Wednesday, 20, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The Kolkata Municipal ... vs Rajpath Contractors & Engineers ...
2023 Latest Caselaw 1570 Cal/2

Citation : 2023 Latest Caselaw 1570 Cal/2
Judgement Date : 14 July, 2023

Calcutta High Court
The Kolkata Municipal ... vs Rajpath Contractors & Engineers ... on 14 July, 2023
                 IN THE HIGH COURT AT CALCUTTA

                 (Ordinary Original Civil Jurisdiction)

                              ORIGINAL SIDE

Present:

The Hon'ble Justice Krishna Rao



                              AP 1985 of 2014



                  The Kolkata Municipal Corporation

                                  Versus

               Rajpath Contractors & Engineers Limited



           Mr. Jaydip Kar, Sr. Adv.
           Mr. A.N Banerjee
           Mr. Rudranil De
                                            .....For the KMC
           Mr. Sakya Sen
           Mr. Priyankar Saha
           Mr. Amritam Mondal
           Mr. Hemant Tiwari
           Ms. Ananya Chakraborty
           Ms. Shipra Nashar
                                      .....For the respondent

Hearing Concluded On : 16.05.2023

Judgment on :14.07.2023

Krishna Rao, J.:

1. This is an application under Section 34 of the Arbitration and

Conciliation, Act, 1996 challenging the Award passed by the Learned

Sole Arbitrator dated 22.09.2014 wherein the Learned Arbitrator has

awarded an amount of Rs. 2,69,05,241/- (Rupees two crores sixty nine

lakhs five thousand two forty one) with the direction upon the

petitioner herein i.e. Kolkata Municipal Corporation Limited (herein

after referred to as "KMP") to pay the said amount to the respondent

within a period of thirty (30)days from the date of Award. In default of

payment of the same within the aforesaid time period, the awarded

amount shall be paid by the KMC to the respondent along with interest

@ 18% per annum for the period from date of the award till the date of

payment.

2. The Kolkata Municipal Corporation invited a tender on 17th October,

1996 for renovation of existing 7 M.G. Semi Underground Reservoir at

Tallah and the value of the said work was fixed at Rs. 3,53,00,288/-.

The respondent had participated in the said tender and the respondent

had accepted the tender of the petitioner for a total value of Rs.

3,77,39,537/- and accordingly the respondent had deposited an

earnest money of Rs. 1,10,751/-. After receipt of the tender of the

petitioner, work order was issued on 24th July, 1997 and as per the

work order the work was to be completed within 12 months from the

date of the work order. An Article of Agreement was entered between

the parties which stipulated all the conditions of the contract as laid

down in the tender document.

3. The respondent has completed the work on 31st July, 1999 and after

completion of the work the respondent has submitted his 3rd Running

Account and Final Bill on 16th September, 1999 which was received by

the petitioner on 20th September, 1999. Even on receipt of the Final

Bill, no amount was paid by the petitioner to the respondent inspite of

several reminders. Accordingly, the respondent had filed writ petition

being W.P No. 1925 of 2002 praying for appropriate direction for release

of payment and during the pendency of the writ application, by a letter

dated 15th May, 2005, the petitioner has blacklisted the respondent.

4. Challenging the order of blacklisting, the respondent had filed another

writ application being WP No. 779 of 2005 and by an order dated April

25, 2005, the order of blacklisting was set aside. Being aggrieved with

the said order, the petitioner has preferred an appeal and the said

appeal was disposed of at the ad interim stage on 17th May, 2007 with

the modification by deleting the word 'set aside' and incorporating the

words 'operation of the impugned notification till the disposal of the

writ petition'. Finally, the writ petition was disposed of on 24th

February, 2015 wherein the Hon'ble Court had set aside the said order

of blacklisting.

5. This Court by an order dated 26th August, 2009 had disposed of the

first writ application filed by the respondent by giving liberty to the

respondent to file a civil suit or arbitration seeking appropriate remedy

as no relief can be granted in the writ petition. While disposing of the

first writ petition, the Hon'ble High Court also observed that the period

during which the first writ petition was pending before the Hon'ble High

Court shall be excluded for the purpose of limitation under Section 14

of the Limitation Act, 1963.

