Citation : 2023 Latest Caselaw 1501 Cal/2
Judgement Date : 5 July, 2023
In the High Court at Calcutta
Constitutional Writ Jurisdiction
Original Side
The Hon'ble Justice Sabyasachi Bhattacharyya
WPO No. 2335 of 2022
Pearl Corporation
Vs.
West Bengal Police Housing and Infrastructure Development
Corporation Ltd. (WBPHIDCL) and others
For the petitioner : Mr. Tapas Dutta, Adv.,
Mr. M. Halder, Adv.
For the respondents : Mr. Kishore Datta, Sr. Adv.,
Mr. Sayan Sinha, Adv., Mr. Adil Naseer, Adv., Mr. Steven S. Biswas, Adv., Mr. Soham Kumar, Adv.
Hearing concluded on : 15.06.2023
Judgment on : 05.07.2023
The Court:-
1. The petitioner has challenged the termination of the petitioner and
debarment from participating in the respondents‟ contracts for two
years.
2. Learned counsel for the petitioner submits that the respondents have
acted mala fide and arbitrarily. During pendency of a previous writ
petition by the petitioner, against the alleged mala fide action of the
respondents‟, the respondents terminated the petitioner‟s contract.
The previous writ petition thus became infructuous and the same was
withdrawn with liberty to file a fresh writ petition on the subsequent
cause of action. Accordingly, the present writ petition was filed but
during the pendency of the same, the remaining work has been given
to a third party.
3. It is argued that the petitioner had substantially done the work under
the contract between the parties and, if another extension was given,
it would have completed the entire work.
4. It is argued that the petitioner was granted extension twice. As such,
time was not the essence of the contract even as per the conduct of
the respondents.
5. It is next argued that the termination of contract by the respondents
was de hors the contract entered into between the parties.
6. Learned counsel places reliance on Clause 2D of the Conditions of
Contract which contemplates that the contractor shall be liable to pay
compensation if, during review of progress of work as per sub-clause
C of Clause 2, it is found that the progress is falling behind schedule
as given in the Approved Work Programme, and after the respondents
intimating the contractor to expedite the work to achieve the progress.
7. Under sub-clause C, it is submitted that the contractor is to ensure
good progress during the execution of the work in all cases in which
the time allowed for any work exceeds one month after the Approved
Work Programme. In the event of any shortfall in performance
measured against the said programme, a penalty has been stipulated
in the said Clause.
8. It is argued that the stipulation in the contract speaks about levy of
compensation on the petitioner and, as per Clause 3, if the liability to
pay compensation amounts to the whole of his security deposit, only
then the question of termination of contract arises.
9. In the absence of any such allegation, the termination is bad.
10. It is further argued that, in any event, since the petitioner was on the
verge of completion of the work, it would be beneficial for all
concerned if the petitioner was given a further opportunity to complete
the work, instead of awarding the balance work to a third party.
11. It is argued that although extension of time was given till June 4,
2022, before the expiry of the same, that is, on March 29, 2022, the
termination was effected.
12. Hence, the said termination is vitiated due to violation of the
principles of natural justice as well as is in contravention of law and
the contract between the parties.
13. No proper reason of termination was given by the respondents.
Further, it is argued by the petitioner that no opportunity of hearing
was given to the petitioner, nor was any show-cause notice issued
prior to blacklisting the petitioner. Hence, the termination and the
blacklisting ought to be set aside.
14. Learned counsel for the petitioner places reliance on a judgment of the
Supreme Court reported at (2018) 6 SCC 157 [Madhya Pradesh Power
Management Company Limited Vs. Renew Clean Energy Private Limited
and another]. Placing particular reliance on paragraphs 13 and 14 of
the same, it is argued that if the contract permits imposition of
penalty, the contractor is liable to pay penalty. But the action of
termination of the contract was held arbitrary and to have been rightly
set aside by the High Court in the said case. Accordingly, in the said
case, the Supreme Court awarded penalty and set aside the
termination.
15. Learned senior counsel appearing for the respondent-Authorities
controverts the petitioner‟s submissions and argues that upon an
inspection held immediately prior to the termination, it was seen that
work only up to about 27.23 per cent had been done by the petitioner.
Since the work schedule provided for specific components of the work
to be done by phases, it was evident that the petitioner was far behind
the schedule and it would be impossible for the petitioner to conclude
the work within the last date as per the extension lastly granted.
16. It is argued that the petitioner was given several chances to conclude
the work, over two years from 2020 to 2022. However, despite the
same, the petitioner failed to complete the work on each occasion. It
is only out of grace that the respondents did not impose any penalty
on the petitioner, although under the contract, it was permissible for
the respondents to do so.
