were made by both

parties on the submission of GC-3 Form as well. Thus, both sides

commenced arguments on merits on June 6, 2018 itself.

37. On August 28, 2018, the learned advocate for the petitioner (buyer unit)

claimed that the supplier had disclosed new/additional documents, which

allegation was refuted on behalf of the claimant/respondent. The learned

advocate for the buyer unit/petitioner also raised the question of veracity of

bills submitted by the supplier unit and proclaimed that the bills had

already been paid by the buyer unit and that the supplier unit had forged

and fabricated the bills, for which FIR had been lodged, which was denied

by the supplier.

38. The learned advocate for the present petitioner further argued before the

Council on non-submission of GC-3 Form by the buyer unit for reducing

security deposit and contended that therefore the buyer was not entitled to

the release of security deposit. It was alleged that the supplier had

tampered some challans for repair of Kort Nozzle (Port Side), which were

accordingly not considered by the buyer/petitioner. Such contentions were

controverted by the supplier unit on merits.

39. Hence, it is evident that arguments were advanced on several occasions on

merits of the dispute by both the parties. However, at that juncture, the

buyer unit proposed a reconciliation meeting. As per the learned advocate

for the buyer, it expressed eagerness to settle the matter and informed that

the payment against Kort Nozzle could be reviewed by the appropriate

authority and that the supplier was to submit fresh documents on the

CENVAT claim.

40. On September 24, 2019, the buyer unit (present petitioner) admitted the

claim of the supplier unit, including the claim of dues on Kort Nozzle, but

refused to settle the claim of CENVAT and to pay interest. The supplier unit

did not accept such proposal and continued to contest the matter. However,

although on previous occasions the buyer/petitioner had advanced

arguments at length on merits, the learned advocate for the petitioner

submitted that he was not ready to contest the matter and had only come

up with the settlement proposal and wanted to come back "with appropriate

documentary evidences".

41. Conspicuously, even at that stage, the petitioner‟s prayer for adjournment

was granted by the Council, recording that it did not take up the matter for

final arbitration "in order to provide natural justice to both the parties".

42. On January 21, 2020, the matter again came up before the Council, when

the buyer/petitioner, arguing on merits, raised the question whether

repairing came under the purview of the 2006 Act and whether the claim of

the supplier unit came under the category of service. The

supplier/respondent contended that the buyer/petitioner wrongly deducted

some amounts and refused to pay certain justified due amounts. The

matter was then adjourned on the prayer of both sides.

43. Subsequently on May 12, 2021, when the matter was again taken up for

hearing, the learned advocate for the buyer unit/petitioner argued that the

Council is governed by "the Special Act" and addressed the issue of

jurisdiction of the Council to take up the matter for arbitration. The learned

advocate for the buyer unit contended further that the supplier had

erroneously submitted its application before the Council and that the

petitioner was agreeable to sit together on a further offer of Rs.26 Lakhs

settlement. The learned advocate for the buyer unit also sought for a

decision on the said legal points. Legal arguments were advanced by both

sides on the said issues.

44. The learned advocate for the supplier unit requested the Council further to

have an opportunity to place its arguments on merits. In reply, the learned

advocate for the buyer unit countered that it is a contractual matter and

there is "no applicability of equality" and that the arbitration clause would

be applicable only if there is a rejection on the part of the Chairman and

that the arbitration clause should be read as a whole.

45. However, when further asked by the Council to address on merits, the

learned advocate for the buyer unit insisted that the point of jurisdiction

may be decided first before further arguments on merits.

46. The Council decided the objection as to jurisdiction accordingly on the self-

same date and, by giving reasons, held that it had jurisdiction to take up the

matter. It was further clarified that the matter would be taken up in the

next hearing to adjudicate the points on merit.

47. Pausing here, it is abundantly clear that till the above date, both sides had

already argued on merits elaborately, as well as on the issue of jurisdiction.

It is not that the petitioner argued only on jurisdiction, but it had also

addressed the Council on several occasions on the merits of the case. It is

only that on May 12, 2021, the Council decided the issue of jurisdiction

first, that too on the insistence of the buyer/petitioner, and posted the

matter for adjudication on merits on the next date. Thus, although

arguments had been advanced on merits as well as jurisdiction, the

jurisdiction point was decided first and the adjudication on merits was left

for a further date.