6. After the disposal of the first writ application, the respondent had

initiated a Civil Suit being CS No. 255 of 2009 on 1st September, 2009.

In the said suit, the respondent had also filed an application under

Chapter XIIIA of the Original Side Rules of this Court and during the

pendency of the said application, the parties have decided to enter into

an arbitration agreement resolving to settle all disputes and differences

between the parties with respect of the work awarded to the

respondent.

7. On 5th April, 2011, both the parties have entered into an agreement

wherein the parties agreed to resolve their disputes pursuant to such

arbitration agreement and accordingly the Hon'ble High Court referred

the dispute to the arbitration on 5th April, 2011. As the petitioner has

not made the payment till 17th May, 2011, accordingly, the respondent

initiated an arbitration proceeding by filing a statement of claim for a

total sum of Rs. 11,28,29,317/-. Before the Learned Arbitrator, the

petitioner made an overall application under Section 16 of the

Arbitration and Conciliation Act, 1996 challenging the jurisdiction of

the learned Arbitrator to decide upon certain claims on the ground that

the claims mentioned under Category- A & C of the Statement of Claim

are outside the purview of civil suit referred to the arbitration and the

said claims cannot be the subject-matter of the arbitration. The

Learned Sole Arbitrator after hearing of the parties rejected the

objection raised by the petitioner under Section 16 of the Arbitration

and Conciliation Act, 1996 on 26thSeptember, 2012. After considering

the submission of the parties and the evidence laid by the parties, the

learned sole Arbitrator has passed the impugned order on 22nd

September, 2014.

8. Mr. Jaydip Kar, Learned Senior Advocate representing the petitioner

"KMP" submitted that the arbitration agreement contemplates that only

the claim and counter claims, if any, of the parties which are the

subject-matter of CS No. 255 of 2009 are referred to arbitration but the

learned Arbitrator without considering the said clause of the agreement

has rejected the application of the petitioner under Section 16 of the

Arbitration and Conciliation Act, 1996 and taken into consideration of

Schedule-A as well as Schedule-C of the claim of the respondent.

9. Mr. Kar submitted that from the order dated 5th April, 2011 wherein the

matter was referred to arbitration, it was clarified that there is no

further doubt that only the matters which were the subject-matter of

CS No. 255 of 2009 are referred to the arbitration. He submits that the

words used in order dated 5th April, 2011 are "an agreement has been

entered into today between the parties by which they have decided to

refer the matters covered by the suit to arbitration", these means that

the reference is limited to the subject-matter of the suit.

10. Mr. Kar by relying upon the judgment reported in AIR 1985 SC 1156

(Renusagar Power Corporation Limited -vs- General Electric

Company & Anr.) had submitted that the Supreme Court has held

that "whether a given dispute inclusive of arbitrator's jurisdiction

comes within the scope or purview of an arbitration clause or not

primarily depends upon the terms of the clause itself; it is a question of

what the parties intend to provide and what language they employ". He

submits that there is no doubt, the expression "arising out of" or "in

connection with" are the widest amplitude but used in the context of the

present arbitration agreement they are descriptive of and reflect the

amplitude of the suit itself but not the scope of the arbitration

agreement. The scope of the arbitration agreement would be wider than

the scope of the suit.

11. Mr. Kar submitted that the claimant has divided his claims into three

categories i.e. Category-A, Category-B and Category-C. He submits that

Category-B claims have been described as particulars of the dues as

claimed in the suit but there is no heading in respect of Category-A and

Category-C to indicate what their origin is or even to indicate that their

origin is not related to the subject-matter of the suit.

12. Mr. Kar submitted that Claims A and C ought not to have been

entertained as the respondent have raised the said claims for the first

time by a letter dated 4th May, 2011 and the purported claim is false,

frivolous and fatuous.

13. Mr. Kar relying upon the judgment reported in AIR 1999 SC 2102

(Olympus Superstructures Limited vs. Meena Vijay Khetan & Ors.)

submitted that the Hon'ble Supreme Court allowed the plea of

jurisdiction to be raised even at the stage when the application for

setting aside of the award was under consideration under Section 34 of

the Act of 1996.