17. It is submitted that there was no arbitrariness in the termination.
Rather, the debarment was within the discretion of the respondent-
Authorities, in view of the palpable inefficiency and negligence of the
petitioner.
18. In view of the urgency of the nature of the work, the respondents had
to assign the balance work to a third party for the purpose of
completion of the same on expeditious basis.
19. Learned senior counsel appearing for the respondents cites M.P. Power
Management Company Limited, Jabalpur Vs. Sky Power Southeast
Solar India Private Limited and others, reported at (2023) 2 SCC 703.
It is submitted on the basis of the said judgment that normally the
courts would not exercise their discretion to examine issues unless
the action has some public law character attached to it. In the
present case, the matter relates to a private contract between the
petitioner and the respondent-Authorities.
20. It is further argued that when it comes to a challenge to the
termination of contract by the State, which is a non-statutory body,
the action being in purported exercise of the powers/rights under a
contract, it would be oversimplifying a complex issue to lay down any
inflexible rule in favour of the court turning away the petitioner to
alternate fora. However, ordinarily, the cases of termination of
contract by the State, acting within its contractual domain, may not
lend itself for appropriate redress by the writ court. This is
undoubtedly so if the court is duty-bound to arrive at findings which
involve untying knots, which are presented by disputed questions of
fact.
21. Learned senior counsel also places reliance on Joshi Technologies
Internationals INC. Vs. Union of India and others, reported at (2005) 7
SCC 728, wherein it was held that if the rights are purely of private
character, no mandamus can be issued. Even if the respondent is
"State", the other condition which has to be satisfied for issuance of
such a writ is the public duty. In a matter of private character of
purely contractual field, no such public duty element is involved and,
thus, mandamus will not lie. It was further observed that if there are
very serious disputed questions of fact which are of complex nature
and require oral evidence for their determination, the court would not
normally exercise its discretion in interfering with the same. Even in
cases where the question is of choice or consideration of competing
claims before entering into the field of contract, facts have to be
investigated and found before the question of a violation of Article 14
of the Constitution could arise. If those facts are disputed and require
assessment of evidence, the correctness of which can only be tested
satisfactorily by taking detailed evidence, involving examination and
cross-examination of witnesses, the case could not be conveniently or
satisfactorily decided in proceedings under Article 226 of the
Constitution. It was held that in such cases, the court can direct the
aggrieved party to resort to the alternative remedy of civil suit, etc.
22. Upon hearing learned counsel for the parties, a perusal of the
conditions of the contract becomes necessary.
23. The only specific provision as to termination of the contract is
stipulated in Clause 2B of the Conditions of Contract. The said sub-
clause stipulates that in the event of failure to start the work after 15
days from commencement of the work as per the Work Order due to
the contractor‟s fault, a notice is to be issued to the contractor giving
further 7 days to start the work. If the contactor fails to start even
within the extended period, the contract will be terminated without
giving any further notice. In the event of termination of contract
under the said Clause, the earnest money deposited would be forfeited
and the contractor would be barred from applying in any tender of the
Corporation for 2 years from the date of termination of the contract.
24. However, Clause 2B was never resorted to or referred to in any of the
correspondences by the respondent-Authorities, not even in the letter
of termination and debarment.
25. Sub-clause D is, in turn, dependent on sub-clause C, since it
stipulates that during any review of progress of work as mentioned on
sub-clause C, if it is found that the progress is falling behind schedule
as given in the Approved Work Programme, the contractor would be
intimated to expedite the work to achieve the progress with the
Approved Work Programme. In the next review of progress, if the
progress still fell behind the schedule, the contractor would be liable
to pay compensation of 2 per cent or such smaller amount as the
Managing Director may decide.
26. Sub-clause C stipulates that the contractor shall ensure good progress
and shall be bound, where the time allowed for work exceeds one
month, by the Approved Work Programme. In the event of shortfall in
performance measured against the said Programme, an amount at the
rate of 1 per cent of the tendered amount can be retained as penalty
from the successive bill. During the subsequent review, if it is found
that the previous delay has been recouped, the retained penalty
amount may also be refunded.
27. In the present case, as admitted in the impugned termination letter
dated March 29, 2022, no penalty was imposed on the petitioner
under Clause 2C. Although the respondents cite "good gesture" as the
reason for non-imposition of penalty, the same does not justify such
non-imposition. In fact, there is nothing on record to deduce that the
same was merely good gesture, since the non-imposition of penalty
may very well be interpreted also to mean that the petitioner was
either not liable to pay penalty, since it had no fault of its own in the
delay, or even that it had recouped the delay in execution, leading to
refund of the penalty or adjustment of the same. In any event, a
conclusion on such score would have to be based merely on
conjecture. The fact remains that, admittedly, no penalty was
imposed. As such, there did not arise any occasion to invoke sub-
clause C of Clause 2 at all. As a result, sub-clause D does not come
into the picture at all.
28. Taking the worst case scenario against the petitioner, an initial default
under Clause 2C might have led to steps being taken under Clause
2D. However, the maximum step which could be taken under sub-
clause D was imposition of compensation of 2 per cent or smaller
amount, as may be decided by the MD, of the tendered cost of the
whole work for every week that the due quantity of work as per
Approved Work Programmed remains incomplete.
29. Again, sub-clause E of Clause 2 provides that the work shall be
executed throughout the stipulated period of contract with all due
diligence. In the event of the contractor failing to do so, he shall be
liable to pay as compensation an amount equal to 2 per cent or
smaller amount as may be decided by the MD.
30. The sub-clause thereafter states that the entire amount of
compensation to be paid under the provision of Clause 2 shall not
exceed 10 per cent of the tendered amount of the work.
31. Thus, nothing in Clause 2D, which has been cited in the termination
letter, could invite the ultimate action of terminating the contract of
the petitioner.
32. It is important to note that Clause 3 of the Conditions of Contract
(which has never been mentioned by the respondents in the
Termination Letter) provides that where, under any Clause of the
Contract, the contractor shall have rendered himself liable to pay
compensation amounting to the whole of his security deposit, the
Managing Director or his authorized representative shall have the
power to adopt the courses given thereunder. Under Clause (a), one of
such sanctions is to rescind the contract, in which case the security
deposit of the contractor shall stand forfeited and be absolutely at the
disposal of the Managing Director or his representative.
33. However, the termination letter impugned in the present writ petition,
dated March 29, 2022, shows that the same was issued not by the
Managing Director but by the Executive Engineer (Zone-VII). As such,
the said termination letter itself was vitiated by lack of authority.
34. Even if it is construed that the Executive Engineer was duly
authorized by the Managing Director, upon a consideration of the
same, it is seen that the respondents have cited therein penal action
under Clause 2D. However, there is nothing in Clause 2D to attract
the ultimate punishments of termination and debarment.
35. Hence, the termination effected by the impugned Communication
dated March 29, 2022 is palpably de hors the contract.
36. That apart, the same also violates natural justice, since as per the last
Revised Work Schedule, annexed at page 89 of the writ petition, the
last date of completion of the contract was June 4, 2022, much before
which the impugned termination was effected.
37. The argument that the petitioner had failed to complete even the
initial phase of work schedule is not germane, since there is no
provision in the contract for termination of contract if each phase was
not completed within time.
38. Although the respondents have alleged that the petitioner had failed
even on March 29, 2022 to complete the component of the Work
Schedule which was stipulated to be done by March 29, 2022, the
Work Schedule itself shows that the first element of the activities to be
done by the petitioner was 3rd Floor Tiles Rectification Work, which
was to be completed by March 30, 2022. Notably, the termination
letter was issued even prior to March 30, 2022, that is on March 29,
2022. That apart, the respondents have stated in the second
paragraph of the termination letter that during inspection on the site
on March 28, 2022 by the concerned Assistant Engineer, it was found
that only rectification work at 3rd Floor Toilet had been taken up by
dismantling 3rd Floor Toilet Wall Tiles and using two number of
„Santras‟.
39. A bare perusal at the Revised Work Schedule shows that the activity
with regard to 3rd Floor comprises of as many as five elements. The
first, that is, Tiles Rectification Work was to be done by March 30,
2022. The second, that is, Plaster Rectification Work was to be
completed by April 1, 2022, the third, that is, Primer-Paint Work was
to be concluded within April 15, 2022; thereafter the fourth
component, that is, External Repairing Work, by April 25, 2022 and
the fifth component, that is, External Primer-Paint Work was to be
done by May 25, 2022. Hence, the termination, about two and half
months prior to the end of the work, was palpably illegal and
unlawful. The mere allegation, that an inspection of the site on March
28, 2022 (which was two days prior to the date of completion of even
the first phase of the extended work schedule) showed that the 3rd
Floor Toilet Work was being taken up by the petitioner, does not
provide any ground to the respondents to terminate the contract all on
a sudden.
40. Mere previous delay of the petitioner, in the absence of anything else,
is not sufficient to attribute fault for such delay solely on the
petitioner, particularly since the respondents themselves had gone on
extending time on several occasions, admittedly without imposing
penalty as provided for in the contract.
41. On a more serious footing, the respondents also debarred the
petitioner from participating in any procurement process under the
West Police Housing and Infrastructure Development Corporation
Limited for the next two years. Such debarment tantamounts to
blacklisting. It has been held time and again in several judgments of
the Supreme Court and different High Courts that blacklisting cannot
be effected without giving prior opportunity of hearing/show cause to
the contractor.
42. Since, in the present case, the only provision of blacklisting is found
in Clause 3(a), in the absence of any allegation of the satisfaction of
the conditions of Clause 3, that is, the whole of the security deposit
having become equal to the liability of compensation to be paid by the
petitioner, such blacklisting is palpably de hors the contract.
43. In fact, Clause 3(a) merely confers power on the respondents to
terminate the contract and not to debar the contractor. The sole
provision of debarment is found in Clause 2B of the contract.
However, it was too late in the day for the respondents to resort to
Clause 2B, since there is no allegation at all that the petitioner failed
to start work after 15 days from the date of commencement of the
work. In fact, the work had progressed over two years after the date of
commencement, and, as such, Clause 2B had not or could not be
invoked by the respondents at all.
44. Hence, the obvious conclusion is that the debarment took place de
hors the provisions of the contract.
45. Although it cannot be denied that an employer may, under certain
circumstances, being so dissatisfied with a contractor on serious
grounds that the employer does not want to continue with the said
contractor, blacklist him; however, in such cases, it is the well-settled
position of law that a Show-Cause Notice has to be issued to the
contractor and the allegedly recalcitrant contractor has to be given an
opportunity of hearing before passing an order of debarment. In the
present case, none of such modalities have been resorted to by the
respondents, thereby palpably vitiating and rendering arbitrary the
action of the respondents in issuing the termination and debarment
letter to the petitioner.
46. As such, the termination of contract and debarment of the petitioner
by the respondents vide communication dated March 29, 2022 and
the follow-up action of the respondents in awarding the balance work
to a third party are tainted and vitiated by contravention of law,
natural justice and the terms of the contract.
47. Insofar as the scope of interference of this Court under Article 226 of
the Constitution is concerned, in view of the above discussions, it is
well-settled in law that the respondent-Authorities, which come within
the purview of „State‟ as contemplated in Article 12 of the
Constitution, have a higher responsibility than an ordinary employer
to be transparent, follow natural justice and give a free play to fair
play in all its actions. Let alone being transparent, the impugned
action here was palpably arbitrary and, as such, calls for interference
by this Court.
48. Insofar as the nature of the work is concerned, the urgency of the
same has been harped on by the respondents themselves all along.
The administrative authorities‟ repeated warning regarding alleged
slow pace of work has been cited even in the impugned termination
letter. Hence, there cannot be any doubt that the renovation and
upgradation of the head quarters of the traffic guard of Kolkata Police
assumes a public character, since the said Authorities discharge
public duties, for which the basic amenities pertaining to the work-in-
question are essentially and integrally in public interest.
49. Hence, the impugned termination and debarment are justiciable in a
judicial review.
50. However, in the present case, even if the termination and debarment
are set aside, the relief of the petitioner lies in damages, since the
remaining work has already been awarded to a third party and has, in
all probability, been concluded by it by now.
51. In such circumstances, WPO No.2335 of 2022 is allowed, thereby
setting aside the communication dated March 29, 2022 (Annexure P-
23 at page 91 of the writ petition), whereby the petitioner‟s contract
was terminated and the petitioner was debarred from participating in
any procurement process under the respondent no.1-Corporation for
the next two years. The petitioner will be at liberty to participate in all
such procurement processes in future, being undeterred by the
impugned communication dated March 29, 2022.
52. In view of the termination of contract being, thus, set aside, the
petitioner will be at liberty to approach the competent civil court
claiming appropriate damages for such illegal termination. For the
purpose of limitation for filling such suit, the commencement of such
limitation period shall be deemed to start from this day, since the
cause of action therefor ripens with this order.
53. It is made clear that although the termination and the debarment
have been set aside herein, this Court has not entered into the merits
of the quantum of the damages and compensation which is to be
awarded to the petitioner. Such consideration is left to the competent
civil court, if so approached by the petitioner, to be assessed by taking
detailed evidence and upon taking into consideration all factors
involved.
54. There will be no order as to costs.
55. Urgent certified server copies, if applied for, be issued to the parties
upon compliance of due formalities.
( Sabyasachi Bhattacharyya, J. )
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!