Citation : 2022 Latest Caselaw 2842 Cal/2
Judgement Date : 24 November, 2022
IN THE HIGH COURT AT CALCUTTA
Ordinary Original Civil Jurisdiction
Original Side
Present:
The Hon'ble Justice Shekhar B. Saraf
AP 537 of 2022
Rajinder Singh Walia And Anr.
VS
Nabanita Singh And Anr.
For the Petitioners : Mr. Debnath Ghosh, Adv.
Mr. Megnad Dutta, Adv.
Ms. Debanjana De, Adv.
For the Respondents : Mr. A.C. Kar, Sr. Adv.
Mr. T.K. Aich, Adv.
Last heard on: November 04, 2022
Judgment on: November 24, 2022
Shekhar B. Saraf, J.:
1. The petitioners in the instant application [being A.P. No. 537 of 2022]
under Section 9 of the Arbitration and Conciliation Act, 1996 [hereinafter
referred to as 'the Act'] are partners in a partnership firm under the name
of 'Kirat Construction', carrying on the business of developing properties.
2
2. The respondent no. 1 is the owner of the premises No. 2A, Hari Bose Lane,
Police Station - Burtolla, Kolkata 700016 measuring more or less 6
cottahs, 9 chittacks 25 sq. ft. [hereinafter referred to as 'the Premises'].
Respondent no. 2 is the husband of respondent no. 1.
3. The petitioners have preferred this application praying for injunction on
the Premises in the form of the following directions: (a) the respondents,
his men, servants, agents be restrained from dealing with disposing off,
alienating and/or creating any third party right, title or interest in the
Premises; (b) the respondents, his men, servants, agents be restrained
from giving effect or further effect to the cancellation and/or termination
notices dated July 9, 2021 and October 25, 2021; (c) the operation of the
notices dated July 9, 2021 and October 25, 2021 issued by respondent
no. 1 be stayed.
Relevant Facts
4. Respondent no. 1, being the absolute owner of the Premises, accompanied
by respondent no. 2, approached the petitioners for developing the
Premises.
5. The petitioners and respondent no. 1 entered into a development
agreement dated August 25, 2009 [hereinafter referred to as 'the
Agreement'] followed by a General Power of Attorney dated August 25,
2009 [hereinafter referred to as the 'GOA'].
6. The petitioners paid Rs. 65,00,000/- to the respondents via various
cheques in pursuance of the Agreement.
7. Since a tenant, by the name of Snighdha Jana [hereinafter referred to as
'the tenant'] was already residing at the said premises, a tripartite
agreement was entered into between the petitioners, tenant and
respondent no. 1 [hereinafter referred to as the 'tripartite agreement'], vide
which the tenant was promised a total of 2500 sq. ft. in the Premises after
development.
8. The petitioners spent a further amount of Rs. 24,15,000/- for developing
the Premises, Rs. 5,00,000/- for the tripartite agreement and Rs.
25,00,000/- on sanction plan for construction on the Premises.
9. The petitioners constructed some portions of the ground floor and first
floor of the building on the Premises. These facts are also confirmed by the
receiver's report which was taken on record vide order dated November 4,
2022.
10. The respondent no. 1 vide two notices dated July 9, 2022 and October 25,
2022 terminated the Agreement and the GOA [hereinafter referred to as
'termination notices']. The petitioners contested the termination vide two
notices dated August 12, 2021 and November 29, 2021.
11. The respondent no. 1 has stated in the termination notices that only Rs.
65,00,000/- were paid and substantial amounts due as per the Agreement
were remaining. Since substantial time has passed, termination had to be
effected. The respondent also deducted Rs. 15,00,000/- by way of
damages for suffering loss and mental agony and 25% of the total price
and offered a refund of Rs. 15,00,000/- to the petitioners.
The Submissions
12. It is pertinent now to state the arguments put forth by counsels of both sides.
13. Mr. Debnath Ghosh, learned Advocate, appearing on behalf of the
petitioners submitted the following arguments:
a) The petitioners have been ready and willing to perform their obligations
under the Agreement, except the obligations whose execution has been
waived and/or prevented by the respondents;
b) The petitioners have a right to specific performance of the contract and
despite thirteen years already having been passed since the execution
of the Agreement the right still subsists as time was not essence of the
contract. Reliance has been placed on N. Srinivasa v. Kuttukaran
Machine Tools Limited ([2009] 5 SCC 182) to substantiate the point
that there is a presumption in contracts relating to immovable property
that time is not the essence of the contract. Irrespective of this
contention, even after termination, the arbitration clause survives and
interim safeguards must be granted;
c) The petitioners have also placed reliance on Branch Manager, Magma
Leasing and Finance Limited and Another v. Potluri Madhavilata
and Another ([2009] 10 SCC 103) to argue that a right to take the
claim to arbitration subsists even if the contract comes to an end by its
termination;
d) The respondent No. 1 has entered into agreements with third parties,
which is evidence of mala fide intent and will subsequently frustrate
their rights, leading to irreparable loss.
14. Mr. A.C. Kar, Senior Advocate, appearing on behalf of the respondents
submitted the following arguments:
a) The petitioners reneged on their obligations by not paying the entire
amount and a substantial period of time has passed, therefore the
performance of the Agreement was barred and hence was terminated;
b) This court does not have jurisdiction under the Act as on account of
non-encashment of any cheque issued by the petitioner, the Agreement
under Clause 6, provides for refund after determination of costs and
expenses incurred by the petitioner for carrying on the construction
work. Such amounts have to be assessed by the Architects of the newly
appointed developer and respondent no. 1. Clause 6 supersedes the
arbitration clause since it is a prior clause. Reliance has been placed
on Ramkishorelal and Another v. Kamal Narayan (1963 Supp [2]
SCR 417) for the said proposition.
Issues
15. Upon analysing the arguments put forth by both the parties, I am of the
view that the following issues are required to be addressed by me to
resolve the disputes between the parties:
a) Whether this court can exercise power under the Act in light of the
arbitration clause?
b) If the answer to the former issue is in the affirmative, whether interim
relief should be granted as per Section 9 of the Act?
Analysis
16. Mr. A.C. Kar, Senior Advocate, appearing on behalf of the respondents
submitted that clause 6 supersedes the arbitration clause. The Apex
Court, in Ramkishorelal and Another (supra) held that where earlier
clauses make absolute disposition of property, latter clauses which limit
such disposition must be disregarded. However, the Court also avers that
attempts must be made to read the two parts of the document
harmoniously, if possible.
17. Mr. Debnath Ghosh, learned advocate appearing on behalf of the
petitioners relied upon judgements to impress upon this court that the
termination was dehors the contract for two reasons: (i) the contract does
not provide for deduction of amounts for mental agony and harassment
and (ii) time was not the essence of the contract. Reliance was placed on
N. Srinivasa (supra) and Branch Manager (supra).
18. The petitioners also contended that despite termination of the contract,
the dispute has to be referred to arbitration and interim relief should be
granted.
19. The relevant portion from Branch Manager (supra) is extracted below
wherein the Apex Court held:
"14. The statement of law expounded by Viscount Simon, L.C. in Heyman
[1942 AC 356 : (1942) 1 All ER 337 (HL)] as noticed above, in our view,
equally applies to the situation where the contract is terminated by one
party on account of the breach committed by the other particularly in a case
where the clause is framed in wide and general terms. Merely because the
contract has come to an end by its termination due to breach, the arbitration
clause does not get perished nor is rendered inoperative; rather it survives
for resolution of disputes arising "in respect of" or "with regard to" or
"under" the contract. This is in line with the earlier decisions of this Court,
particularly as laid down in Kishorilal Gupta [AIR 1959 SC 1362 : (1960) 1
SCR 493]"
20. The Apex Court's observations in N. Srinivasa (supra) are extracted
below:
"31. As noted herein earlier, one of the main issues for the purpose of
deciding the application for injunction was whether time was the essence of
the contract or not. By the impugned order, the High Court had failed to
appreciate that in the contract relating to immovable property, time cannot
[Ed.: The complete legal position as to time being of the essence in contracts
for sale of immovable property is stated in para 27.] be the essence of the
contract. In any event even in such a case the arbitration clause would
survive and the dispute would be required to be resolved. That being the
position, pending disposal of the arbitration proceeding, interim measure to
safeguard the interest was required to be taken."
Conclusion
21. Relevant clauses of the Agreement are extracted below for proper
determination of the said dispute:
"6. It may be mentioned that if any of the aforesaid cheques issued by the
Developer in favour of the owner and/or her nominated person namely
Arjun Singh upto the month of November is not encashed due to any reason
whatsoever then the owner shall be at liberty to stop the work and if within
15 days from the date of stop of work, the amount is not paid then the
owner shall be at liberty to complete the said work either by herself or by
deputing new constructor and in such event the owner shall refund the
money received today or to be received in the meantime from the Developer
herein after deducting 25% of the total sale price. The cost and expenses
incurred by the Developer in the meantime for carrying on the construction
work shall be paid by the owner after handing over the said project to any
new Developer. The amount of such expenses to be assessed by the
Architects of the Developer and the Owner engaged and/or to be engaged in
the said project"
"22. Any dispute arising as between the Owner and the Developer
regarding any matter in respect of the development of the said property
shall be referred to Arbitration as per provision of the law in this regard."
22. A harmonious understanding of the Agreement would lead to an inference
that while the expenses incurred may be assessed by the Architects, the
arbitration clause is not ousted. Such assessments can be submitted to
the arbitrator, but first the arbitrator has to decide on the validity of the
termination notices and contractual retractions of the parties.
23. Prima facie, I find that the contract was not one where time was of the
essence of the contract. Even if it were, it is a determination that the
arbitrator has to make. What is undisputed though is that there are
certain amounts deducted vide termination notices which are clearly not
contemplated in the Agreement. Thereafter, attempts have been made to
make commercial arrangements with third parties with respect to the said
premises. In my view, a prima facie case has been made out by the
petitioners with respect to validity of the arbitration clause and for
injunctive reliefs. Furthermore, balance of convenience is in favour of the
petitioner as development work has progressed and termination of the
same would lead to irreparable loss to the petitioners.
24. In light of the above, Issue No. 1 and Issue No. 2 are decided in the
affirmative. Interim reliefs are granted in terms of prayers (a), (b) and (c) of
the notice of motion. The interim orders shall continue for a period of 8
weeks from date or until further orders, whichever is earlier.
25. Accordingly, affidavit-in-opposition is to be filed within five weeks from the
date of this order and affidavit-in-reply, if any, two weeks thereafter.
26. Urgent Photostat certified copy of this order, if applied for, should be made
available to the parties upon compliance with the requisite formalities.
(Shekhar B. Saraf, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!