14. Mr. Kar submitted that the Hon'ble Arbitrator has awarded a sum of

Rs. 46,86,644/- in respect of Claims of Category-A which have surfaced

for the first time in the reference and do not form the subject-matter of

the suit. He submits that the Learned Arbitrator has awarded part of

the Claim of the Category-A on account of off-site and on-site expenses

and costs on account of area, apart from being non-arbitrable and

barred by limitation. He further submits that there can be no dispute

that such claim must have been arisen prior to completion of the work

and no on site and off site expenses could have been incurred by the

respondent after completion of the work.

15. Mr. Kar submitted that disregarding the date of completion of the work

and taking into account, the date of Final Bill as the starting point of

limitation, then also, the claim towards on-site and off-site expenses

are barred by limitation. He submits that the sum of Rs. 37,73,952/-

was awarded on account of on-site and off-site expenses did not form

part of the suit filed before the Hon'ble High Court and thus period

during which the suit was pending before this Court would not matter

for the purpose of limitation. He submits that as long as the on-site and

off-site expenses are concerned, no evidence has been adduced by the

respondent to support the claim and thus the award of Rs. 37,73,952/-

is vitiated as the same has been awarded without any evidence.

16. Mr. Kar submitted that the Arbitrator has awarded a sum of Rs.

9,12,692/- on account of costs whereas the claim was for Rs.

5,40,692/- though there is no computation by the claimant, nor any

evidence adduced in support of the claim for Rs. 4 lakhs (over and

above Rs. 5,40,692/-) made in the statement of the claim. He submits

that the additional sum of Rs. 4 lakhs is without any basis and without

any evidence.

17. Mr. Kar submitted that as regard Claim of Category-B are concern, the

Arbitrator has awarded a sum of Rs. 1,45,02,288/- towards the balance

of 2nd Running Account Bill and a sum of Rs. 50,41,348/- on account

of 3rdRunning Account and Final Bill. He submits that the said claims

are also barred by limitation as 2ndBill was issued on 31st August, 1998

and part payment was made on 27th May, 1999. He submits that the

respondent claimed for two bills separately on the basis that they did

not represent advance against work done/to be done and to be

adjusted against the final bill but payment on account of the work

actually done in the concern bill. He submits that the cause of action

accrued on the date of receipt of such bill and limitation for recovery of

the amount thereunder expired three years from the date of receipt of

the said bill by the petitioner. He submits that taking into account, the

exemption towards the 2ndRunning Account Bill is barred by limitation.

He also submitted that taking into account the date of receipt of 3rd

Running Account and Final Bill the claim is barred by limitation. He

submits that the Hon'ble Court while referring the parties to arbitration

in terms of the arbitration agreement dated April 5, 2011 did not grant

any exemption under Section 14 of the Limitation Act nor did it hold

that the time taken in processing the suit should be excluded while

computing limitation.

18. Mr. Kar submitted that the amount awarded on account of escalation

aggregating Rs. 18,86,977/- would not have been awarded as the same

being contrary to the express terms of the contract between the parties.

He submits that the contract expressly bars and prohibits the award for

escalation and in face of such prohibition, no award could have been

made by the Learned Arbitrator. He submits that the claim of

escalation is not proved and the Learned Arbitrator has taken various

parameters in the formula for escalation/de-escalation have been

misapplied. He submits that on account of retention money and refund

of earnest money are not payable. Retention money has been claimed

twice over and above the respondent is purporting to make unjust

enrichment out of such award and having been failed to perform his

contractual obligations cannot be entitled to refund of security deposit

and earnest money.

19. Mr. Kar submits that the finding of the Learned Arbitrator are bad in

law and there are errors on the face of the award and the materials of

the record go to show, inter alia, that the Learned Arbitrator had come

to its finding and conclusion without any basis. He submits that the

Learned Arbitrator came to the findings, which are unreasonable,

perverse and against the public policy of India.

20. Mr. Kar submits that the arbitral award is bad by virtue of Section 34

(2) (a) (iv) of Section 34 (2) (b) (i) (ii) of the Act of 1996.