48. Accordingly, the matter was taken up on April 28, 2022, when the buyer

unit/petitioner took a flimsy pretext of an undertaking having been given by

the parties regarding no steps being taken before the Council, since

apparently a challenge had been preferred against the decision of the

council on its jurisdiction.

49. It is noteworthy that the challenge under Section 34 of the 1996 Act, to the

decision of the Council that it has jurisdiction, failed before a learned Single

Judge as well as affirmed by a Division Bench of this Court subsequently,

on the ground that the ruling on jurisdiction was not an „award‟ which was

amenable to a challenge under Section 34 of the 1996 Act.

50. Coming back to April 28, 2022, the learned advocate for the

buyer/petitioner, quite surprisingly, urged that he had not made his

submission on merits and that the matter should be heard on merit. The

learned advocate for the supplier/respondent submitted that he had already

argued the matter on merits at least five times during the arbitral

proceedings. The Council, quite rightly, opined that the matter had been

thoroughly heard on several occasions on merits and proceeded to scrutinize

the written arguments of the parties and their pleadings and decide the

matter on merits.

51. The above narrative clearly goes on to show that not only was ample

opportunity given to the petitioner to argue the matter on merits but the

petitioner had availed of such opportunity by arguing the matter on merits

as well as on jurisdiction on several dates, covering the salient features of

the dispute. The prior adjudication of the issue of jurisdiction, that too on

the insistence of the petitioner, does not automatically signify that the other

issues were not heard previously.

52. In fact, the conduct of the present petitioner is deplorable, since it sought to

hinder the proceedings before the Council by seeking several adjournments

and lingering a non-maintainable challenge before this Court, first the

learned Single Judge concerned and thereafter in appeal before the

concerned Division Bench, on the issue of jurisdiction.

53. Accordingly, I am of the clear opinion that the facts on record are clearly

contrary to the argument of the petitioner that no opportunity of hearing

was given to it. Thus, the natural justice principle, reiterated in Ssangyong

Engineering and Construction Company Limited (supra), was never violated

by the Council in the present case.

54. Hence, this issue is also decided against the petitioner.

Non-submission of GC-3 Form

55. In terms of the contract between the parties, the GC-1 and GC-2 Forms

precede the submission of GC-3 Form. In the present case, the materials on

record placed before the Tribunal clearly show that certificates were issued

by the petitioner itself under Form GC-1 and Form GC-2 in respect of final

completion of the work done by the respondent. The liability of the

petitioner to clear the respondent‟s dues for such work arose immediately,

upon such completion certificates being issued by the petitioner itself, and

was not dependent on any further paraphernalia.

56. The claimant/respondent duly submitted its bill on October 15, 2013, which

was also produced before the Tribunal and has been annexed to the present

application of the petitioner itself.

57. The GC-3 Form, in terms of the contract between the parties, as evidenced

by the tender document, was in the nature of a "No Dues Certificate" in full

and final settlement of claims between the parties, which could only be

submitted by the respondent if it did not have any further dispute regarding

non-payment of its legitimate dues. The very crux of the present reference is

such a dispute as to non-payment and it is absurd to argue that non-

submission of GC-3 Form can be a deterrent to the respondent getting its

dues, as the very submission of a GC-3 Form by the respondent would

indicate its acceptance of the amount paid in full and final settlement of the

dues and would preclude the respondent from raising any challenge thereto.

58. Hence, such argument of the petitioner is hereby negated as well.

Merits

59. A thorough perusal of the impugned award shows that the Council

meticulously dealt with the pleadings of the parties, including the Statement

of Defence and written arguments filed by the petitioner, and the arguments

of parties advanced on several occasions. It thoroughly discussed the

claims under separate heads by adverting to the materials on record,

including the invoices raised by the supplier unit, the tender document, the

letters issued by the petitioner and the certificates issued in respect of

completion of the work. Upon a consideration of the entire germane body of

evidence, the Tribunal came to reasoned conclusions and decided separately

each and every head of the claim, granting some and refusing others.

60. It is thus found that there is no dearth of reasons in the impugned award.

It cannot be lost sight of that this Court, sitting in its jurisdiction under

Section 34 of the 1996 Act, is not taking up a regular appeal or reassessing

the evidence on record. The limited window within which the court can

intervene has to be read on the anvil of the parameters set forth in Section

34 itself. I do not find any patent illegality or the violation of the

fundamental policy of Indian Law and/or natural justice or for that matter

any other provisions of the 1996 Act to justify interference under Section 34.

As such, no case has been made out on merits of the case by the petitioner

to interfere with the impugned award. In fact, the majority of the claims had

been admitted by the petitioner itself in its several letters as well as

submissions made before the Council itself. However, the Council took the

pains of independently adjudicating on each of the said claims of the

respondent on merits. The petitioner, by its several letters, agreed the settle

the claim under all the heads in principle, although not on quantum, except

the claims on the respondent on CENVAT and deduction on account of Kort

Nozzle.

61. However, by its communication dated September 24, 2019, the petitioner

agreed to settle the Kort Nozzle claim as well, without admitting the claim in

respect of interest only.

62. The Council proceeded on the basis of the petitioner‟s letter, on the minutes

of the meeting dated January 28, 2014 granting additional time for

completion of the work, the satisfactory completion of the Kort Nozzle work

by the letter dated July 24, 2014, the agreement of the petitioner to pay the

majority of the heads of claim by its letter dated September 26, 2018, and

also independently adjudicated that the deductions in respect of illegal

claims is not permissible. Such findings were arrived at by adverting to the

evidence at length. The Council decided all issues accordingly on giving

substantial reasons and it is not for this Court, under Section 34 of the

1996 Act, to substitute its own views, even if possible, on a re-appreciation

of the evidence.

63. Thus, there is no scope of interference with the impugned award on merits

in the present case.

Initiation of conciliation in the midst of arbitration

64. The very premise of the arguments of the petitioner is fallacious, since it is

only on the basis of the proposal of the petitioner, as recorded in the

minutes dated June 6, 2018, that the option of settlement of the claims

between the parties was again explored by the Council. It is found from the

records that such an attempt could not be equated with a re-commencement

of the pre-arbitral conciliation process, since there is no such provision of

re-initiation of pre-arbitral conciliation afresh after the commencement of

arbitration, once the pre-arbitral conciliation is terminated. The Council

had already recorded in its Order dated November 16, 2016 that in view of

the non-participation of the buyer/petitioner, the conciliation procedure

under Section 18(2) was terminated and arbitral process was initiated under

Section 18(3) of the 2006 Act. Due communication was made on December

4, 2017 to the parties to that effect.

65. Thus, once arbitral proceedings commenced under Section 18(3), the clock

could not be set back by recommencing pre-arbitral conciliation, nor did the

Council do so. Rather, it is only on the prayer of the petitioner that further

avenues of mutual settlement, in addition to the arbitral proceeding, were

explored by the Council, which having failed, the matter was decided on

merits. It is to be noted further that the parallel attempts at mutual

settlement did not deter the parties from continuing with the arbitral

proceeding by advancing arguments on merits as well as jurisdiction before

the Council all along, as reflected in the minutes of the prior proceedings

and recorded in the impugned award itself.

66. Thus, such argument of the petitioner cannot also be accepted.

Sub-delegation of interest-adjudication by Council

67. The ordering portion of the impugned award is self-explanatory and

comprehensively answers such issue. The Council held therein that the

buyer unit is liable to pay Rs.16,77,027/- against deduction made for excess

and extra work from different bills "plus interest thereon @ 3 times of Bank

Rate of RBI, compounded with monthly rest to the supplier unit under

Section 16 of Chapter V of the 2006 Act". It was further recorded that such

interest would be "calculated after 45 days from the date of invoice till

realisation of the due amount".

68. Sections 15 and 16 of the 2006 Act govern the imposition of interest under

the 2006 Act. A bare perusal of the said provisions, juxtaposed with the

language used by the Council in the award, as narrated above, goes on to

show that the Council categorically decided all the adjudicable elements of

interest in consonance with Sections 15 and 16 of the 2006 Act, not only

stipulating the agreed date but also the period for which interest would be

payable, the rate and mode of interest, as well as specifically invoked

Section 16 of the 2006 Act while doing so. Hence, a complete and thorough

adjudication on all the decisive ingredients of interest was undertaken by

the Council.

69. It was only the clerical act of mathematical calculation of the interest that

was left to the CA, duly certified, to be appointed by the

claimant/respondent. The job of the CA was clear-cut - merely to

arithmetically calculate the quantum in terms of the parameters already

fixed by the Tribunal in its award. Hence, there was no element of

"adjudication" which was delegated to the respondent or its CA.

70. In Usha Martin (supra), relied on by the petitioner in this context, the

principal amount was left to be adjudicated by the CA and the award did not

specify the time from which the interest was to be calculated.

71. Again, in Government of Maharashtra v. Srivin (supra), the Council had failed

to indicate the time-period for calculation of interest.

72. As opposed to both the above cases, all such ingredients of adjudication

were completely taken care of by the Council in its award. Thus, the ratio

laid down in the said judgments is not applicable to the instant case at all.

73. Rather, the reliance of the respondent on M/s Silpi Industries (supra) is apt

in the present context. Sections 15 to 23 of the 2006 Act have overriding

effect on all other statutes, including the 1996 Act and, being a beneficial

legislation, has to be given a wider interpretation, since it is not in dispute

that the respondent is an MSME unit and is squarely covered by the 2006

Act.

Whether the MSME Council had jurisdiction to adjudicate on disputes

in respect of Works Contract

74. Although not elaborately stated in its written notes of arguments, the

petitioner‟s counsel verbally agued the point, for which the same is taken up

for adjudication for the sake of completion.

75. The issue at hand was dealt with elaborately by this Court in Hindustan

Petroleum Corporation Limited (supra) in WPO No.2896 of 2022, referred to

by the respondent in its written notes of arguments.

76. The relevant judgments of the Supreme Court in respect of works contracts,

rendered in respect of taxing statutes, were misinterpreted in some of the

judgments of different High Courts by automatically borrowing such concept

in respect of the 2006 Act, which is a beneficial piece of legislation, whereas

those were read in correct context by others. The entire gamut of the said

citations was considered and dealt with in Hindustan Petroleum Corporation

Limited (supra), which is not being repeated verbatim to save unnecessary

time and paper (virtual) space. Suffice to mention the crux of the principle

as follows:

77. Section 2(e) of the 2006 Act defines "enterprise" as an industrial

undertaking or a business concern or any other establishment, by whatever

name called, engaged in the manufacture or production of goods or engaged

in providing or rendering any service or services.

78. Section 2(m) provides that "supplier" means a micro or small enterprises

which has filed a memorandum with the authority referred in sub-section (1)

of Section 8 of the 2006 Act. The 2006 Act applies to all such enterprises,

irrespective of the nature of the contract entered into. There is no bar in the

2006 Act for works contracts, having ingredients both of goods and services

supply, to come within the purview of the Act. Rather, the expansive

definition of "enterprise", covering both manufacture and production of

goods as well as providing or rendering of any service or services, makes it

abundantly clear that both supply of goods and services are covered by the

Act. Section 18 is impartial as to the nature of dispute which may be

referred to the Council and merely provides that "any dispute regarding any

amount under Section 17" of the 2006 Act is referable under the said

provision to the Council.

79. Section 17 of the 2006 Act stipulates that the recovery of amount has to be

of any good supplied or services rendered by the supplier. Hence, both the

facets of goods and services are included within the ambit of such dispute

and works contracts, which by their very nature have both components,

cannot be excluded from the purview of the Act.

80. In fact, the previous judgments in that regard were elaborately dealt with in

Hindustan Petroleum Corporation Limited (supra) in the backdrop of the

liberal interpretation of the 2006 Act, which is a beneficial statute, as

opposed to the interpretation of whether "works contracts" would be taxable

by the States in the context of taxing statutes, which are by their very

nature to be interpreted strictly, being penal in nature.

81. Furthermore, there is nothing in the 2006 Act itself to debar works contracts

from being covered by the 2006 Act, including Section 18 therein, provided

the dispute relates to an MSME unit and is covered by Section 17 of the said

Act.

82. As such, the above issue is also decided in the negative and against the

petitioner.

CONCLUSION

83. In fine, on the basis of the discussions above, there is no scope of

interference with the impugned award under Section 34 of the 1996 Act.

The petitioner has abjectly failed to establish any of the grounds stipulated

under Section 34 of the 1996 Act for this Court to intervene with the arbitral

award. In fact, if we go by the principle enunciated in Section 5 of the 1996

Act itself, no judicial authority shall intervene except were so provided under

the concerned Part of the 1996 Act and, as such, there cannot be any

intervention in the present case.

84. Another aspect of the matter is required to be dealt with here. In the

caption of the present application under Section 34 of the 1996 Act, a

challenge has also been purportedly thrown to the Order dated May 12,

2021 passed by the Council, whereby the Council had held in favour of its

jurisdiction to adjudicate the dispute.

85. However, such challenge is not maintainable within the four corners of the

1996 Act. The only two situations in which a challenge can be preferred

under the 1996 Act to a decision of a domestic arbitral tribunal are under

Sections 34 and 37 of the said Act.

86. Section 34 contemplates a challenge to an award. The petitioner preferred a

previous challenge under Section 34 to the self-same Order dated May 12,

2021 which was turned down by the learned Single Judge on the ground

that such a challenge was not maintainable since the order was not an

award. The said view was affirmed by a Division Bench of this Court. Thus,

there is no scope of further reopening the said issue.

87. Insofar as Section 37 of the 1996 Act is concerned, the said provision clearly

stipulates the specific orders which can be challenged under it. Sub-section

(2)(a) of Section 37 provides for a challenge where a plea referred to in sub-

section (2) or sub-section (3) of Section 16 of the Act is "accepted".

88. Section 16(2) and Section 16(3) pertain respectively to the Arbitral Tribunal

not having jurisdiction and exceeding the scope of its authority.

89. In the present case, by the order dated April 12, 2021, the objection as to

jurisdiction under sub-sections (2) and/or (3) of Section 16 of the 1996 Act,

raised by the petitioner, was not "accepted" but refused. Thus, under the

specific scheme of Section 37(2)(a), although an acceptance of an objection

of jurisdiction would be appealable, the converse is not true and, thus, no

appeal lies against the refusal to entertain an objection under sub-Sections

(2) and (3) of Section 16 of the 1996 Act.

90. An analogy cannot be drawn with Section 105 of the Code of Civil Procedure,

under sub-section (1) of which an error, defect or irregularity in any order

affecting the decision of a case may be set forth as a ground of objection in a

memorandum of appeal under Section 96 of the Code against the final

decree, since Section 105 is only provided in respect of an appeal under the

Code of Civil Procedure, which provides for an entirely distinct and different

legal ecosystem and hierarchy of appeals than Sections 34 and 37 of the

1996 Act. Thus, we cannot superimpose the provision of a different statute,

operating in a completely different field, to an arbitral proceeding under the

1996 Act. What cannot be done directly cannot also be indirectly brought in

by the backdoor by permitting a challenge to an interlocutory order passed

by the arbitral tribunal within the ambit of a challenge to the final award by

way of an application under Section 34 of the 1996 Act.

91. Another important aspect of the matter is that although a challenge under

Section 37 of the 1996 Act has been consciously termed as an "appeal", the

Legislature, in its wisdom, has deliberately named a challenge under Section

34 not as an "appeal" but as an "application".

92. Hence, the analogy of an appeal could not even otherwise be drawn in

respect of an application under Section 34 of the 1996 Act, which is not an

appeal in any event.

93. Hence, the said challenge to the Order dated May 12, 2021 is not

maintainable and is hereby turned down as well.

94. In view of the above, the present challenge fails. Accordingly, A.P.-COM

No.296 of 2024 (Old No. A.P. 179 of 2023) is dismissed on contest without,

however, any order as to costs, thereby affirming the impugned award dated

April 28, 2022, passed by the West Bengal Micro, Small Enterprises

Facilitation Council and turning down the challenge to the order dated May

12, 2021 passed by the said Council as not maintainable.

95. Urgent certified copies of this order, if applied for, be supplied to the parties

upon compliance of all formalities.

(Sabyasachi Bhattacharyya, J.)

LATER :

After the above judgement is passed, learned Counsel appearing for

the petitioner seeks a stay of operation of the above judgement.In view of

certain arguable question being involved, stay of operation of the above

judgement is granted for a period of four weeks from date.

Learned Counsel appearing for respondent seeks permission to

withdraw the amount which has been deposited pursuant to a previous

order passed in the matter. However, such prayer shall be subject to any

order, if passed in the challenge, if any, to be preferred against the above

judgement and/or till the period of four weeks from date, whichever is

earlier. In the event no appeal is preferred against the above judgment

within four weeks, the respondent shall be at liberty to withdraw such

amount and adjust it with the decretal dues.

(Sabyasachi Bhattacharyya, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter