Citation : 2023 Latest Caselaw 7388 Cal
Judgement Date : 17 November, 2023
In the High Court at Calcutta
Constitutional Writ Jurisdiction
Appellate Side
The Hon'ble Justice Sabyasachi Bhattacharyya
W.P.A. No.25102 of 2022
ILEAD Foundation and another
Vs.
State of West Bengal and another
For the petitioners : Mr. Chayan Gupta,
Mr. Rittick Chowdhury,
Mr. Dwip Raj Basu
For the State : Mr. Sk. Md. Galib,
Mr. K.M. Hossain
Hearing concluded on : 10.10.2023
Judgment on : 17.11.2023
Sabyasachi Bhattacharyya, J:-
1. The petitioner no.1 is an institute of technology which approached the
respondent no.2 for execution of a project floated by the Ministry of
Rural Development, Government of India by way of a Scheme named
"Din Dayal Upadhyaya Grameen Kaushaliya Yojana" (for short, "the
Scheme"). Under the Scheme, the subsidy was to be given in tranches
at different stages, upon completion of specific percentages of the
project. The petitioner no.1 was appointed as a Project Implementing
Agency (PIA). The proposal of the petitioner no.1 on such count was
accepted by the respondent no.2 by a sanction order dated August 30,
2017, stipulating that a total number of 880 residential candidates
were to be trained under the project and the total project cost would
be Rs.4,79,67,440/-. A Memorandum of Understanding (MOU) for
implementation of the project as per the Standard Operating
Procedure (SOP) and Guidelines were also executed on the same date.
The petitioner no.1 started its work accordingly. Although the first
instalment was paid to the petitioners, the second instalment was
withheld by the respondent no.2 on certain allegations, which has
prompted the petitioners to move this court in the writ jurisdiction.
2. Learned counsel for the petitioners relies on Clause 4.1.2 of the MOU
which ensures timely release of financial grants to the PIA. Clause 5
speaks about sanction for skill development training of 880 students
in the District of North 24 Parganas, Kolkata. It is submitted that the
petitioner no.1 was disbursed 25 per cent of the project cost as per the
conditions. Despite the petitioners having achieved the milestones
required for the release of the second instalment of 25 per cent of the
project cost and having submitted all requisite documents, it is argued
that the respondent have withheld the second instalment of
Rs.1,19,91,860/-.
3. Addressing the question of maintainability raised by the respondents,
it is argued that arbitration would not be an equally efficacious
alternative remedy since due to non-disbursal of the second
instalment, the entire training programme is being stalled and the
future of 880 enrolled students is at stake. By citing Union of India v.
Tantia Construction (P) Ltd., reported at (2011) 5 SCC 697, it is argued
that existence of arbitration clause is not an absolute bar to a writ
petition. The judgments cited by the respondent on such count have
been substantially watered down, since existence of an arbitration
clause is not an absolute bar to a writ petition, as there are no
disputed questions of fact requiring adjudication as per the
petitioners.
4. The quantum claimed by the writ petitioners is ascertained and there
are no disputed questions of fact. It is argued that the respondents
have sought to raise bogies of disputes in their opposition, which
never existed between the parties.
5. Learned counsel places reliance on the affidavit-in-reply of the
petitioners in their affidavit-in-reply to submit that the petitioners
have successfully answer all the queries raised by the respondents.
6. Learned counsel for the petitioners cites Khaitan Winding Wire Private
Limited and another Vs. Steel Authority of India Limited, in WP 8692
(W) of 2019for the proposition that even if there is admitted monetary
claim, a writ petition lies for recovery of the same.
7. Learned counsel also relies on M.P. Power Management Co. Ltd. v. Sky
Power Southeast Solar India (P) Ltd. and others, reported at (2023) 2
SCC 703,for the proposition that a writ petition is maintainable even
in contractual disputes.
8. Learned counsel for the respondent nos.1 and 2 argues that the writ
petition is not maintainable as the lis involves liabilities arising out of
contractual relations between the parties and the contract between
the parties has an arbitration clause. The contract is non-statutory,
for which the writ petition is not maintainable, particularly since it
involves complex questions of fact and law requiring elucidation by
leading evidence.
9. In support of the objection as to maintainability, learned counsel cites
the following judgments:
I) 2022 SCC OnLine SC 1591 [M.P. Power Management Co. Ltd.,
Jabalpur v. Sky Power Southeast Solar India Pvt. Ltd. and ors.];
II) (1996) 6 SCC 22 [State of U.P. and ors. v. Bridge & Roof Co.
(India) Ltd.];
III) (2004) 3 SCC 553 [ABL International Ltd. and Anr. v. Export
Credit Guarantee Corpn. of India Ltd. and ors];
IV) (1975) 2 SCC 436 [Titagarh Paper Mills Ltd. v. Orissa State
Electricity Board and Anr.];
V) (2004) 9 SCC 786 [National Textile Corpn. Ltd. and ors. v. Haribox
Swalram and ors.];
VI) (1974) 2 SCC 706 [Babubhai Muljibhai Patel v. Nandlal Khodidas
Barot and ors.];
VII) (2000) 3 SCC 379 [India Thermal Power Ltd. v. State of M.P. and
ors.];
VIII) 2023 SCC OnLine SC 1223 [BTL EPC Ltd. v. Macawber Beekay
(P) Ltd. and ors.].
10. On merits, it is argued by the respondents that the petitioners failed
to comply with the necessary pre-conditions for release of the second
instalment of the funds as provided in the Notification dated October
21, 2019 annexed at page 25 of the affidavit-in-opposition filed by the
respondents.
11. Several inspections were held by the respondents, upon which various
irregularities were found. Many of the candidates enrolled by the
petitioners are not rural youth for whom the project is specifically
designated. That apart, there have been diversions of funds and
investment on unaccounted-for assets by the petitioners.
12. Upon due inspection being held and hearing being given to the
petitioners on December 22, 2021 by the Chairman of the hearing
committee and project director, a chance was given to the petitioners
to make good, within 30 days, all the irregularities regarding training,
placement of candidates and financial aspects. Instead of complying,
the petitioners issued a reminder on March 14, 2022 for disbursement
of the second instalment without bothering to rectify their deviations
and faults in terms of the directions as recorded in the minutes of
hearing dated December 22, 2021.
13. The Guidelines and SOP which are binding on both the parties were
contravened by the petitioners, it is alleged, leading to the withholding
of the amount-in-question by the respondents.
14. Upon hearing learned counsel for the parties, the issue of
maintainability acquires prime importance in the present case. Before
entering into the merits as such, the said issue it taken up for
adjudication.
15. The respondent nos. 1 and 2 have referred to several judgments. In
Titagarh Paper Mills (supra), interference by the High Court under
Article 226 to determine questions which formed the subject-matter of
arbitration was deprecated.
16. In National Textile Corpn. Ltd(supra) interference by the writ court in
simple business contracts has been discouraged.
17. In State of U.P. and ors. v. Bridge & Roof Co. (India) Ltd.(supra),
exhaustion of alternative remedy has been encouraged by the
Supreme Court before interference under Article 226 of the
Constitution.
18. In ABL International (supra), the Supreme Court observed that the writ
court can interfere in appropriate cases involving disputed questions
of fact and that there is no absolute bar in interference. It has also
been observed that in some cases, oral evidence can be taken.
Naturally, the respondents have placed strong reliance on the said
judgment.
19. The said judgment laid down the proposition that even in contractual
matters, the remedy of Article 226 lies in certain cases and is not
absolutely barred. The stress in the said judgment was on the
proposition that merely because disputed questions of fact are
involved, the writ court may not shy away in all cases.
20. However, it is evident from the judgments cited by the parties, the writ
jurisdiction has evolved considerably since, thereby diluting the bar of
alternative remedy. However, the said bar does not altogether negate
the self-imposed restriction of Constitutional courts in case of
availability of alternative remedy. The jurisprudence which has
evolved in the field, as evident from the judgments relied on by both
sides, is clearly that interference under Article 226 by the High Court
is circumscribed by certain tests. If there is gross arbitrariness,
palpable illegality, violation of the Wednesbury principle, perversity,
mala fides, unreasonableness or violation of any fundamental right,
the writ court can interfere.
21. However, the Supreme Court has never laid down that in any and
every case where there is an existence of an alternative remedy, the
writ jurisdiction can be invoked despite such remedy as a matter of
rule, which would tantamount to erasing such alternative remedy
from the statute books.
22. One such important bar to the interference of the writ court is where
disputed questions of fact arise between the parties.
23. Even in the judgments cited by the petitioners, it is found that a writ
court may interfere in money claims or contractual cases or otherwise,
although the contract is not statutory, subject to the satisfaction of
the above window of interference. In the present case, there is
nothing palpable on the face of the materials to indicate that there
was any patent arbitrariness, unreasonableness or mala fides or
existence of such like ground calling for such interference by this
Court.
24. It is found from the annexures to the affidavit in opposition that
hearing was given to the petitioners. Moreover, there were several
reports and an elaborate prior exercise by the respondent-authorities
before refusing to disburse the second instalment of funds to the
petitioners under the concerned project. In the very provisions of the
Scheme, the training contemplated was to be imparted to rural
candidates. Admittedly, at least in certain cases, the said rule was
deviated from. That apart, there were specific delineated peripheries
of utilisation of the investments, which have arguably not been
adhered to by the petitioners.
25. The respondent nos. 1 and 2, in their opposition, have annexed
several inspection reports which are detailed and comprehensive in
nature and point out numerous major deficiencies and irregularities
on the part of the petitioners.
26. Although the petitioners have disputed those, the very nature of the
allegations are such that they strike at the root of the execution of the
project within the contemplation of the SOP and the MOU between the
parties.
27. The quality of training, the persons to whom it is imparted and the
subsequent placement, which are essential components of the project,
affected by the irregularities as per the allegations of the respondents.
28. Clause 5.3 of the MOU between the parties clearly stipulates that all
payments to the PIA may be suspended if the PIA fails to perform any
of its obligations under the MOU and the respondent-authorities shall
take the action after giving due notice to the PIA which has apparently
been given in the present case, granting the petitioners/PIA ample
opportunity to take remedial measures as specified in the Notice.
29. The right to get the subsequent instalment of disbursals are not
unfettered. Clause 4.1.2 of the MOU, strongly relied on by the writ
petitioners, itself provides that timely release of financial grants are to
be as per the prescribed service standards and operational norms
which are provided in the MOU as well as the SOP. In view of the
serious allegations of contravention of the said provisions by the
petitioners, it would not be prudent for the writ court, by the stroke of
a pen, to issue a Rule of Mandamus, which is a prerogative writ
against the respondents, without entering into the factual disputes
involved.
30. By their very nature, the allegations, defences and counter-allegations
by the parties call for a detailed adjudication upon an elaborate
factual assessment of materials and evidences, which is entirely
beyond the domain of the writ court.
31. In such view of the matter, since disputed questions of fact calling for
detailed assessment of evidence is required, this Court is not inclined
to interfere under the writ jurisdiction.
32. Thus, WPA No.25102 of 2022 is dismissed as not maintainable on the
grounds as indicated above.
33. Nothing in this order, however, shall preclude the parties from
approaching the appropriate Arbitral Tribunal and/or other forum, if
they are so entitled in law, for adjudication of the disputes raised
between the parties in the present writ petition.
34. For the sake of clarity, this Court has not entered into the merits of
the respective contentions of the parties and it will be open to any
forum having jurisdiction, as and when approached, to decide
independently all issues of law and fact involved between the parties
without being prejudiced in any manner by any of the observations
made herein.
35. There will be no order as to costs.
36. Urgent certified server copies, if applied for, be issued to the parties
upon compliance of due formalities.
( Sabyasachi Bhattacharyya, J. )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!