21. Mr. Kar relied upon the following judgments in support his

submissions :

i. (2020) 14 SCC 643 (Geo Miller & Co. Pvt. Ltd. -vs- Chairman Rajasthan Vidyut Utpadan Nigam).

ii. (2010) 8 SCC 563 (Rashtriya Chemicals & Fertilizers Limited -vs- Chowgule Brothers &Ors.).

iii. (2012) 12 SCC 581 (State of Goa -vs- Praveen Enterprises).

iv. (2022) 1 SCC 131 (Delhi Airport Metro Express Pvt. Ltd. -vs- Delhi Metro Rail Corporation Ltd.).

22. Mr. Sakya Sen, Learned Advocate representing the respondent submits

that the main point which was argued by the petitioner before the

Learned Arbitrator was the claims under Category-A and Category-C of

the Statement of the Claim were not the subject-matter of the suit and

therefore, not arbitrable. He submits that the Hon'ble High Court by its

order dated 5th April, 2011, gave effect to the arbitration agreement and

was executed between the parties herein on the same date. The

arbitration agreement envisages settlement of all disputes between the

parties: "arising out of and in connection with the work order dated 24th

July, 1997" and also "the disputes and differences in respect of and/or

in relation to and/or arising out of the said agreement dated 27th

August, 1997 being claims of the plaintiff and the counter claims, if any

of the defendant in CS No. 255 of 2009 referred to above through

arbitration........".

23. Mr. Sen submits that the word "also" must be taken as "including" in

the facts and circumstances of the case. In other words that all

disputes arising between the parties in connection with the subject

contract/work order including the disputes which were covered by the

suit were agreed to refer to arbitration. He submits that the arbitration

agreement did not cover only the disputes referred to the suit.

24. Mr. Sen submitted that after receipt of the statement of claim, the

petitioner has filed statement of defence but the petitioner has not

raised any issues to the effect that the claims which were not in the

suit are not arbitable before the Arbitral Tribunal.

25. Mr. Sen submitted that final bill was submitted on 16th September,

1999 and the writ petition was filed on 6th September, 1999. He

submits that within three years from submitting the final bill, the

respondent has filed writ petition. The writ petition was disposed of on

26th August, 2009 and the suit was filed on 1st September, 2009. He

submits that the respondent has filed the suit within the stipulated

period of time and thus it cannot be said that the claim made by the

respondent is barred by limitation.

26. Mr. Sen submitted that by way of letter dated 4th May, 2011, additional

claim was raised which was duly incorporated in the statement of claim

and the same was duly decided by the Learned Arbitrator by taking into

consideration of the order of reference, agreement and the suit filed by

the respondent.

27. Mr. Sen relied upon Clause 1 (b) (ii), Clause 1 (c), Clause 7, Clause 8

and additional condition Clause 21 and submits that the said clauses

of the agreement are relevant for the purpose of deciding as to how

limitation could have been applied.

28. Mr. Sen submitted that Final Bill is prepared and the same is certified

for payment, the question of limitation does not arise in the work's

contract. He relied upon unreported judgment passed by the Division

Bench of this Hon'ble Court in FMA No. 1093 of 2013 (M/s. Biptrade

vs. Union of India &Ors.) and submitted that if there was any

question of right to go to arbitration being barred by limitation, such

issue ought to have been decided at such stage as it was incumbent on

the Chief Justice or his designated exercising authority under Section

11(6) of the Act to adjudicate on such aspect before referring the

disputes to the arbitration. The second aspect of limitation could not

have been re-opened by the employer after the arbitral reference

commenced in terms of the order under Section 11 of the Act.

29. Mr. Sen submitted that admittedly final bill was accepted on 20th

September, 1999 thereby three years period would lapse on 19th

September, 2002 but the writ petition was filed on 6th September, 2002

i.e. before 15 days, the limitation could expire and after disposal of the

writ petition on 26th August, 2009 i.e. within 5 days the suit was filed

on 1st September, 2009 and hence, there is no limitation as alleged by

the petitioner.

30. Mr. Sen submitted that additional claims being Category-A and

Category-C of the Statement of the Claim are incidental claims arising

out of the claims made in the suit. Such claims are consequential to

the claims made in the suit and would arise with the claim in the suit

and would die down if the claim made in the suit does not succeed. He

submitted that the claim do not have any independent existence.

31. Mr. Sen submitted that in the agreement itself the escalation Clause is

existing and accordingly by virtue of the said formula, the Learned

Arbitrator has granted escalation.

32. Mr. Sen submitted that the factual finding as held by the Learned

Arbitrator it was not open to challenge and the findings are not

contrary to the fundamental policy of Indian Law. He relied upon the

Judgment reported in (2015) 3 SCC 49 (Associate Builders vs. Delhi

Development Authority) and submitted that when a Court is applying

the "public policy" test to an arbitral award, it does not act as a Court

of appeal and consequently errors of facts cannot be corrected. A

possible view by the arbitrator on factsis necessarily to pass muster as

the arbitrator is the ultimate master of quantity and quality of evidence

to be relied upon when he delivers his arbitral award.

33. Mr. Sen submitted that relying upon the judgment reported in 2017 (5)

CHN 221 (DB) (State of West Bengal vs. Pam Developments Private

Limited) and submitted that in the said case also by which the claim of

escalation was allowed in the face of no damage clause was not

interfered with by the Hon'ble Supreme Court.

34. Mr. Sen further relied upon the judgment reported in (2007) 13 SCC

43 (K.N. Sathyapalan (Dead) by Lrs. vs. State of Kerala & Anr.)

and the judgment reported in (2008) 16 SCC 128 (Associated

Construction vs. Pawanhans Helicopters Limited).

35. Clause 1 (b) (ii) :

For the value of work above Rs. 10.00 lakhs -

Ernest money deposited shall be converted into security deposit at the

time of execution of agreement in case of successful tenderer and a

further amount is to be deposited at the time of execution of agreement

to total S.D. @ 2%.

The security deposit will be refunded to the party immediately after

payment of Final Bill.

Clause 1 (c) :

Another 8 % will be deducted as Retention Money progressively from R.A.

Bills at the time of passing of the bills contractors. The Retention Money

is not to be released before one year from the date of completion of the

work and subject to issuing of satisfactory reports by the concerned

department.

Clause 7 :

No payment shall be made for works estimated to cost less than ten

thousand rupees, till after the whole of the works shall have been

completed and certificate of completion given. But in the case of works

estimated to cost more than ten thousand rupees, the Contractor shall

on submitting the bill therefor, be entitled to receive monthly payment

proportionate to the part thereof, then approved and passed by the

Engineer-in-Charge whose certificate passing of the sum so payable shall

be finaland conclusive against the Contractor. But all such intermediate

payments shall regarded as payments by way of advance against the final

payment only and not as payment for work actually done and completed,

and shall not preclude the requiring of bad, unsound and imperfect or

unskillful work to be removed and taken away and reconstructed or re-

erected, or be considered as an admission of the due performance of the

contract, or any part thereof. In any respect of and reconstructed, or re-

erected or be considered as an admission of the due performance of the

contract, or any part thereof. In any respect of the accruing of any claim,

nor shall it calculated, determine or affect in any way the powers of the

Engineer-in-Charge under these conditions or any of them as to the final

settlement or adjustment of the accounts otherwise or in any other way

vary or affect the contract. The final bill shall be submitted by the

Contractor within one month of the date fixed for completion of the work,

otherwise the Engineer-in-charge's certificate of the measurement and of

the total amount payable for the work accordingly shall be final and

binding on all parties.

Clause 8 :

A bill regarding works executed in the previous month shall be submitted

by the Contractor in each month on or before the date fixed by the

Engineer-in-Charge, and the Engineer-in-Charge shall take or cause to

be taken the requisite measurement for the purpose of having the same

verified and the claim as far as admissible adjusted, if possible, before

the expiry of ten days from the presentation of the bill. If the Contractor

does not submit the bill within the time fixed as aforesaid, the Engineer-

in-Charge may depute a subordinate to measure up the said work in the

presence of the Contractor whose counter-signature to the measurement

list will be sufficient warrant ; and the Engineer-in-charge may prepare a

bill from such list which shall be binding on the Contractor in all

respects.

Bills to be on printed forms.

Clause 21 :

Work Programme :

The contractor shall have to submit within three days from the written

order to commence work a detailed time schedule for completion of the

works in all respect to the Engineer-in-Charge. The time schedule

approved by the Engineer-in-charge will form the work programme for

the work and shall be binding on the contractor. The work programme

shall no violate the provision of clause-2 of the printed tender form in any

way and prepared in conformity with the condition laid down in clause-2

of the printed tender form and the contractor must maintain the progress

of work in accordance with the work programme. Failure to maintain the

progress of work and completion thereof in accordance with the work

programme will tender the contractor liable to action as laid down to

contract agreement.

Special condition for price contingency of materials and labour

Price escalation or de-escalation will be applicable on tendered

amount for the quantum of the work actually executed on the basis of

the quoted rate as per formula below separately for materials and labour.

The formula is based on consumer price index number of the Reserve

Bank of India Bulletin published periodically. No other formula or

method or calculation will be acceptable.

The escalation or de-escalation will be applicable from the

commencement of the work and will remain valid for the entire period

work in including extended period if any, which extension has been

granted for valid reasons like force majure and or any delay on the part of

the Calcutta Municipal Corporation. Escalation will not however be

allowed if the work is delayed for the fault of the Contractor, even though

extension might have been granted. De-escalation during the period if

any, will however be applicable.

The total escalation cost permissible, calculated on the basis of

formula, will be subject to a maximum limitation of 5 p.c. of the tendered

amount for the quantum of the work actually executed.

Formula for Escalation/De-escalation

(a) Materials :

         vm               =        (0.60W-Md) x Im- Imo
                                                    Imo
        Where             =        Escalation/de-escalation on account of
                                   variation of price of materials.
          W               =        Total gross value of the work done at
                                   tendered rate.
         Md               =        Value of the materials issued by the
                                   Deptt. At fixed price.
                                   Or
                                   Value or materials prevailing at the time
                                   of submission of tender.
          Im              =        Wholesale price index number for all
                                   commodities as ruling during the period
                                   under consideration as published in the
                                   Reserve Bank of India Bulletin.
         Imo              =        Wholesale price index number for all
                                   commodities ruling in the month of
                                   submitting Tender as published in the
                                   Reserve Bank of India Bulletin.

  (b) Labour

          VL                                   0.25w x IL - Ilo
                                   IL
        Where             =



        VL                     Escalation de-escalation on account of
                               variation of price of Labour.




        W               =      Total gross value of the work done at
                               tendered rate.
        IL              =      Consumer price index No. for industrial
                               workers applicable for Calcutta Region
                               as ruling during the period under
                               consideration as published in the
                               Reserve Bank of India Bulletin.
        IL              =      Consumer price index number. for
                               industrial   workers     applicable    for
                               Calcutta Region as ruling in the month
                               of submitting Tender as published in the
                               Reserve Bank of India Bulletin.
        (C)                    Provided that, recovery of materials used
                               less or in excess as indicated in
                               paragraphs (a) and (b) of the sub-clause
                               shall be subject to the decision of the
                               Dy. Chief Engineer (P&D) who may allow
                               variation according to Statement III.


ESCALLATION OF RATE BEYOND STIPULATED TIME PERIOD

If for no fault of the Contractor work is required to be executed beyond

stipulated time period for a period of two years, contractor will execute

the work in the extended period at escalated rate as per Reserve Bank

of India Formula given in this schedule.

Statement-III

Consumption of different materials of construction in the corresponding

contract item of Tender shall be computed on the basis of the

quantities shown in the Calcutta Municipal Corporation schedule of

rates, subject to a variation of plus/minus five percent except in case

of steel materials in respect of which the variation shall be 10%. Where,

however, the circumstances of work so require, the Dy. Chief Engineer,

(P&D) shall be competent to allow (for recorded reasons) for a greater

variation.

36. According to Mr. Kar, Learned Senior Advocate the claims made in the

suit are also barred by limitation on the date of Learned Arbitrator

entered into arbitration. As per the submission, the suit is governed by

Article 18 of the Limitation Act which provides a limitation of three

years from the date when the work was completed. He submits that the

work was completed on 31st July, 1999 and thus the dates of filing of

writ petition as well as the civil suit were barred by limitation. As per

record, the work was completed on 31st July, 1999 and the respondent

submitted his 3rd Running Account and Final Bill dated 16th

September, 1999 which was accepted by the petitioner on 20th

September, 1999 and thus the period of three years would lapse on 19th

September, 2002 but the respondent had filed writ petition claiming the

said amount on 6th September, 2002 i.e. 15 days before the limitation

could expire and after disposal of the writ petition on 26th August, 2009

immediately within 5 days, the respondent has filed the suit on

1stSeptember, 2009 and thus this Court does not find any delay of the

claim raised by the respondent.

37. As regard additional claims being Category-A and Category-C of the

Statement of Claim, the Hon'ble High Court by an order dated 5th April,

2011 had appointed a Sole Arbitrator to decide the disputes and

differences between the parties in relation to and/or arising out of one

contract dated 27th August, 1997 entered between the parties. The

relevant portion of the order dated 5th April, 2011 reads as follows :

"An agreement has been entered into today between the parties by which they have decided to refer the matters covered by the suit to arbitration in accordance with the provisions of the Arbitration and Conciliation Act, 1996. The agreement records the name of the Arbitrator ... Accordingly, C.S. No. 255 of 2009 and all interlocutory applications therein, including G.A. No. 3173 of 2009, has been disposed of by referring the disputes covered thereby to arbitration in accordance with the agreement filed in Court today."

The High Court has appointed Arbitrator on the basis of the agreement

entered between the parties on 5th April, 2011 and the relevant portion

of the agreement reads as follows :

"The parties abovenamed do hereby resolve and agree to settle the disputes between them arising out of and in connection with the said work order dated July 24, 1997 for the work of renovation of the said existing 7 mg. Semi underground reservoir at Tallah and also the disputes and differences in respect of and/or in relation to and/or arising out of the said agreement dated August 27, 1997 being claims of the plaintiff and Counter-Claims, if any, of the defendant in the said C.S. No. 255 of 2009 referred to above through arbitration in accordance with the provisions of the Arbitration and Conciliation Act, 1996. By consent of parties, Mr. Arijit Banerjee, Barrister-at-Law of premises No. 1/1B, Deodar Street, Kolkata - 700 019."

The respondent being the claimant before the Arbitrator has set up

three claims in three categories as Categories - A, B & C which reads as

follows :

"PARTICULARS

1. Loss of profit as per Schedule-I of the letter dated May 4, 2011 .............. Rs. 37,73,952.00

2. Offsite and onsite expenses as per Schedule-II of the letter dated May 4, 2011 .............. Rs. 37,73,952.00

3. Costs as per Schedule-III of the letter dated May 4, 2011...........Rs, 5,40,692.00

Sub Total Rs. 80,88,596.00

4. Interest @18% per annum on the due amount of Rs. 80,88,596.00 from August 01, 1999 to April 05, 2011 as per Schedule-IV of the letter dated 5th April, 2011 ...... Rs. 1,70,16,633.00

5. Interest @18% per annum on the due amount of Rs. 80,88,596.00 from April 6, 2011 to May 17, 2011 (Rs. 80,88,596/- X 0.18 X 42 days/365 days) ..... Rs. 1,67,534.00

6. Loss of reputation on the ground of illegal black-listing Rs. 1,00,00,000.00

Sub Total (A): Rs. 3,52,72,763.00

Particulars of the dues as claimed in the suit

1. Principal amount of second running account bill

...................... Rs. 1,95,02,287.00

Less paid vide cheque No. 988502 dt. 7.5.1999

Rs. 50,00,000.00

Rs. 1,45,02,287.00

2. Principal amount of third running account & final bill ............................................... Rs, 40,51,347.81

3. Escalation Bill .......... Rs. 31,81,630.15

4. Retention Money........Rs. 16,67,233.00

5. Refund of security deposit and earnest money Deposit Rs. 2,34,478.00 Rs. 91,34,689.00

Sub Total: Rs. 2,36,36,976.00

6. Interest for delayed payment against first running Account bill @18% from 01.03.1998 to 16.07.1998 = 138 days on Rs. 1,36,00,000.00 (Rs. 1,36,00,000.00 X 0.18 X 138 days/365 days) Rs. 9,25,545.00

7. Interest for delayed payment against second Running account bill @18% from 01.09.1998 to 07.05.1999 = 249 days on Rs. 1,95,02,287.00 ..... Rs. 23,94, 774.00

8. Interest for delayed payment against second running account bill @18% from 08.05.1999 to 19.09.1999 = 135 days on Rs. 1,45,02,287.00 (Rs. 1,45,02,287 x 0.18 x 135 days/365 days) Rs. 9,65,495.00

9. Interest for delayed payment against second and third running account and final bill @18% from 20.09.1999 to 31.08.2009 = 3634 days on Rs. 2,36,36,976.00 (Rs. 2,36,36,976 X 0.18 X 3634 days/365 days) Rs. 4,23,60,051.00

Sub Total (B) Rs. 7,02,82,841.00

10. Interest for delayed payment against second and third running account and final bill @18% from 01.09.2009 to 17.05.2011 = 624 days on Rs. 2,36,36,976.00

(Rs. 2,36,36,976 X 0.18 X 624 days/365 days) Sub Total (C)

Rs. 72,73,713.00 Grand Total (sub total A+B+C): Rs. 11,28,29,317.00"

The Arbitration Agreement envisaged of all disputes between the parties

arising out of and in connection with the said work order dated 24th

July, 1997 and also the dispute and differences in respect of and/or in

relation to and/or arising out of the agreement dated 27th August, 1997

being the claims of the plaintiff and counter claims, if any of the

defendant in CS No. 255 of 2009 referred to the arbitration. Combined

reading of the agreement entered between the parties during the

pendency of the suit includes the claims and counterclaims of the suit,

work order and the agreement entered between the parties with respect

of the said work order. The disputes arose between the parties with

respect of the payment of the work executed by the respondent.

Initially, the respondent has filed writ petition and as per the liberty

given by the Writ Court, the respondent has filed civil suit and during

the pendency of the civil suit, the petitioner agreed for arbitration and

entered into an arbitration agreement. The Learned Arbitrator

considered the whole aspect of the matter when the petitioner has

raised the issue with regard to the maintainability of Claims A & C of

the respondent and the Learned Arbitrator had rejected the objection

raised by the petitioner and proceeded with the Arbitration. In the case

of Associate Builders (supra), the Hon'ble Supreme Court has

categorically held that a Court does not sit in appeal over the award of

an Arbitral Tribunal by reassessing or re-appreciating the evidence. The

award can be challenged only under the grounds mentioned in Section

34 (2) of the Act. In the present case, the Arbitrator after hearing of the

parties and after appreciating the relevant orders and documents held

that the claims made by respondent with respect of Claim A and Claim

C are arbitrable and thus this Court does not find any infirmity to

interfere with the finding of the Arbitrator.

38. As regard the escalation, the same has been provided in the agreement

itself in Clause 21 of the additional condition of the agreement and the

formula has also prescribed. The Learned Sole Arbitrator while deciding

the claim of escalation has adopted the method as prescribed in the

agreement. The said clause specified that the total escalation cost as

permissible or calculated on the basis of the formula mentioned

therein, will be subject to maximum limitation of 5 p.c of the tender

amount for the quantum of work actually executed. The Learned

Arbitrator taking into consideration of the said clause has passed the

award and as such this Court does not find any infirmity with regard to

the award passed by the Arbitrator on account of escalation.

39. As regard refund of security deposit and earnest money admittedly the

respondent has deposited a sum of Rs. 1,10,751/- as earnest money

with the petitioner by way of cheque at the time of submitting the

tender form and admittedly the respondent has completed the work

tothe satisfaction of the petitioner and inspite of completion of the

work, the petitioner has not released the said amount in favour of the

respondent and thus the Learned Arbitrator has rightly awarded the

said amount in favour of the respondent.

40. As regard the cost, the Learned Arbitrator has categorically held that

the petitioner has not released the payment of the respondent inspite of

completion of the work and the petitioner has approached the writ

Court, subsequently, the Civil Court and also in the arbitration

proceeding and thus this Court does not find any illegality for awarding

the said cost.

41. In view of the above, this Court does not find any illegality to interfere

with the award passed by the Learned Arbitrator dated 22nd September,

2014. Accordingly, AP 1985 of 2014 is thus dismissed.

Parties shall be entitled to act on the basis of a server copy of

the Judgment placed on the official website of the Court.

Urgent Xerox certified photocopies of this Judgment, if applied

for, be given to the parties upon compliance of the requisite

formalities.

(Krishna Rao, J.)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter